BLD-Final | 4/21/2017 | 4/24/2017 | 4/24/2017 | A | CANC |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
DOC - Permit Finaled | 4/24/2017 | 4/24/2017 | 4/24/2017 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 4/21/2017 | 4/21/2017 | 4/21/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 3/27/2017 | 3/27/2017 | 3/27/2017 | P | NR |
Jim Sly
|
|
|
Rollo Phone #: ###-#### Need Public Works Final.
|
Meeting | | | 3/27/2017 | | DONE |
|
|
|
as per Laura in addressing-addresses are permanent now
|
BLD-Energy code compliance | 12/21/2016 | 12/21/2016 | 12/21/2016 | P | PASS |
Jim Sly
|
|
|
Kyle Phone #: ###-####
|
BLD-Framing/Rough-in | 12/19/2016 | 12/20/2016 | 12/20/2016 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### ok to insulate c/n on site
|
BLD-Framing/Rough-in | 12/14/2016 | 12/15/2016 | 12/15/2016 | A | NR |
Phil Shearer
|
|
|
kyle Phone #: ###-####
|
BLD-Wall Bracing | 12/5/2016 | 12/5/2016 | 12/5/2016 | P | PART |
Phil Shearer
|
|
|
Shear // Kyle Phone #: ###-####
|
BLD-Wall Bracing | 12/2/2016 | 12/5/2016 | 12/5/2016 | A | NR |
Phil Shearer
|
|
|
Shear // Kyle Phone #: ###-####
|
BLD-Wall Bracing | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | NR |
Phil Shearer
|
|
|
Shear // Kyle Phone #: ###-####
|
PubWorks Subgrade Approval | 11/30/2016 | 11/30/2016 | 11/30/2016 | | DONE |
Jason C. Taylor
|
|
|
*** COLUMNS APPROVED ***A letter from the applicant’s geotechnical engineer indicating that the column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
CHANGE STATUS TO (ISS) | | | 11/22/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/21/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 11/14/2016 | 11/14/2016 | 11/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing PW Grading-Hillside | 11/21/2016 | | 11/21/2016 | | PASS |
Jason C. Taylor
|
|
|
Approved revised grading plan that randomly showed up on my desk. Jason Taylor ###-####.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/21/2016 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
BLD-Other | 11/17/2016 | 11/18/2016 | 11/18/2016 | A | DONE |
Phil Shearer
|
|
|
David-underground utilities Phone #: ###-####
|
Case Summary (BLD) | | | 11/17/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/14/2016 | | 11/17/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing PW Grading-Hillside | 11/16/2016 | | 11/16/2016 | | PASS |
Jason C. Taylor
|
|
|
Approved revised grading plan. JCT
|
BLD-Foundation | 11/13/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Phil Shearer
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
Plan Modification Accepted | | | 11/14/2016 | | DONE |
|
|
|
received 3 sets of grading plans, two sets of engineering, and 2 sets of shhets A1.0, A1.2, A1.3, and S1.0- gave to Brian
|
BLD-Footing | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Phil Shearer
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
PubWorks Subgrade Approval | 11/10/2016 | 11/10/2016 | 11/10/2016 | | DONE |
Jason C. Taylor
|
|
|
**FOOTINGS ONLY NO COLUMNS***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 11/4/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/3/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 10/28/2016 | 10/28/2016 | 11/3/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | | | 11/3/2016 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 11/3/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/3/2016 | | DONE |
|
|
|
MET
|
Inspection Record Card- Bld | | | 11/3/2016 | | DONE |
|
|
|
|
Telephone call | | | 11/3/2016 | | DONE |
|
|
|
called Chelsea- told her permit is ready and fees due
|
Routing - MECHANICAL | 10/7/2016 | | 11/3/2016 | | PASS |
Chad Schwendiman
|
|
|
New Manual J submitted
After further review of new manual j report. I am unable to verify any changes.
|
Routing - PLANNING | 10/28/2016 | | 10/28/2016 | | PASS |
Nicolette Womack
|
|
|
|
Plan resubmittals received | | | 10/28/2016 | | DONE |
|
|
|
resubmittal received 2 sets of calcs, a shear wall schedule, 1 floor plan, 2 sets of sheets A1.2, A1.3, S1.0- took to Brian McGowan
|
Plan resubmittals received | | | 10/24/2016 | | DONE |
|
|
|
Two copies of Structural Engineering, two copies of sheets a1.2, a1.3, s1.0 and s1.1. Taken to Brian Mc
|
Routing - PLAN CHECK | 10/14/2016 | | 10/19/2016 | | FAIL |
Brian McGowan
|
|
|
Wall bracing did not match engineering and rear wall of Great room had no wall bracing.
