Information based on query as of Saturday, June 22, 2024.
Permit Information
Permit NumberBLD16-02870
StatusFinaled
Name ESI
Site Address 8256 W OVERLAND RD
Project NameWal-Mart Fueling Station
Customer Number 
ePlanReviewYes
Description
(WALMART FUELING STATION) //Plan Modification to fuel canopy. 11/14/16 JG// Permit to construct a new 1,499 sq., ft. mercantile building, a new 4,413 gas pump station canopy and related site improvements. (Note: In regards to the thermal envelope/lighting this building used the “Energy Cost Budget Method” under ASHRAE 90.1-2010 Section 11. see attached letter/report in small documents.) Scope of work includes: construction of a slab on grade concrete foundation, construction of 8” CMU exterior walls, roof construction, construction of interior non-bearing walls to create an equipment room, a sales area, two accessible restrooms and a new walk-in cooler, installation of new storefront windows and doors, new electrical, new mechanical, new plumbing, site work, and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. The building is not fire sprinklered. Special Inspections Required see form 310. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  6/20/2017 DONE
Third Notice 5/15/20176/12/2017 DONE
Mailed 6-13-17
Second Notice 4/21/20175/10/2017 DONE
sent in mail 5-11-17
First Notice 3/26/20174/11/2017 DONE
sent in mail 4-12-17
BLD-Final3/15/20173/16/20173/16/2017APASS
DetailsMike Jordan
Chris Phone #: ###-####. ok for perm occ.
Permanent Occupancy  3/16/2017 DONE
Zoning Approval3/15/20173/15/20173/15/2017 PASS
DetailsSarah Schafer
Final inspection approved. Will start release of Bond (BND17-00025)
FIRE-Final Inspection3/14/20173/14/20173/14/2017PPASS
DetailsTroy Cobbley
Life safety passed
PubWorks Occupancy Approval3/14/20173/14/20173/14/2017 DONE
DetailsTiffany Lowery
FIRE-Final Inspection3/6/20173/7/20173/7/2017APART
DetailsTroy Cobbley
A temporary is being given with the Boise Fire Dept. permission until the fire alarm permit has been finaled (need approved as-builts), and the correction items for the fire dept have been addressed which include the remaining sign at the remote emergency off switch, 6" curbing and the fuel pumps repaired.

Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Final3/6/20173/7/20173/7/2017PPART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Chris Palmer. Ok for temp occ. Will be ok for perm occ. once fire/life/safety signs perm. and the fire alarm signs perm.
Temporary Occupancy3/7/20176/5/20173/7/2017 DONE
DetailsChristina Prado
Zoning Approval Temp3/7/20173/7/20173/7/2017 PASS
DetailsSarah Schafer
Bond placed for landscape to be finished by the end of the week.
Print Occupancy Form  3/7/2017 DONE
FIRE-Final Inspection3/2/20173/2/20173/2/2017PFAIL
DetailsTroy Cobbley
Not ready for a final yet, I went over requirements with Chris such as needing the project related fire alarm permit addressed, remove the deadbolt on the beer cooler, need fire extinguisher for store, need verification of permiting through Fire Dept,, need verification Fire Dept is ok with the pumps/tanks and lack of 6" at the gas pumps, testing of the emergency off buttons, missing exit discharge lights....ect
BLD-Energy code compliance1/27/20171/27/20171/27/2017PPASS
DetailsMike Jordan
BLD-Energy code compliance1/26/20171/27/20171/27/2017ANR
DetailsMike Jordan
Wall insulation inspection. Late morning inspection, if at all possible. Thanks, Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in1/25/20171/26/20171/26/2017APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Chris Palmer. Interior steel stud framed walls, furred walls and hardlids ok.
CHANGE STATUS TO (ISS)  1/25/2017 DONE
DetailsChristina Prado
OVERRIDE  12/2/2016  
BLD-Footing12/1/201612/2/201612/2/2016ADEFR
DetailsMike Jordan
Grout at 9:15, Masonry rebar - Chris Phone #: ###-####. Special inspection.
