Print Occupancy Form | | | 10/13/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/11/2017 | 10/12/2017 | 10/11/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Tim Phone #: ###-####
|
FIRE-Final Inspection | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | CANC |
Troy Cobbley
|
|
|
Opticon was non-functional.
Tim Sanders Phone #: ###-####
|
PubWorks Occupancy Approval | 9/14/2017 | 9/14/2017 | 9/14/2017 | | DONE |
Mike Sheppard
|
|
|
|
Print Occupancy Form | | | 9/14/2017 | | DONE |
|
|
|
|
Zoning Approval | 9/12/2017 | 9/12/2017 | 9/12/2017 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 5/3/2017 | 5/4/2017 | 5/4/2017 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given until the permanant address is installed, permanant building number, and gates/fire dept access is provided. The fire dept is ok with the 16' electric gate with the additional 4' leaf.
|
FIRE-Final Inspection | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | FAIL |
Troy Cobbley
|
|
|
need building number, site adress and small documents
|
Place hold on job | 8/17/2016 | | 8/19/2016 | | DONE |
Kristal Soland
|
|
|
DO NOT ISSUE WITHOUT BLD16-01617, BLD16-02948 TO BLD16-02954
|
Issue PAID IN FULL permit | | | 8/19/2016 | | DONE |
|
|
|
|
Telephone call | | | 8/18/2016 | | DONE |
|
|
|
notified customer that permit is ready
|
Plan assigned to (AJS) | 8/11/2016 | 8/11/2016 | 8/17/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 8/17/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/17/2016 | | DONE |
|
|
|
Need Signature on Applications, RP, GC Form, Revised Cert
**ACHD Fee is all with BLD16-01617**
|
Print Occupancy Form | | | 8/17/2016 | | DONE |
|
|
|
|
Routing - Addressing | | | 8/16/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing Off Site - STRUCTURAL | 7/22/2016 | | 8/16/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Sewer Design | | | 8/15/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Solid Waste | | | 8/15/2016 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - Design Review | 8/11/2016 | | 8/15/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLANNING Land Div | | | 8/15/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - FIRE | 8/11/2016 | 8/11/2016 | 8/12/2016 | | PASS |
Katie Marron
|
|
|
All buildings originally reviewed under BLD16-01617. Comments attached to case.
|
Routing PW Drainage | | | 8/12/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | | | 8/12/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Rating | | | 8/12/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PUBLIC WORKS | | | 8/12/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | | | 8/12/2016 | | PASS |
Andy J. Long
|
|
|
Approved. See BLD16-01617 & ESC16-00722 for ESC plan review & permit conditions.
|
Routing - PLUMBING | | | 8/12/2016 | | PASS |
Bill VanDegrift
|
|
|
Bill called and asked to have PLM signed off.
|
Route to Impact Fee Review | 8/11/2016 | 8/16/2016 | 8/11/2016 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 8/11/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | | | 8/11/2016 | | PASS |
Tim L. Woodard
|
|
|
signed off by TLW on BLD16-01617
|
Plans ACCEPTED BY PLAN TECH | | | 8/11/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 8/11/2016 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/11/2016 | | DONE |
Christina Prado
|
|
|
|
Routing Off Site - STRUCTURAL | 5/9/2016 | | 6/13/2016 | | FAIL |
Christina Prado
|
|
|
|
Application received | | 8/11/2016 | | | |
|
|
|
|