|
Plan resubmittals received | | | 10/14/2016 | | DONE |
|
|
|
received (2) sets of revised plans & engineering
|
Routing PW Grading-Hillside | 10/7/2016 | | 10/10/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 10/10/2016 | | 10/10/2016 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 10/4/2016 | | 10/7/2016 | | FAIL |
Brian McGowan
|
|
|
Various items need revised.
|
Plan resubmittals received | | | 10/4/2016 | | DONE |
|
|
|
resubmittals recieved 2 sheets of sheet # 1-took to Brian McGowan
|
Routing - PUBLIC WORKS | 10/4/2016 | | 10/4/2016 | | FAIL |
Rachael Beierle
|
|
|
See JCT in hillside
|
Routing PW Grading-Hillside | 10/4/2016 | | 10/4/2016 | | FAIL |
Jason C. Taylor
|
|
|
Need revised grading plans submited. JCT
|
Routing - PLAN CHECK | 9/27/2016 | | 10/4/2016 | | FAIL |
Brian McGowan
|
|
|
See hillside
|
Plan resubmittals received | | | 9/28/2016 | | DONE |
|
|
|
Two copies of HVAC/Manuel, two copies of structural edge engineering pplc, and two copies of sheets A0.0, A0.1, A1.0, A1.1, A1.2, A1.3, A2.0, A2.1, A3.1, E1.0, E1.1, S1.0, S1.1, S2.0, and S2.1 Taken to Brian McG
|
Plan resubmittals received | | | 9/27/2016 | | DONE |
|
|
|
received (1) set of grading revisions
|
Plan assigned to (BJM) | 9/21/2016 | 9/21/2016 | 9/21/2016 | | FAIL |
Brian McGowan
|
|
|
Fail - need top of wall and ftg elev. misc structural items
|
1st review completed | | | 9/21/2016 | | FAIL |
|
|
|
Stamped and signed Foundation required. Missing WUI Details. Misc. notes not corresponding.
|
Routing - FIRE | 9/12/2016 | 9/2/2016 | 9/14/2016 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - Erosion and Sediment | 9/2/2016 | | 9/12/2016 | | PASS |
Evan Jenkins
|
|
|
(Site prep inspection and approval required prior to earth disturbance)
***Please do not issue until after 9-13-16***LOT 45/ Block 1 Harris Ranch North-see waiver attached***Permit for the construction of a new 4298 sq. ft., two story (first story 2515 sq. ft., second story 1783 sq. ft.) single family dwelling with 7 bedrooms, 4 bathrooms, approximately #### sq. ft. of covered patio’s/porches and 935 sq. ft. attached garage per the approved plans, plan review report and any notations.
|
Routing - MECHANICAL | 9/7/2016 | | 9/9/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/7/2016 | | 9/7/2016 | | FAIL |
Nicolette Womack
|
|
|
waiting on waiver
|
Routing - PUBLIC WORKS | 9/7/2016 | | 9/7/2016 | | FAIL |
Rachael Beierle
|
|
|
|
Routing PW Grading-Hillside | | | 9/7/2016 | | FAIL |
Jason C. Taylor
|
|
|
See email dated 9/7/2016 for review notes. JCT
|
Routing - Addressing | 9/2/2016 | | 9/2/2016 | | PASS |
Laura Hunter
|
|
|
Preliminary address is 5587 E Hootowl Dr, need correct parcel when plat is recorded to validate given address
|
Intake Approval | | | 9/2/2016 | | PASS |
|
|
|
|
Plan assigned to (LEG) Tisha | 9/2/2016 | | 9/2/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing PW Sewer Rating | 9/2/2016 | | 9/2/2016 | | PASS |
Rachael Beierle
|
|
|
|
Telephone call | | | 8/30/2016 | | DONE |
|
|
|
sent email to Chelsea taht we still need the hold harmless letter
|
Recd Pcfee & Taken To Pln CK | | | 8/29/2016 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/29/2016 | | DONE |
|
|
|
|
Application received | | 8/29/2016 | | | |
|
|
|
|