BLD-Final | 8/17/2016 | 8/17/2016 | 8/17/2016 | P | PASS |
Jim Storey
|
|
|
After 3 // Joseph Phone #: ###-####
|
Permanent Occupancy | | | 8/17/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/10/2016 | 8/11/2016 | 8/11/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, no fire alarm modifications, commercial cooking hood fire suppression system has current inspection tag with no modifications made to cooking appliances, fire extinguisher will be mounted in discussed location. Final life fire sfatey inspection passed/complete.
|
Permit Ready to Issue | | | 8/10/2016 | | DONE |
|
|
|
All Met
|
Print Occupancy Form | | | 8/10/2016 | | DONE |
|
|
|
|
Telephone call | | | 8/10/2016 | | DONE |
|
|
|
Spoke with Joseph informing him that this permit is ready to be picked up
|
Issue PAID IN FULL permit | | | 8/10/2016 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 8/5/2016 | 8/5/2016 | 8/9/2016 | | DONE |
David Ferguson
|
|
|
8/10 L2 SHOGUN SUSHI Occ Eval
|
Routing - PLAN CHECK | 8/8/2016 | | 8/9/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 8/9/2016 | | DONE |
David Ferguson
|
|
|
|
1st review completed | | | 8/9/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/9/2016 | | DONE |
|
|
|
|
Routing - FIRE | 8/5/2016 | 8/5/2016 | 8/8/2016 | | PASS |
Katie Marron
|
|
|
No comments. Final approval will be subject to satisfactory field inspection.
|
Plan assigned to (JG) | 8/4/2016 | 8/4/2016 | 8/5/2016 | | DEFR |
Javier Guzman
|
|
|
8/10 L2 SHOGUN SUSHI Occ Eval
|
Routing - PUBLIC WORKS | 8/4/2016 | | 8/4/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 8/4/2016 | | 8/4/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing PW Sewer Rating | 8/4/2016 | | 8/4/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Environmental | 8/4/2016 | | 8/4/2016 | | PASS |
Rick Christenson
|
|
|
Shared GI
|
Plans ACCEPTED BY PLAN CHECK | | | 8/4/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/4/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/4/2016 | | DONE |
|
|
|
|
First Notice | | 8/27/2016 | | | |
|
|
|
|
Application received | | 8/4/2016 | | | |
|
|
|
|