BLD-Final | 4/7/2017 | 4/10/2017 | 4/10/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick. Provide blowe door test result or 3rd. party inspection report.
|
BLD-Final | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick No inspection pending electrical
|
BLD-Energy code compliance | 1/20/2017 | 1/20/2017 | 1/20/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 1/18/2017 | 1/18/2017 | 1/18/2017 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick. Fire block at concealed area at ceiling level adjacent to main entry door, provide floor joist hangar for floor joist by stairs, nail off simpson hangar upstairs. Ok to insualte.
|
BLD-Wall Bracing | 1/3/2017 | 1/4/2017 | 1/4/2017 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Weston Wagner
|
BLD-Foundation | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 11/3/2016 | 11/4/2016 | 11/4/2016 | P | PASS |
Jim Storey
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | PASS |
Phil Shearer
|
|
|
As early as possible Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 10/13/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/13/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/8/2016 | | |
|
|
|
|
1st review completed | | | 9/8/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/8/2016 | | DONE |
|
|
|
ALL REQUIREMENTS MET
|
Plan assigned to (LEG) Tisha | 8/26/2016 | | 9/8/2016 | | DONE |
Tisha Gallop
|
|
|
9/8
|
Routing - PLAN CHECK | 8/26/2016 | | 9/8/2016 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 8/26/2016 | | 8/30/2016 | | PASS |
Jeff Lowe
|
|
|
|
Routing - MECHANICAL | 8/26/2016 | | 8/29/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 8/26/2016 | | 8/26/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 8/26/2016 | | 8/26/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/26/2016 | | DONE |
|
|
|
|
Intake Approval | | | 8/26/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/26/2016 | | DONE |
|
|
|
|
Application received | | | 8/23/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 23 2016 2:03PM
|
Intake Approval | | | 8/23/2016 | | FAIL |
|
|
|
Missing Manual. Offered to upload them, but Jared stated they wouldn't get them for a couple of days so I told him I would go ahead and fail the prescreen so he will get another task and can upload them once he has the manuals
|