BLD-Final | 6/13/2017 | 6/14/2017 | 6/14/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 6/14/2017 | 6/14/2017 | 6/14/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 4/17/2017 | 4/19/2017 | 4/19/2017 | A | PASS |
Brandon Shaw
|
|
|
Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 4/13/2017 | 4/17/2017 | 4/17/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | PASS |
Jim Sly
|
|
|
Rudy Phone #: ###-####
|
BLD-Foundation | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Footing | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Phil Shearer
|
|
|
Alvaro Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/20/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/19/2016 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2016 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2016 | | DONE |
|
|
|
called Tahoe- left message that permit is ready and fees due
|
Permit Ready to Issue | | | 9/19/2016 | | DONE |
|
|
|
All Met
|
Plan assigned to (BJM) | 8/22/2016 | 8/22/2016 | 9/17/2016 | | DONE |
Brian McGowan
|
|
|
Due 8-31
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/9/2016 | | 9/16/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 9/16/2016 | | DONE |
Brian McGowan
|
|
|
|
Plan resubmittals received | | | 9/9/2016 | | DONE |
|
|
|
received (2) sets of calculations and plan resubmittals
|
1st review completed | | | 8/31/2016 | | FAIL |
Brian McGowan
|
|
|
Tall wall engineering needed. (Requested by Dave for similar Model)
|
Routing - MECHANICAL | 8/22/2016 | | 8/23/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/18/2016 | | 8/22/2016 | | PASS |
Jeff Lowe
|
|
|
|
Plan assigned to (LEG) Tisha | 8/18/2016 | | 8/22/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/18/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/18/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/18/2016 | | DONE |
|
|
|
|
Routing - Addressing | 8/18/2016 | | 8/18/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 8/18/2016 | | PASS |
|
|
|
|
Routing PW Flood Plain | | | 8/18/2016 | | PASS |
Jim Wyllie
|
|
|
Property out of floodplain as per Letter of Map Revision.
Jim Wyllie / ###-####
|
Application received | | 8/17/2016 | | | |
|
|
|
|
Routing - PLAN CHECK | 8/23/2016 | | | | |
Brian McGowan
|
|
|
|