Permit Information
Permit NumberBLD16-03242
StatusFinaled
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 351 N MITCHELL ST SUITE 300
Project NameFood Safety Net Services
Customer Number 
ePlanReviewYes
Description
(FOOD SAFETY NET SERVICES) ***Project Management-Angie Brosious***PRIORITY GREEN TAG REVIEW***New food safety laboratory and offices within an existing 8,475 sq. ft. space with work to include the addition of a 4,843 second story to include offices, training rooms and food testing facilities. This building is fully fire sprinklered for area increase. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 3/20/20173/16/2017 DONE
This permit finaled on the web by Brian McCoy
First Notice 2/19/20173/10/2017 DONE
sent in mail 3-13-17
BLD-Final2/9/20172/9/20172/9/2017PPASS
DetailsMike Jordan
All issues resolved. Ok for perm occ.
BLD-Final2/8/20172/9/20172/9/2017AFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. vertical grab bar not with in the 39 to 41 inch tolerance. Remove door hardware from inactive leaf of double doors.
Permanent Occupancy  2/9/2017 DONE
FIRE-Final Inspection2/7/20172/8/20172/8/2017PPASS
DetailsTroy Cobbley
Life safety passed. The appliances under the kitchen hood have not installed yet and therefore the project related hood suppression permit is not being inspected/finaled. The general contractor has been notified that the appliances/hood are not to be used until inspected/tested. There is a separate FIR for the suppression system that is not being finaled until work is complete that is not attached to this BLD permit.
FIRE-Final Inspection2/6/20172/7/20172/7/2017PFAIL
DetailsTroy Cobbley
Not ready for final yet. I did verify the fire extinguishers, door hardware and the exit signs/emergency lighting. Need the fire alarm and hood suppression permits/inspections prior to a building life safety sign off.
BLD-Conference2/3/20172/3/20172/3/2017PDONE
DetailsMike Jordan
BLD-Conference2/2/20172/3/20172/3/2017ACANC
DetailsMike Jordan
conference for Building and Safety Final Phone #: ###-#### Inspection requested via web by Todd Landvatter. Moved to pm.
BLD-Ceiling Grid Inspection1/31/20171/31/20171/31/2017PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter
BLD-Ceiling Grid Inspection1/28/20171/30/20171/30/2017APASS
DetailsMike Jordan
Remaining 2nd floor, main lab and incubators 1st floor. Phone #: ###-#### Inspection requested via web by Todd Landvatter
BLD-Ceiling Grid Inspection1/23/20171/24/20171/24/2017PPART
DetailsJim Sly
2nd floor Phone #: ###-#### Inspection requested via web by Todd Landvatter
Grid Ceiling OK except.....Halls, Storage, Electr, and Lab.
BLD-Ceiling Grid Inspection1/19/20171/20/20171/20/2017PPASS
DetailsMike Jordan
partial, downstairs. Phone #: ###-#### Inspection requested via web by Todd Landvatter. 1st. floor under mezz ok for tile.
BLD-Wall cover11/29/201611/29/201611/29/2016PPASS
DetailsMike Jordan
Fire calking elevator equipment room Phone #: ###-#### Inspection requested via web by Todd Landvatter
BLD-Framing/Rough-in11/23/201611/28/201611/28/2016APASS
DetailsMike Jordan
2nd floor framing. Elevator equipment room fire calking 1hr rating. Phone #: ###-#### Inspection requested via web by Todd Landvatter. 2nd. floor interior steel stud walls ok.
BLD-Framing/Rough-in11/19/201611/21/201611/21/2016PPASS
DetailsMike Jordan
rough framing south phase ground floor, and review stamped letter for 24 in OC framing in lieu of 16 in OC. Phone #: ###-#### Inspection requested via web by Todd Landvatter. North half framing, 1st. floor ok per letter from architect approving stud spacing at 14 inches o.c. South half framing, 1st floor ok, pending electrical and plumbing rough in inspections.
BLD-Framing/Rough-in11/17/201611/17/201611/17/2016PFAIL
DetailsDave Hannah
under mezzanine Phone #: ###-#### Inspection requested via web by Todd Landvatter plans call for 16 oc spacing framed at 24 oc
BLD-Conference11/15/201611/15/201611/15/2016ADONE
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Discussed phased inspections for framing and UL listings for 1hr. room.
BLD-Framing/Rough-in11/2/201611/2/201611/2/2016PDEFR
DetailsMike Jordan
Steel Mezzanine deck reinforcing and welding before concrete. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Will have special inspection.