Plan assigned to (JG)11/10/201611/10/201612/2/2016 PASS
DetailsJavier Guzman
1st review completed, Plan Mod, Wal-Mart Fueling Station
Routing Off Site - STRUCTURAL11/28/2016 12/2/2016 PASS
DetailsJavier Guzman
signed off in ePlan by Dave Haugland of AHJ Engineers
PLANS/APPL TAKEN TO FRONT DESK  12/2/2016 DONE
Permit Ready to Issue  12/2/2016 DONE
please do not re issue
BLD-Other11/30/201612/1/201612/1/2016PCANC
DetailsMike Jordan
Masonry rebar & re-grout, grouting at 1:45 - Chris Phone #: ###-####
BLD-Other11/29/201611/30/201611/30/2016ADEFR
DetailsMike Jordan
masonry grout at 8:30AM - Chris Phone #: ###-####.
BLD-Other11/23/201611/28/201611/28/2016APART
DetailsMike Jordan
masonary grout & rebar, scheduled for 1:15PM - Chris Phone #: ###-####. Work in progress, masonry exterior walls, FF to 4ft. elevation. Will have special inspection.
Routing - PLAN CHECK11/28/2016 11/28/2016 PASS
DetailsJavier Guzman
Routing Off Site - STRUCTURAL11/14/2016 11/21/2016 FAIL
DetailsJavier Guzman
Failed in ePlan by AHJ Engineers Dave Haugland
Routing - PLAN CHECK11/14/2016 11/17/2016 PASS
DetailsJavier Guzman
BLD-Other11/14/201611/14/201611/14/2016PPASS
DetailsMike Jordan
Rebar - Chris Phone #: ###-####. Column pad footings for fuel canopy.
Plan Modification Accepted  11/10/2016 DONE
Deferred submittal for canopy
BLD-Foundation11/8/201611/9/201611/9/2016APART
DetailsMike Jordan
Stem wall pour at the C-Store. Concrete is scheduled for 9AM. Please call me with any questions.
Thanks, Phone #: ###-#### Inspection requested via web by Chris Palmer. Work in progress, will have special inspection. Needs clean debrie from bottom of stemwall.
BLD-Footing11/2/201611/2/201611/2/2016PPART
DetailsMike Jordan
Perimeter footings for store portion. Work in progress. Will have special inspection.
BLD-Footing11/1/201611/2/201611/2/2016PCANC
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Justin Parrish
Print Occupancy Form  11/1/2016 DONE
Issue PAID IN FULL permit  11/1/2016 DONE
OVERRIDE  10/27/2016  
Plan assigned to (JG)9/20/20169/20/201610/27/2016 PASS
DetailsJavier Guzman
1st review completed, 10/17 New Wal-Mart Fuling Station ePlan
Routing PW Sewer Design10/27/2016 10/27/2016 PASS
DetailsMike Sheppard
Signed off in ePlan by Mike Shepard of PW
Routing - PLAN CHECK10/27/2016 10/27/2016 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  10/27/2016 DONE
Permit Ready to Issue  10/27/2016 DONE
***MET 11-1-16 CAN***Need ACHD, GC Form and Revised Cert of Value.
ESC permit is with Grading per Andy
Routing PW Environmental10/18/2016 10/25/2016 PASS
DetailsRick Christenson
Routing Off Site - STRUCTURAL10/18/2016 10/25/2016 PASS
DetailsJavier Guzman
signed off in ePlan by Dave Haugland of AHJ Engineers
Routing PW Sewer Design10/18/2016 10/25/2016 FAIL
DetailsMike Sheppard
Mike Shepard wrote in ePlan "The Civil plan does not indicate how new construction will be served for sewer requirement."
Routing - PLAN CHECK10/18/2016 10/21/2016 PASS
DetailsJavier Guzman
Routing - Design Review10/18/2016 10/18/2016 PASS
DetailsJosh Wilson
Routing PW Drainage10/18/2016 10/18/2016 PASS
DetailsBrian Murphy
Routing - PLUMBING10/18/2016 10/18/2016 PASS
DetailsBill VanDegrift
per plans and ISPC
Route to Impact Fee Review10/11/201610/14/201610/12/2016 PASS
DetailsCindy M. Gould
Routing Off Site - C.D.H10/8/2016 10/11/2016 PASS
DetailsJavier Guzman
Signed off in ePlan by Central District Health Department Brent Copes
1st review completed  10/11/2016 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK9/20/2016 10/11/2016 FAIL
DetailsJavier Guzman
Routing Off Site - STRUCTURAL9/20/2016 10/6/2016 FAIL
DetailsJavier Guzman
Failed in ePlan by AHJ Engineers Dave Haugland
Routing PW Environmental9/20/2016 10/6/2016 FAIL
DetailsRick Christenson
Failed in ePlan by Rick Christenson of PW Enviormental
Routing PW Sewer Design9/20/2016 10/3/2016 FAIL
DetailsMike Sheppard
Provide sewer connection plan.
