BLD-Final | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
DOC - Permit Finaled | 2/21/2017 | 2/21/2017 | 2/21/2017 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Energy code compliance | 10/25/2016 | 10/25/2016 | 10/25/2016 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Framing/Rough-in | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | FAIL |
Phil Shearer
|
|
|
I see that the plans were flipped will have corrected plan there in the am Phone #: ###-#### Inspection requested via web by Marty Pieroni
|
BLD-Framing/Rough-in | 10/18/2016 | 10/19/2016 | 10/19/2016 | A | FAIL |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Pieroni. Needto provide correct floor plan. (Fliped)
|
Plan Modification Accepted | | | 10/4/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 10/4/2016 | | 10/4/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 9/20/2016 | 9/21/2016 | 9/21/2016 | P | PASS |
Jim Storey
|
|
|
Jed Phone #: ###-####
|
BLD-Foundation | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PASS |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 8/30/2016 | 8/31/2016 | 8/31/2016 | P | PART |
Tony Young
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/23/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 8/22/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 8/22/2016 | | DONE |
|
|
|
all requirements met
|
Plan assigned to (DAF) | 8/11/2016 | 8/11/2016 | 8/20/2016 | | DONE |
David Ferguson
|
|
|
due 8/22
|
1st review completed | | | 8/20/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/9/2016 | | 8/20/2016 | | PASS |
David Ferguson
|
|
|
|
Routing - MECHANICAL | 8/12/2016 | | 8/12/2016 | | PASS |
Chad Schwendiman
|
|
|
|
Plan assigned to (LEG) Tisha | 8/9/2016 | | 8/11/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Application received | | | 8/9/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 9 2016 2:43PM
|
Plans ACCEPTED BY PLAN TECH | | | 8/9/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/9/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/9/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 8/9/2016 | | 8/9/2016 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 8/9/2016 | | 8/9/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 8/9/2016 | | 8/9/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 8/9/2016 | | | | FAIL |
Troy James
|
|
|
Emailed corrections
|