Permit Information
Permit NumberBLD16-03250
StatusFinaled
Name IRMINGER CONSTRUCTION INC
Site Address 4172 W QUAIL RIDGE DR
Project NameQuail Ridge Booster Station
Customer Number 
ePlanReviewYes
Description
(QUAIL RIDGE BOOSTER STATION – SUEZ WATER) (CUP16-00015) This building does not have a fire sprinkler system. To construct a new 302 square foot building to be used as a booster pumping station to replace an existing underground booster station at the Briar Hill tank site. Water will be pumped from the Briar Hill tank to the Quail Hill tank. This booster station will provide potable and irrigation water to homes in the upper elevations of Quail Ridge in addition to supplying service areas down the hill to the intersection of Hill Road and 36th Street. Work is to include concrete footings, concrete foundations, concrete slab on grade, a concrete thrust block structure, concrete pump pedestals, concrete equipment pad, masonry walls, glass block windows, exterior double leaf door, emergency shower and eyewash, wood joist roof structure, wood roof sheathing, noncombustible roof hatches, an awning above the exterior door, and a Class A roof covering. Keystone block retaining walls and a generator within a sound attenuating enclosure will be installed on site outside of the pump building. Special Inspection is required for concrete, masonry, welding, post installed anchors in concrete and masonry (if applicable), and soils. The work is required to comply with the approved drawings, with the structural calculations, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice6/26/20176/26/20177/12/2017 DONE
DetailsTony Young
Mailed 7-13-17
BLD-Final6/26/20176/26/20176/26/2017PPASS
DetailsTony Young
call for key location // Travis Phone #: ###-####
DOC - Permit Finaled6/26/20176/26/20176/26/2017PPASS
DetailsTony Young
BLD-Framing/Rough-in2/17/20172/21/20172/21/2017APASS
DetailsTony Young
Dave Phone #: ###-####-late as possible,, roof frame ok
BLD-Framing/Rough-in2/16/20172/17/20172/17/2017PPART
DetailsTony Young
Dave Phone #: ###-####-late as possible,, need trades,, need a-35 at each block
BLD-Footing12/16/201612/19/201612/19/2016PPART
DetailsTony Young
travis Phone #: ###-####,, ok pending special inspection
Issue PAID IN FULL permit  11/3/2016 DONE
Print Occupancy Form  11/3/2016 DONE
(F) Reprint permit  11/3/2016 DONE
OVERRIDE  11/1/2016  
Permit Ready to Issue  11/1/2016 DONE
***all requirments met 11-3-16 /CEV

Need GC Form and Revised Cert of Value ***NO ACHD PER CARL W BUILDING FOR PUMPING EQUIPMENT***
Plan assigned to (CJW)9/27/20169/27/201610/31/2016 PASS
DetailsCarl Westfall
(1st done) (Oct 17 - 15 days) Suez pump station
PLANS/APPL TAKEN TO FRONT DESK  10/31/2016 DONE
Routing PW Drainage10/26/2016 10/31/2016 PASS
DetailsJason C. Taylor
No review required as all drainage will remain the same. Exterior french drain is for interior floor drain only. JCT
Routing - PLAN CHECK10/26/2016 10/26/2016 PASS
DetailsCarl Westfall
Drawings approved with redlines
Plan resubmittals received  10/26/2016 DONE
Route to Impact Fee Review10/10/201610/13/201610/10/2016 PASS
DetailsCindy M. Gould
Routing PW Environmental9/27/2016 10/10/2016 PASS
DetailsRick Christenson
1st review completed  10/10/2016 DONE
Plan resubmittals requested  10/10/2016 DONE
Routing Off Site - STRUCTURAL9/27/2016 10/9/2016 PASS
DetailsCarl Westfall
Dave Haugland - AHJ Engineers
Routing - PLAN CHECK9/27/2016 10/8/2016 FAIL
DetailsCarl Westfall
Revised drawings required.
Routing - PLANNING Land Div9/27/2016 10/6/2016 PASS
DetailsTodd Tucker
Routing PW Sewer Design9/27/2016 10/4/2016 PASS
DetailsKyle S. Rosenmeyer
No review required.
Routing - Erosion and Sediment9/27/2016 9/29/2016 PASS
DetailsAndy J. Long
ESC plan with narrative site map submitted and approved. Valid PD and RP designated. Site preparation inspection required, call ###-#### or ###-####
Routing - PLUMBING9/27/2016 9/29/2016 PASS
DetailsBill VanDegrift
floor drainage to french drain
Routing - FIRE9/27/20169/27/20169/28/2016 PASS
DetailsScott Arellano
No comments required.
Routing PW Drainage9/27/2016 9/28/2016 FAIL
DetailsJason C. Taylor
See changemarks in ePlan. JCT
Routing - Addressing9/27/2016 9/27/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS9/27/2016 9/27/2016 PASS
DetailsRachael Beierle
Routing - PLANNING9/27/2016 9/27/2016 PASS
DetailsCeline Acord
approved per CUP16-00015
Routing - MECHANICAL9/27/2016 9/27/2016 PASS
DetailsTroy James
Intake Approval  9/27/2016 PASS
Plan Reviewer's activity  9/23/2016 PASS
Plan intake review approved
Intake Approval  9/22/2016 FAIL
DetailsCarl Westfall
(9-22-16) Please see the circled items in the plan intake checklist and resolve each item as noted.
Application received  9/2/2016 DONE
Application submitted via PDS Online on Sep 2 2016 9:15AM