Third Notice | | 6/17/2017 | 7/5/2017 | | DONE |
|
|
|
This permit finaled on the web by Brad Booher
|
Second Notice | | 5/20/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
First Notice | 4/28/2017 | 4/28/2017 | 5/10/2017 | | DONE |
Jim Sly
|
|
|
Mailed 5-11
|
BLD-Final | 4/26/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Jim Sly
|
|
|
Call me and I will meet you at the gate. I will also have hard copies of 3rd Party Inspections printed for you.
Thanks,
Ed Comeau (HITT Contracting, Inc.) Phone #: ###-#### Inspection requested via web by Ed Comeau
|
DOC - Permit Finaled | 4/28/2017 | 4/28/2017 | 4/28/2017 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 4/27/2017 | 4/27/2017 | 4/27/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Zoning Approval | 4/27/2017 | 4/27/2017 | 4/27/2017 | | DONE |
Nicolette Womack
|
|
|
Photos Attached
|
BLD-Other | 12/15/2016 | 12/19/2016 | 12/19/2016 | P | PART |
Jim Sly
|
|
|
Inspect prep for slab on grade Phone #: ###-#### Inspection requested via web by Ed Comeau Slab OK pending Geotech special inspection, teasts and approvals.
|
BLD-Footing | 12/1/2016 | 12/2/2016 | 12/1/2016 | P | PASS |
Jim Sly
|
|
|
Ed Phone #: ###-#### OK pending Terricon Special inspection, tests and approvals.
|
Telephone call | | | 11/21/2016 | | DONE |
|
|
|
notified customer that permit is ready
|
Issue PAID IN FULL permit | | | 11/21/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/18/2016 | | |
|
|
|
|
Plan assigned to (JG) | 10/31/2016 | 10/31/2016 | 11/18/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 11/17 L3 VZW Shelter Expansion paper
|
Inspection Record Card- Bld | | | 11/18/2016 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/16/2016 | | 11/18/2016 | | PASS |
Javier Guzman
|
|
|
signed off by Keith Jones of AHJ Engineers
|
Case Summary (BLD) | | | 11/18/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/18/2016 | | DONE |
|
|
|
**MET*** Need RP, GC Form and Revised Cert of Value
|
Route to Impact Fee Review | 11/10/2016 | 11/13/2016 | 11/17/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 11/16/2016 | | DONE |
|
|
|
Three copies of Materials testing & inspection packet, structural analysis for wall column/foundation design, structural analysis for canopy structure, addendum #1 geotechnical engineering report, addendum #2 geotechnical engineering report, 310 special Inspections, as well as three copies of sheets 1 of 3, 2 of 3 and 3 of 3. Taken to Javier
|
Plan assigned to (CDM) | 10/21/2016 | 10/21/2016 | 11/15/2016 | | DONE |
Carl D Madsen
|
|
|
pending assignment and routing
|
Routing - FIRE | | 10/25/2016 | 11/10/2016 | | PASS |
Katie Marron
|
|
|
Plans reviewed for FD Access and hydrant availability. No comments required.
|
1st review completed | | | 11/10/2016 | | FAIL |
|
|
|
Failed Erosion Control and Off Site Structural
|
Plan Reviewer's activity | | | 11/10/2016 | | DONE |
Javier Guzman
|
|
|
Fire placed a note that ESC failed 1 st revie but ESC was previously passed on 11/8 by Andy
|
Routing - PLAN CHECK | | | 11/9/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 11/9/2016 | | 11/9/2016 | | FAIL |
Javier Guzman
|
|
|
failed by Keith Jones of AHJ Engineers
|
Routing - Design Review | | | 11/9/2016 | | PASS |
Javier Guzman
|
|
|
Not in a "D" zone and zonning certificate was approved
|
Routing - Erosion and Sediment | 11/8/2016 | | 11/8/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted as requested and approved.
|
Routing - PUBLIC WORKS | 10/27/2016 | | 11/3/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 11/3/2016 | | 11/3/2016 | | PASS |
Nicolette Womack
|
|
|
CZC16-00239
|
Routing PW Drainage | 10/27/2016 | | 11/2/2016 | | PASS |
Brian Murphy
|
|
|
approved under odi2622
|
Routing PW Sewer Rating | 10/27/2016 | | 10/27/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 10/26/2016 | | 10/27/2016 | | PASS |
Emily Dixon
|
|
|
|
Routing - PLANNING Land Div | 10/25/2016 | | 10/26/2016 | | PASS |
Todd Tucker
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/21/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/21/2016 | | PASS |
|
|
|
as per Dave Ferguson; okay to take in
|
Recd Pcfee & Taken To Pln CK | | | 10/21/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/3/2016 | | FAIL |
David Ferguson
|
|
|
1) Provide a completed #502 New Commercial/Commercial Additions Checklist
This checklist will ask you to submit additional information including but not limited to the following;
- # 304 Registered Design Professional form
- Stamped, signed and dated plans (this applies to the original Verizon plans that were submitted with the first submittal).
- Plans submitted on min. 18x24 sized sheets (this applies to the shop drawings)
- Break out sheets individually and not in a bundle (this refers to both the 19 pages of the Verizon plans only).
- Provide a Zoning Certificate from our Planning department approving this addition
- Code analysis for the project
- Elevations for the project
- Erosion and Sediment Control plan or a Waiver Letter.
|
Intake Approval | | | 10/3/2016 | | FAIL |
David Ferguson
|
|
|
- Stamped, signed and dated plans (this applies to the original Verizon plans that were submitted with the first submittal and your last submittal). All plan sheets need to be stamped, signed and dated by the design professional.
- Code analysis for the project. This should appear on the cover sheet of the Verizon plans.
- Adequate site plan showing property lines, setbacks of the proposed building to property lines, dimensions showing distance to surrounding buildings, etc.
- Elevations for the building
- Fire flow letter. You marked the check list that you've provided this but I don't see it.
|
Intake Approval | | | 8/24/2016 | | FAIL |
David Ferguson
|
|
|
1) Provide a completed #502 New Commercial/Commercial Additions Checklist
This checklist will ask you to submit additional information including but not limited to the following;
- # 304 Registered Design Professional form
- Stamped, signed and dated plans
- Plans submitted on min. 18x24 sized sheets
- Break out sheets individually and not in a bundle
- Provide a Zoning Certificate from our Planning department approving this addition
- Code analysis for the project
- Elevations for the project
- At this time, it is not clear what the addition is. There are no plan sheets showing the structure nor is there any engineering for the structure other than the foundation.
|
Application received | | | 8/18/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 18 2016 6:09AM
|
Routing - Erosion and Sediment | | | | | FAIL |
Andy J. Long
|
|
|
Please submit ESC plan or plan waiver.
|