BLD-Final | 1/26/2017 | 1/26/2017 | 1/26/2017 | P | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 1/26/2017 | 1/26/2017 | 1/26/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 12/2/2016 | 12/5/2016 | 12/5/2016 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
BLD-Framing/Rough-in | 12/5/2016 | 12/5/2016 | 12/5/2016 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
BLD-Energy code compliance | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | FAIL |
Jim Sly
|
|
|
Brett Phone #: ###-#### Complete #1 on correction notice.
|
BLD-Framing/Rough-in | 11/30/2016 | 12/1/2016 | 12/1/2016 | A | FAIL |
Mike Jordan
|
|
|
Brett Phone #: ###-####. Complete lateral bracing on A3, A10 and A12 trusses. Provide purlin on top chord of A11,A10 and A8 trusses were roof sheathing has been left off. Correction notice posted. Ok to insulate.
|
BLD-Wall Bracing | 11/17/2016 | 11/17/2016 | 11/17/2016 | P | PASS |
Phil Shearer
|
|
|
Winston Phone #: ###-####
|
BLD-Foundation | 10/25/2016 | 10/26/2016 | 10/26/2016 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 10/24/2016 | 10/25/2016 | 10/25/2016 | P | PART |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/19/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/19/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/21/2016 | | |
|
|
|
|
Plan assigned to (DAF) | 9/7/2016 | 9/7/2016 | 9/21/2016 | | DONE |
David Ferguson
|
|
|
due 9/14 - Plan review complete - plan is mirrored, must be flipped.
|
Routing - PLAN CHECK | 9/21/2016 | | 9/21/2016 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/21/2016 | | DONE |
|
|
|
All Met
|
1st review completed | | | 9/15/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 9/1/2016 | | 9/15/2016 | | FAIL |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 9/1/2016 | | 9/7/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 9/1/2016 | | 9/6/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/1/2016 | | 9/1/2016 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 9/1/2016 | | 9/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 9/1/2016 | | 9/1/2016 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/1/2016 | | DONE |
|
|
|
|
Intake Approval | | | 9/1/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/1/2016 | | DONE |
|
|
|
|
Application received | | | 8/31/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 31 2016 2:36PM
|