BLD-Concrete10/26/201610/27/201610/27/2016ADEFR
DetailsMike Jordan
final lift grout elevator 11am. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Special inspector on site. Grout placement completed when arrived on site.
BLD-Concrete10/25/201610/26/201610/26/2016APART
DetailsMike Jordan
3rd grout lift elevator shaft at 11am. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Work in progress on elevator shaft, 16ft. elevation to 24ft. Will have special inspection. inspection.
BLD-Concrete10/24/201610/25/201610/25/2016APART
DetailsMike Jordan
second 8 foot grout lift @ 11am. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Work in progress for elevator shaft, 8ft. to 16ft. elevation, special inspector will be on site.
BLD-Concrete10/21/201610/24/201610/24/2016APART
DetailsMike Jordan
CMU grout 11 AM Phone #: ###-#### Inspection requested via web by Todd Landvatter. Work in progress on masonry elevator shaft, F.F. to 8ft. elevation, hight lift grout with cleanouts. Verified Letter from engineer of record approving high lift grouting.
BLD-Footing10/18/201610/19/201610/19/2016ADEFR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Concrete placed when arrived on site. reinforcement was inspected by special inspection.
BLD-Wall Bracing10/12/201610/13/201610/13/2016APART
DetailsMike Jordan
rebar CMU Elevator shaft Phone #: ###-#### Inspection requested via web by Todd Landvatter. Elevator pit to finish floor. Work in progress, needs to place vert. reinforcement. Will have special inspection.
BLD-Footing10/10/201610/11/201610/11/2016APASS
DetailsMike Jordan
late morning inspection for 1pm pour. Phone #: ###-#### Inspection requested via web by Todd Landvatter. F1 type column pad footings for new stairs ok. Work in progress on elevator pit reinforcing. ok t o place concrete after special inspection signs off.
OVERRIDE  10/6/2016  
Plan assigned to (CDM)9/8/20169/8/201610/6/2016 PASS
DetailsCarl D Madsen
First review completed Green Tag FSNA Testing Lab E Plan Level 3
Routing - PLAN CHECK10/4/2016 10/6/2016 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL10/4/2016 10/6/2016 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  10/6/2016 DONE
Permit Ready to Issue  10/6/2016 DONE
Needs; GC Form, Revised Cert of Value, RP
Issue PAID IN FULL permit  10/6/2016 DONE
Print Occupancy Form  10/6/2016 DONE
Routing - MECHANICAL10/4/2016 10/4/2016 PASS
DetailsTroy James
Route to Impact Fee Review9/25/20169/28/20169/29/2016 PASS
DetailsCindy M. Gould
Routing Off Site - STRUCTURAL9/8/2016 9/25/2016 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK9/8/2016 9/25/2016 FAIL
DetailsCarl D Madsen
1st review completed  9/25/2016 FAIL
Routing - FIRE9/13/20169/13/20169/13/2016 PASS
DetailsKatie Marron
Revised report and provided HMIS attached to case.
Routing - MECHANICAL9/8/2016 9/13/2016 FAIL
DetailsTroy James
Routing - FIRE9/8/20169/8/20169/9/2016 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing - Erosion and Sediment9/8/2016 9/9/2016 PASS
DetailsAndy J. Long
ESC plan waiver appproved.
Intake Approval  9/8/2016 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLUMBING9/8/2016 9/8/2016 PASS
DetailsDaryl Spivey
May require additional backflow protection. Install per ISPC.
Routing - Addressing9/8/2016 9/8/2016 PASS
DetailsLaura Hunter
Changed suite number to #130
Routing - PUBLIC WORKS9/8/2016 9/8/2016 PASS
DetailsRachael Beierle
Routing PW Environmental9/8/2016 9/8/2016 PASS
DetailsRick Christenson
Grease Traps Shown per conversation.
Routing PW Sewer Rating9/8/2016 9/8/2016 PASS
DetailsRachael Beierle
Intake Approval  9/2/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Donald,

I was assigned the prescreen for your project. Please complete and upload the 520 check list. Documents listed in the submitted check list are required to be up loaded. All documents need to be uploaded into the drawing folder.

I have deleted all of the submitted drawings to allow you to upload new one. All drawings need to be uploaded to read left to right. All drawings need to be labeled as indicated in the electronic submittal guidelines, A.0 Cover Sheet, A0.1 Floor Plan for example.

Please contact Christina Prado if you have any questions regarding our ePlan system.
Application received  9/1/2016 DONE
Application submitted via PDS Online on Sep 1 2016 1:56PM