Letter of compliance/Occupancy | | | 1/4/2019 | | DONE |
|
|
|
|
BLD-Final | 11/15/2017 | 11/15/2017 | 11/15/2017 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 11/15/2017 | 11/15/2017 | 11/15/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Ceiling Grid Inspection | 11/15/2017 | 11/15/2017 | 11/15/2017 | P | CANC |
Jim Sly
|
|
|
Graciela Phone #: ###-####
|
BLD-Conference | 10/31/2017 | 11/1/2017 | 11/1/2017 | P | DONE |
Jim Sly
|
|
|
Please call ahead for access - Graciela Phone #: ###-####
|
BLD-Final | 10/23/2017 | 10/24/2017 | 10/24/2017 | P | NR |
Jim Sly
|
|
|
Graciela Phone #: ###-####
|
BLD-Foundation | 12/22/2016 | 12/23/2016 | 12/23/2016 | A | PASS |
Jim Sly
|
|
|
Call with question - Victor Phone #: ###-#### Talked with Contr. OK to pour as long as concrete is protected per ACI 306....Cold weather concrete Guidelines.
|
BLD-Footing | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | PASS |
Jim Sly
|
|
|
victor Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/18/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/17/2016 | | |
|
|
|
|
Telephone call | | | 11/17/2016 | | DONE |
|
|
|
notified customer that permit is ready
|
Routing - PLAN CHECK | 11/17/2016 | | 11/17/2016 | | PASS |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 11/17/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/17/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/17/2016 | | DONE |
|
|
|
all requirments met
|
Plan assigned to (LEG) Tisha | 8/8/2016 | | 11/17/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 8/12; MH on foundation (plan check/planning requirements)
|
Routing - PLANNING | 11/16/2016 | | 11/16/2016 | | PASS |
David Moser
|
|
|
Approved as redlined need paved parking space (min 16.5 feet x 20 feet) with a paved driveway that is 20 feet from edge of common drive. OK as per CVA16-00060 and CUP16-00079
|
Routing - PLAN CHECK | | | 8/12/2016 | | FAIL |
Tisha Gallop
|
|
|
called and left voicemail for applicant. Need further details about manufactured home such as year, and elevations to verify it meets enhanced manufactured home requirements.
No foundation review done per planning fail. Possible revisions might effect foundation plan.
|
1st review completed | | | 8/12/2016 | | FAIL |
Tisha Gallop
|
|
|
|
Telephone call | | | 8/12/2016 | | DONE |
|
|
|
spoke to Graciela. She said is 2006 MH and not multi-sectional.
|
Route to Impact Fee Review | | 8/11/2016 | 8/11/2016 | | PASS |
|
|
|
|
Routing - PLANNING | 8/9/2016 | | 8/11/2016 | | FAIL |
Jeff Lowe
|
|
|
dwelling does not appear to be multi-sectional
|
Routing - Addressing | 8/8/2016 | | 8/9/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 8/9/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/8/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/8/2016 | | DONE |
|
|
|
|
Application received | | 8/8/2016 | | | |
|
|
|
|