BLD-Final | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Jim Sly
|
|
|
Zach Phone #: ###-####
|
DOC - Permit Finaled | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | NR |
Jim Sly
|
|
|
Zach Phone #: ###-#### Need Mech final.
|
BLD-Final | 2/28/2017 | 2/28/2017 | 2/28/2017 | P | NR |
Tony Young
|
|
|
Zach Phone #: ###-####,, need trades,, record of survey is done per zoning
|
BLD-Energy code compliance | 11/18/2016 | 11/18/2016 | 11/18/2016 | P | PASS |
Tony Young
|
|
|
zach Phone #: ###-####
|
BLD-Framing/Rough-in | 11/14/2016 | 11/15/2016 | 11/15/2016 | P | PART |
Tony Young
|
|
|
Zach Phone #: ###-####,, correction notice ,, ok to insulate
|
BLD-Wall Bracing | 10/14/2016 | 10/17/2016 | 10/17/2016 | A | PASS |
Tony Young
|
|
|
Bob Phone #: ###-####,, exterior nailing ok
|
BLD-Foundation | 9/16/2016 | 9/19/2016 | 9/19/2016 | A | DONE |
Tony Young
|
|
|
Wall// Zack Phone #: ###-####
|
BLD-Footing | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | PASS |
Tony Young
|
|
|
Zack Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/7/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/7/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/6/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 9/6/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan assigned to (DAF) | 8/24/2016 | 8/24/2016 | 9/4/2016 | | DONE |
David Ferguson
|
|
|
due 9/2
|
1st review completed | | | 9/4/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/22/2016 | | 9/4/2016 | | PASS |
David Ferguson
|
|
|
|
Routing - PLANNING | 8/22/2016 | | 8/25/2016 | | PASS |
Nicolette Womack
|
|
|
|
Route to Impact Fee Review | 8/22/2016 | 8/25/2016 | 8/24/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (LEG) Tisha | 8/22/2016 | | 8/24/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 8/22/2016 | | 8/22/2016 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 8/22/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/22/2016 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/22/2016 | | DONE |
|
|
|
|
Routing - Addressing | 8/22/2016 | | 8/22/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 8/22/2016 | | 8/22/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 8/16/2016 | | FAIL |
|
|
|
NEEDS to upload Manual J
|
Application received | | | 8/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2016 2:02PM
|