BLD-Final | 4/21/2017 | 4/24/2017 | 4/24/2017 | P | NR |
Tony Young
|
|
|
Mark -- call 1st; Phone #: ###-####,, needs mech pass
|
BLD-Final | 4/20/2017 | 4/21/2017 | 4/24/2017 | P | NR |
Tony Young
|
|
|
Mark -- call 1st; Phone #: ###-####
|
BLD-Final | 4/19/2017 | 4/20/2017 | 4/20/2017 | A | NR |
Tony Young
|
|
|
Mark -- call 1st; Phone #: ###-####
|
BLD-Final | 4/19/2017 | 4/19/2017 | 4/19/2017 | P | NR |
Tony Young
|
|
|
Mark -- call 1st; Phone #: ###-####,, need trades 1st
|
BLD-Aging Inspection | 3/29/2017 | 3/29/2017 | 3/31/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 3/28/2017 | 3/28/2017 | 3/31/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Jim Sly
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 11/2/2016 | 11/3/2016 | 11/3/2016 | P | PASS |
Tony Young
|
|
|
Marc Phone #: ###-####,, verify seal package
|
BLD-Conference | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | PASS |
Tony Young
|
|
|
marc Phone #: ###-####,, soffits are work in progress,, ok
|
BLD-Foundation | 9/13/2016 | 9/14/2016 | 9/14/2016 | P | PASS |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
PubWorks Subgrade Approval | 9/12/2016 | 9/12/2016 | 9/12/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | PEND |
Tony Young
|
|
|
Ryan Phone #: ###-####,, need soils report approval
|
BLD-Footing | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####,, pending soils report
|
BLD-Footing | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 9/7/2016 | 9/8/2016 | 9/8/2016 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####,, needs soils pass PW
|
Issue PAID IN FULL permit | | | 8/31/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 8/30/2016 | | |
|
|
|
|
Plan assigned to (DAF) | 8/24/2016 | 8/24/2016 | 8/30/2016 | | DONE |
David Ferguson
|
|
|
due 8/30
|
Routing PW Grading-Hillside | 8/24/2016 | | 8/30/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing - Erosion and Sediment | 8/24/2016 | | 8/30/2016 | | PASS |
Evan Jenkins
|
|
|
Addition of Approx 375'SF
|
Routing - PLAN CHECK | 8/30/2016 | | 8/30/2016 | | PASS |
David Ferguson
|
|
|
Route to Evan and Jason T.
|
Case Summary (BLD) | | | 8/30/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/30/2016 | | DONE |
|
|
|
|
Telephone call | | | 8/30/2016 | | DONE |
|
|
|
called Marc to let know permit is ready and how much is owed
|
Routing Walk-In (BLD) | 8/24/2016 | 8/24/2016 | 8/24/2016 | P | DONE |
Kristal Soland
|
|
|
|
Routing Walk-In (Zoning) | 8/22/2016 | 8/22/2016 | 8/22/2016 | A | PASS |
Jeff Lowe
|
|
|
Plan complies with setbacks as corrected. Permit to be issued only after hillside review approved.
|
Routing Walk-In (BLD) | 8/22/2016 | 8/22/2016 | 8/22/2016 | A | FAIL |
Tisha Gallop
|
|
|
needs pw hillside sign off, foundation plan and calcs enginereed/stamped, WUI A requirements, erosion waiver request letter.
|
1st review completed | | | 8/22/2016 | | FAIL |
|
|
|
|
Application received | | 8/22/2016 | | | |
|
|
|
|