Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD16-02938
StatusFinaled
Name TONY TSENG
Site Address 303 N KIMBALL PL
Project NameWorld Connections
Customer Number 
ePlanReviewYes
Description
**(WORLD CONNECTIONS)** //Plan modification to construct new interior nonbearing walls to create (2) offices, a conference room, a storage room, a reception area and select new door/door frames. 1-25-2018 JG// Permit is to remodel an existing 22,124 sq. ft. building. Approval is contingent upon adhering to the approved plans on file. Work to include: construction of select interior nonbearing walls to create (2) offices, acoustic suspended ceiling, relocate light fixtures, electrical work and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 2/19/20183/13/2018 DONE
Mailed 3-14-18
BLD-Ceiling Grid Inspection2/9/20182/9/20182/9/2018PPASS
DetailsMike Jordan
Adam Phone #: ###-####. OK for perm occ.
BLD-Final2/9/20182/9/20182/9/2018PPASS
DetailsMike Jordan
Ceiling grid insp on 2/9/18 was supposed to be final bldg insp. see inspectors notes in ceiling grid inspection for OK for perm occupancy
Permanent Occupancy  2/9/2018 DONE
Print Occupancy Form  2/9/2018 DONE
CHANGE STATUS TO (ISS)  2/9/2018 DONE
Plan Mod
Plan assigned to (JG)1/25/20181/25/20182/2/2018 PASS
DetailsJavier Guzman
1st rev comp, Plan Mod World Connections
Routing - PLAN CHECK1/30/2018 2/2/2018 PASS
DetailsJavier Guzman
Permit Ready to Issue  2/2/2018 DONE
DO NOT REISSUE plan mod, fees due
Routing - PLAN CHECK1/25/2018 1/27/2018 FAIL
DetailsJavier Guzman
Route to Impact Fee Review1/25/20181/28/20181/25/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan Modification Accepted  1/25/2018 DONE
DetailsChristina Prado
Plan Mod to update floor configuration and add office walls
BLD-Final1/18/20181/22/20181/22/2018PPEND
DetailsMike Jordan
Adam Phone #: ###-####-no plan on site but will try and get them from the architect. Will need to architect to submit plan modifiaction to show the additional two offices that have been constructed.
Telephone call  1/22/2018 DONE
GC called wanted to know what needed done to get the C of O-told him he needed the approved drawings before his final building inspections and since he doesn't have the sign off card he can email or call us and we'll print the sign off card fill it out and he can come pick up the card or we can email it to him
FIRE-Final Inspection11/13/201711/13/201711/13/2017PPASS
DetailsTroy Cobbley
life safety passed.

Adam Phone #: ###-####
FIRE-Conference6/7/20176/12/20176/12/2017ADONE
DetailsJim Page
Fire conference complete, fire alarm modifications still need to be made to the existing system, fire sprinkler modifications have been completed, fire extinguishers are in place with current inspection tags, exit signs with discharge lighting will be installed before final inspection, exterior exits that are designated as emergency exits will also need to have exit discharge illumination installed per note number 12 on fire plan review comments.
FIRE-Final Inspection3/6/20173/6/20173/6/2017PFAIL
DetailsTroy Cobbley
No plans or small documents on site. I did a courtesy walk through with Adam. I noted the need for fire sprinkler and fire alarm modifications in several locations. It appears the emergency generator has been removed so backup power for emergency lights is an issue. Door hardware does not meet ADA on the new doors.

Leanne Phone #: ###-####
Issue PAID IN FULL permit  2/21/2017 DONE
Print Occupancy Form  2/21/2017 DONE
Print Occupancy Form  2/21/2017 DONE
Telephone call  2/17/2017 DONE
Spoke with Jeff to get Tony's phone number to inform him that this permit it 10 days past its expiration date. Stated that I saw Tony brought in the GC Form, Revised Value and letter from parcel owner.
Telephone call  2/6/2017 DONE
Left a message for Jeff informing him that this permit is going to expire at 5pm tonight and if he would like he may send in a request for a 180 day extension. Left him the permit number, my email and my phone number
Telephone call  1/30/2017 DONE
Left a message for Jeff informing him that this permit is going to expire in 8 days and that if he would like he may send in a request for an extension. Stated the permit number, my email and my phone number.
Expiration Notice1/17/20172/7/20171/17/2017 DONE
DetailsBrittany Hill
Plan assigned to (JG)8/11/20168/11/20169/21/2016 PASS
DetailsJavier Guzman
1st review completed, 8/17 L1 World Connections ePlan
Routing - PLAN CHECK9/21/2016 9/21/2016 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  9/21/2016 DONE
Permit Ready to Issue  9/21/2016 DONE
***all requirments met 2-15-17 /CEV

NEED GC form and certificate of value
1st review completed  8/16/2016 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK8/11/2016 8/16/2016 FAIL
DetailsJavier Guzman
ePlan
Routing - FIRE8/15/20168/15/20168/15/2016 PASS
DetailsKatie Marron
Comments attached to case.
Intake Approval  8/11/2016 PASS
DetailsJavier Guzman
Routing - Addressing8/11/2016 8/11/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS8/11/2016 8/11/2016 PASS
DetailsRachael Beierle
Application received  8/10/2016 DONE
Application submitted via PDS Online on Aug 10 2016 1:50PM