First Notice | | 8/19/2017 | 9/25/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/9/2017 | | DONE |
|
|
|
|
BLD-Final | 8/7/2017 | 8/8/2017 | 8/8/2017 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Ok for perm occ. No electrical permit was required.
|
FIRE-Final Inspection | 7/26/2017 | 7/27/2017 | 7/27/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 7/3/2017 | 7/5/2017 | 7/5/2017 | P | FAIL |
Troy Cobbley
|
|
|
Still missing two exit signs as marked on the city approved plans.
|
BLD-Framing/Rough-in | 7/3/2017 | 7/3/2017 | 7/3/2017 | P | PASS |
Mike Jordan
|
|
|
|
Case Summary (BLD) | | | 5/24/2017 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/24/2017 | | DONE |
|
|
|
|
BLD-Conference | 5/4/2017 | 5/8/2017 | 5/8/2017 | A | DONE |
Mike Jordan
|
|
|
Meeting with Steve from K2 construction at 10:00am.
|
BLD-Framing/Rough-in | 5/8/2017 | 5/8/2017 | 5/8/2017 | A | PASS |
Mike Jordan
|
|
|
Meeting with Steve from K2 construction at 10:00am. Column wraps for 1hr. const. ok.
|
BLD-Conference | 4/28/2017 | 5/5/2017 | 5/5/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 5/1/2017 | 5/4/2017 | 5/4/2017 | A | DONE |
Mike Jordan
|
|
|
Went over completed work and what still needs to be addressed. Tenant aslo to schedule a fire/life/safety final to see what outstanding issues need addressed. A meeting with Steve from K2 construction has been set up for Monday May 8th. to go over 1hr. construction for type V-A construction to eliminate fire walls.
|
FIRE-Final Inspection | 5/4/2017 | 5/4/2017 | 5/4/2017 | P | FAIL |
Troy Cobbley
|
|
|
Provide new exit signs as per plan, relocate exit signs as discussed to match plans, repair emergency lights, provide correct hardware in game room, provide plan modification addressing actual room use as discussed, provide annual inspection for the fire sprinkler system matt Phone #: ###-####
|
BLD-Conference | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | DONE |
Mike Jordan
|
|
|
A correction notice was issued stating to schedule a building conferance to reveiw work done, work remaining and what tenats schedule is to complete work and obtain a certificate of occupancy.
|
BLD-Conference | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | PEND |
Mike Jordan
|
|
|
Check status/scheduling of project. K2 Construction has done some door infill and added some doors. Per K2 this was there scope of work only. I called and left a message with Gabriel Wilson, owner of ABU games but have not received a call back as of 4:40pm today. Will stop by tomorrow and issue a correction notice if needed.
|
BLD-Framing/Rough-in | 3/2/2017 | 3/3/2017 | 3/3/2017 | A | CANC |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
Print Occupancy Form | | | 1/31/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/31/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/31/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/31/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/30/2017 | | DONE |
|
|
|
need RP
|
Telephone call | | | 1/12/2017 | | DONE |
|
|
|
call applicant AND owner- left message that permit is ready for pick up and need GC, certificate of value, and ACHD
|
1st review completed | | | 9/27/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/27/2016 | | DONE |
Christina Prado
|
|
|
Need ACHD, GC Form & Revised Certificate of Value for issuance
|
Plan assigned to (CJW) | 9/20/2016 | | 9/27/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) (Oct 7 - 15 days) ABU games
|
Routing - PLAN CHECK | 9/20/2016 | | 9/27/2016 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Routing - FIRE | 9/20/2016 | | 9/27/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Design Review | 9/20/2016 | | 9/21/2016 | | PASS |
Sarah Schafer
|
|
|
|
Intake Approval | | | 9/19/2016 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 9/16/2016 | | PASS |
|
|
|
Plan intake approved
|
Intake Approval | | | 8/31/2016 | | FAIL |
|
|
|
(8-31-16) See the circled items in the plan intake checklist and resolve those items as noted. Please resolve all circled items.
|
Intake Approval | | | 8/30/2016 | | FAIL |
|
|
|
(8-30-16) See the circled items in the plan intake checklist and resolve those items as noted.
|
Application received | | | 8/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2016 4:14PM
|