First Notice | | 11/24/2016 | 1/4/2017 | | DONE |
|
|
|
Emailed in final value/first notice 1-4-17
|
Print Statement | | | 1/4/2017 | | DONE |
|
|
|
|
BLD-Final | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy | | | 11/14/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | FAIL |
Troy Cobbley
|
|
|
Install and test the duct smoke detector as per plan or provide approval for its removal. Provide annual inspection for the fire extinguisher. Provide address numbers as discussed.
|
BLD-Ceiling Grid Inspection | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | PASS |
Jim Sly
|
|
|
Barry Phone #: ###-####
|
BLD-Framing/Rough-in | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Mike Jordan
|
|
|
Berry Phone #: ###-####. Interior steel stud framed walls, hardlids and soffits ok.
|
BLD-Energy code compliance | 10/13/2016 | 10/13/2016 | 10/13/2016 | P | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/3/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/3/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/29/2016 | | |
|
|
|
|
Plan assigned to (JG) | 9/6/2016 | 9/6/2016 | 9/29/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 10/03 L3 Papa Murphy Level 3 E Plan
|
Routing - PLAN CHECK | 9/29/2016 | | 9/29/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/29/2016 | | DONE |
Christina Prado
|
|
|
***all requirments met 10-3-16 /CEV***
Need RP, GC Form & Revised Certificate of value for issuance
|
1st review completed | | | 9/28/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 9/6/2016 | | 9/28/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 9/6/2016 | | 9/12/2016 | | PASS |
Troy James
|
|
|
approved with redlines
|
Routing - FIRE | 9/6/2016 | 9/6/2016 | 9/8/2016 | | PASS |
Katie Marron
|
|
|
No cooking is done on site. Building shell was completed under BLD15-01601. No additional comments attached.
|
Routing PW Environmental | 9/6/2016 | | 9/7/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 9/6/2016 | | 9/7/2016 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Erosion and Sediment | 9/6/2016 | | 9/7/2016 | | PASS |
Andy J. Long
|
|
|
ESC site map with narrative approved. RP to be designated at time of permit issuance. Valid PD
|
Routing - Addressing | 9/6/2016 | | 9/6/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 9/6/2016 | | 9/6/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 9/6/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 8/30/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 30 2016 2:35PM
|