VOIDED CHANGE STATUS | | | 10/17/2016 | | DONE |
|
|
|
as per Joe-no longer doing project-Joe says the homeoweners have altered the project as well as the electrical and he will no longer be responsible for any work that was done after the frame inspection was done
|
CHANGE STATUS TO (ISS) | | | 10/17/2016 | | DONE |
|
|
|
we voided by mistake
|
Permit EXPIRED | | | 10/17/2016 | | DONE |
|
|
|
as per Joe-no longer doing project-Joe says the homeoweners have altered the project as well as the electrical and he will no longer be responsible for any work that was done after the frame inspection was done
|
BLD-Framing/Rough-in | 9/20/2016 | 9/21/2016 | 9/21/2016 | A | PASS |
Jim Sly
|
|
|
Darren-please call 30 minutes prior for access Phone #: ###-####
|
BLD-Framing/Rough-in | 9/19/2016 | 9/20/2016 | 9/20/2016 | P | PASS |
Jim Sly
|
|
|
would like call ahead; Joe Phone #: ###-####
|
Routing Walk-In (BLD) | 8/11/2016 | 8/11/2016 | 8/11/2016 | P | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 8/11/2016 | 8/11/2016 | 8/11/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 8/11/2016 | | 8/11/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 8/11/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 8/11/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/11/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/11/2016 | | DONE |
|
|
|
|
1st review completed | | | 8/11/2016 | | DONE |
David Ferguson
|
|
|
|
Application received | | 8/11/2016 | | | |
|
|
|
|