Routing PW Drainage9/20/2016 9/30/2016 FAIL
DetailsBrian Murphy
need hydrocarbon filter, o and m and sign apdx j
Routing - Design Review9/30/2016 9/30/2016 PASS
DetailsJosh Wilson
Landscape plan uploaded with GRD16-00077.
Routing - PLANNING9/20/2016 9/29/2016 PASS
DetailsDavid Moser
Routing - PLANNING Land Div9/20/2016 9/26/2016 PASS
DetailsTodd Tucker
Routing - MECHANICAL9/20/2016 9/22/2016 PASS
DetailsTroy James
Routing PW Solid Waste9/20/2016 9/22/2016 PASS
DetailsEvan Carpenter
No new solid waste containers are proposed or approved.
Routing - PLUMBING9/20/2016 9/21/2016 FAIL
DetailsBill VanDegrift
1) 60" max. above finish floor for backflow preventers
2) provide civil plan for sewer and water services
Routing - Design Review9/20/2016 9/21/2016 FAIL
DetailsJosh Wilson
Upload site and landscape plans consistent with DRH16-00268.
Routing - Erosion and Sediment9/20/2016 9/21/2016 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

Proposed Wal-Mart Fueling Station, at existing Wal-Mart Super Center, site development and minor landscaping
Routing - FIRE9/20/20169/20/20169/20/2016 PASS
DetailsKatie Marron
Comments attached to case.
Routing - Addressing9/20/2016 9/20/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS9/20/2016 9/20/2016 PASS
DetailsRachael Beierle
Intake Approval  9/20/2016 PASS
Routing PW Sewer Rating9/20/2016 9/20/2016 PASS
DetailsBeverly Mountain
Intake Approval  9/13/2016 FAIL
DetailsJavier Guzman
Incomplete submittals will not be accepted: Previous request not completed to provide and upload the following - all plan sheets must be uploaded in “Landscape” format in the horizontal position per ePlan submittal standards http://pds.cityofboise.org/media/105041/electronicstandards.pdf
Plan Reviewer's activity  9/13/2016 DONE
DetailsJavier Guzman
Previous request to upload all plan sheets in the horizontal position not completed by applicant, i failed the project and sent it back to applicant to complete previous task
Intake Approval  8/11/2016 FAIL
DetailsJavier Guzman
Please provide and upload all the following documents or plans as required per the 502 checklist, Incomplete submittals will not be accepted:
1. Soils and geotech report for support of the structure stamped and signed by an Idaho licensed engineer or declare on plans the default seismic site class & soil bearing per IBC
2. Soils and geotech report for infiltration systems stamped and signed by an Idaho licensed civil engineer, geologist, or soil scientist
3. Verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff
4. Central District Health Department (CDHD) provide a completed Food Establishment License application
5. Central District Health Department (CDHD) provide a completed Food Establishment Plan Review and Approval form for any building where food is prepared, manufactured or stored.
6. Site specific fire flow at hydrants letter from Suez Water or other public water provider. Include static pressure if sprinklers are to be installed
7. Site Drainage Report stamped and signed by an Idaho licensed design professional including descriptive narrative and calculations
8. Drainage System Operation & Maintenance Plan stamped and signed by Idaho licensed design professional
9. Erosion & Sediment Control (ESC) Narrative. Narrative must be designed for the specific project, and be prepared and signed by a plan designer certified by Boise City.
10. Planning & Zoning letter(s) of approval i.e. Conditional Use Permit (CUP), Design Review Permit (DRH) and/or other approval documents
11. Recorded document (with instrument number) for all new and existing sewer easements
12. All plan sheets must be uploaded in “Landscape” format in the horizontal position per ePlan submittal standards
13. The checklist is not complete unless all
o information is filled out,
o all appropriate boxes are checked and
o all plan page numbers are listed.
14. Please upload any addition or missing plan sheets requested from the 502 checklist
15. Please download and fill out the newest version of the 502 checklist from our website at http://pds.cityofboise.org/home/documents/apps/500/
Application received  8/4/2016 DONE
Application submitted via PDS Online on Aug 4 2016 4:10PM