BLD-Final | 4/21/2017 | 4/24/2017 | 4/24/2017 | A | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
DOC - Permit Finaled | 4/24/2017 | 4/24/2017 | 4/24/2017 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 4/21/2017 | 4/21/2017 | 4/21/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 3/24/2017 | 3/27/2017 | 3/27/2017 | A | NR |
Jim Sly
|
|
|
Rolo Phone #: ###-#### Need Public Works FinaL.
|
BLD-Energy code compliance | 12/27/2016 | 12/28/2016 | 12/28/2016 | A | PASS |
Phil Shearer
|
|
|
Kyle Phone #: ###-####
|
BLD-Framing/Rough-in | 12/28/2016 | 12/28/2016 | 12/28/2016 | P | PASS |
Phil Shearer
|
|
|
Kyle Phone #: ###-####
|
BLD-Framing/Rough-in | 12/23/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Phil Shearer
|
|
|
Kyle Phone #: ###-####
|
BLD-Wall Bracing | 12/9/2016 | 12/9/2016 | 12/9/2016 | P | PASS |
Phil Shearer
|
|
|
kyle Phone #: ###-####
|
PubWorks Subgrade Approval | 11/30/2016 | 11/30/2016 | 11/30/2016 | | DONE |
Jason C. Taylor
|
|
|
*** COLUMNS APPROVED ***A letter from the applicant’s geotechnical engineer indicating that the column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 11/15/2016 | 11/15/2016 | 11/15/2016 | P | PASS |
Phil Shearer
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 11/13/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Phil Shearer
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | NR |
Phil Shearer
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
PubWorks Subgrade Approval | 11/10/2016 | 11/10/2016 | 11/10/2016 | | DONE |
Jason C. Taylor
|
|
|
*FOOTINGS ONLY NO COLUMNS***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Meeting | | | 11/7/2016 | | DONE |
|
|
|
have an email to Jason Blais to make sure we're ok to issue permits
|
Telephone call | | | 11/7/2016 | | DONE |
|
|
|
Spoke with Chelsea informing her the permit is ready and the fee amount due for issuance
|
Issue PAID IN FULL permit | | | 11/7/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/4/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 9/21/2016 | 9/21/2016 | 11/4/2016 | | DONE |
Brian McGowan
|
|
|
Fail - need top of wall and ftg elev. misc structural items
|
Print Occupancy Form | | | 11/4/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/4/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/4/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/4/2016 | | DONE |
|
|
|
MET
|
Routing - PLAN CHECK | 10/27/2016 | | 11/4/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 10/28/2016 | | 10/28/2016 | | PASS |
Nicolette Womack
|
|
|
|
Plan resubmittals received | | | 10/27/2016 | | DONE |
|
|
|
recieved (2) sets of resubmittals
|
Routing - PLAN CHECK | 10/10/2016 | | 10/27/2016 | | FAIL |
Brian McGowan
|
|
|
Wall bracing
|
Routing - PLAN CHECK | 10/14/2016 | | 10/25/2016 | | FAIL |
Brian McGowan
|
|
|
Fail - Foundation Plan needs to be updated.
|
Plan resubmittals received | | | 10/14/2016 | | DONE |
|
|
|
received (2) sets of revised plans & engineering
|
Routing PW Grading-Hillside | 10/10/2016 | | 10/10/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 10/10/2016 | | 10/10/2016 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 10/4/2016 | | 10/10/2016 | | FAIL |
Brian McGowan
|
|
|
Various items need corrections. See email
|
Plan resubmittals received | | | 10/4/2016 | | DONE |
|
|
|
resubmittals recieved 2 sheets of sheet # 1-took to Brian McGowan
|
Routing - PUBLIC WORKS | 10/4/2016 | | 10/4/2016 | | FAIL |
Rachael Beierle
|
|
|
See JCT in hillside.
|
Routing PW Grading-Hillside | 10/4/2016 | | 10/4/2016 | | FAIL |
Jason C. Taylor
|
|
|
Need revised grading plans submitted. JCT
|
Plan resubmittals received | | | 9/28/2016 | | |
|
|
|
Two copies of Structural Edge Engineering PLLC, Two copies of sheets A0.0, A0.1, A1.0, A1.2, A2.0, A2.1, A3.1, E1.0, S1.0, and S2.0 Taken to Brian McG
|
Plan resubmittals received | | | 9/27/2016 | | DONE |
|
|
|
received (1) set of grading revisions
|
1st review completed | | | 9/21/2016 | | FAIL |
Brian McGowan
|
|
|
Foundation plan must be stamped and signed. Missing WUI code details
|
Routing - FIRE | 9/12/2016 | 9/2/2016 | 9/14/2016 | | PASS |
Scott Arellano
|
|
|
No comments attached to plans.
|
Routing - Erosion and Sediment | 9/9/2016 | | 9/12/2016 | | PASS |
Evan Jenkins
|
|
|
(Site prep inspection and approval required prior to earth disturbance)
***Please do not issue until after 9/13/16****Lot 43 Block 1 Harris Ranch North-see attached waiver***Permit for the construction of a new 3008 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately #### sq. ft. of covered patio/porch, ft., and a 929 sq. ft. attached garage
|
Routing - MECHANICAL | 9/7/2016 | | 9/9/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/7/2016 | | 9/7/2016 | | FAIL |
Nicolette Womack
|
|
|
waiting for Waiver
|
Routing - PUBLIC WORKS | 9/7/2016 | | 9/7/2016 | | FAIL |
Rachael Beierle
|
|
|
|
Routing PW Grading-Hillside | 9/2/2016 | | 9/7/2016 | | FAIL |
Jason C. Taylor
|
|
|
See email dated 9/7/2016 for review notes. JCT
|
Routing PW Sewer Rating | 9/2/2016 | | 9/2/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 9/2/2016 | | 9/2/2016 | | PASS |
Laura Hunter
|
|
|
Preliminary address is 5361 E Hootowl Dr, need correct parcel when plat is recorded to validate given address
|
Intake Approval | | | 9/2/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/2/2016 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 9/2/2016 | | 9/2/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Telephone call | | | 8/30/2016 | | DONE |
|
|
|
sent email to Chelsea taht we still need the hold harmless letter
|
Plans ACCEPTED BY PLAN TECH | | | 8/29/2016 | | DONE |
|
|
|
|
Application received | | 8/29/2016 | | | |
|
|
|
|