Permanent Occupancy | | | 9/15/2016 | | DONE |
|
|
|
|
BLD-Final | 9/13/2016 | 9/14/2016 | 9/14/2016 | P | PASS |
Tony Young
|
|
|
Heidi-please call 30 mintues prior Phone #: ###-####
|
FIRE-Final Inspection | 9/9/2016 | 9/12/2016 | 9/12/2016 | P | PASS |
Katie Marron
|
|
|
Life Safety Pass.
|
Print Occupancy Form | | | 9/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/8/2016 | | DONE |
|
|
|
|
Telephone call | | | 9/8/2016 | | DONE |
|
|
|
called Heidi to let know permit is ready and that they will need CDHD and mechanical inspection as well as the fire and building
|
Issue PAID IN FULL permit | | | 9/8/2016 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 9/1/2016 | 9/1/2016 | 9/7/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/6/2016 | | 9/7/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/7/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/7/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/7/2016 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/1/2016 | | 9/6/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Environmental | 9/1/2016 | | 9/2/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Sewer Rating | 9/1/2016 | | 9/1/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 9/1/2016 | | 9/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/1/2016 | | DONE |
|
|
|
|
Intake Approval | | | 9/1/2016 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/1/2016 | | DONE |
|
|
|
|
First Notice | | 9/25/2016 | | | |
|
|
|
|
Application received | | 9/1/2016 | | | |
|
|
|
|