Permit Information
Permit NumberBLD16-03292
StatusFinaled
Name OKLAND CONSTRUCTION CO INC
Site Address 1101 W FRONT ST
Project NameParcel B Parking Garage
Customer Number 
ePlanReviewYes
Description
(PARCEL B PARKING GARAGE) **PROJECT MANAGEMENT - Angie Brosious** **PLAN MODIFICATION 3 TO ADD AN ADDITIONAL TIER TO THE STRUCTURE. Stand pipe fire protection shall be extended to this additional level. Separate fire protection permits are requried.** PLAN MODIFICATION #2 FOR BELOW SLAB PLUMBING AND ELECTRICAL CONDUITS."" ""MODIFICATION CHANGING THE INTERIOR SLOPE OF THE GARAGE FLOOR AND INTERIOR DRAINAGE PLUMBING"" Permit for the construction of a 228,548 sq. ft., 4 tier parking garage including 13,392 sq. ft. of office area on the first story to be type IB construction with work to in garage construction and general site grading and utilities per the approved plans and any notations. The office requires a separate permit for the tenant improvement and occupancy of this area. This building is to be fully fire sprinklered per NFPA 13. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  3/3/2020 DONE
Meeting  2/7/2020 DONE
Recalculated final value giving credit for entire project BLD16-03292, BLD16-04329, BLD18-03311, GRD16-00081. Final Value fees went from approx 15k to $7,729.46. Emailed Jeff Harden with Okland final statement.
Print Statement  2/7/2020 DONE
emailed updated statement to Jeff Harden at Okland. Jeff.Harden@okland.com
Telephone call  2/6/2020 DONE
left message to GC at ###-#### to inform him of the outstanding fees that are still due.
Print Statement  1/10/2020 DONE
emailed to Jeff Harden w/Okland Const
Telephone call  1/9/2020 DONE
Replied to Bens email to check on the copy of the values his company provided to us and to inform him that their is still remaining fees due.
Telephone call  12/11/2019 DONE
Spoke with Ben about final vaules/fees that are past due. He requested I email him at ben.petzinger@okland.com the fees due and the final values that were sent in.
Print Statement  5/1/2019 DONE
Print Statement  2/5/2019 DONE
Meeting  1/16/2019 DONE
sent emails to Leslie Schulz to verify on the final values that were sent in.
Print Statement  1/10/2019 DONE
Meeting  12/21/2018 DONE
emailed leslie asking her to please provide the final value on mechanical and fire alarm system
Third Notice 11/12/201812/14/2018 DONE
mailed 12-17
Second Notice 10/22/201811/7/2018 DONE
mailed 11-12
First Notice 9/23/201810/12/2018 DONE
mailed 10-15-18
Permanent Occupancy  9/13/2018 DONE
BLD-Final9/11/20189/12/20189/12/2018PPASS
DetailsDave Hannah
Jeff Phone #: ###-####
OVERRIDE  9/11/2018  
Plan assigned to (CDM)9/10/20189/10/20189/11/2018 PASS
DetailsCarl D Madsen
Per Angie - need to remove plan mod from this permit and create a new BLD instead. Sun Shades removed from this permit and transfered to separte permit BLD18-03311.
Routing - PLAN CHECK9/11/2018 9/11/2018 PASS
DetailsCarl D Madsen
Permit Ready to Issue  9/11/2018 DONE
CHANGE STATUS TO (ISS)  9/11/2018 DONE
OVERRIDE  9/5/2018  
Plan assigned to (CDM)8/16/20188/16/20189/5/2018 PASS
DetailsCarl D Madsen
Plan Mod 4 - Add sun shades to the NE Stair Tower at 11th & Front SUNSHADES REMOVED FROM THIS PERMIT
Routing - PLAN CHECK8/22/2018 9/5/2018 PASS
DetailsCarl D Madsen
Permit Ready to Issue  9/5/2018 DONE
PLAN MOD
Routing - PLANNING8/22/2018 8/23/2018 PASS
DetailsCody Riddle
Plan Modification Accepted  8/16/2018 DONE
Plan Mod 4 - add sun shades to the NE Stair Tower at 11th & Front
PubWorks Occupancy Approval8/14/20188/14/20188/14/2018 DONE
DetailsTiffany Lowery
Zoning Approval8/1/20188/1/20188/1/2018 DONE
DetailsAndrea Tuning
Approved per Derick O'Neil
FIRE-Final Inspection7/23/20187/24/20187/24/2018APASS
DetailsJim Page
Final life fire safety inspection complete.

Jeff Phone #: ###-####
Temporary Occupancy7/19/201810/17/20187/19/2018 DONE
DetailsCandy A. Nichols
Jason B ok'd ext on temp c of o good for 60 days from expiration
BLD-Aging Inspection7/16/20187/16/20187/18/2018 PEND
DetailsDave Hannah
Telephone call  7/17/2018 DONE
called Ben-to let know TCO will expire on 7-31-18-left message on his phone
BLD-Aging Inspection4/18/20184/18/20184/24/2018 PEND
DetailsDave Hannah
Temporary Occupancy4/4/20187/3/20184/4/2018 DONE
DetailsCandy A. Nichols
Jason B ok'd 90 day extension on Temp starting from 5/1/18
BLD-Final2/5/20182/5/20182/6/2018PPEND
DetailsDave Hannah
JEFF - DAVE DID WALKTHRU ON FRI - WANTS TO COME BACK TO CHECK STAIRWELLS Phone #: ###-#### ok for temp occ stir towers cleaned up
BLD-Final1/31/20182/1/20182/1/2018APART
DetailsDave Hannah
Late morning after life/safety - Levels 2-5 TCO approval - Jeff Phone #: ###-#### ok for TCO
FIRE-Final Inspection1/31/20182/1/20182/1/2018APART
DetailsJim Page
Previously noted items have been addressed, temp signs are in place for fire alarm control panel, fire sprinkler riser room and FDC/Standpipe details. Temp fill has been put in place for stairwell door windows. Life fire safety inspection for TCO request complete. Stairwells are not to be used as storage after this inspection.
Temporary Occupancy2/1/20185/2/20182/1/2018 DONE
DetailsChristina Prado
FIRE-Final Inspection1/30/20181/31/20181/31/2018AFAIL
DetailsJim Page
Emergency lighting that did not operate needs to be repaired and retested. Signage needs to be installed on the fire panel control room, the fire sprinkler riser room as well as signage for the dry standpipe with dry standpipe info mounted by the FDC location. Mount fire extinguishers in discussed locations and provide inspection tags for each fire extinguisher. Remove storage/combustible material from stairwells. Install glass in stairwell doors.
BLD-Final1/26/20181/29/20181/31/2018PPEND
DetailsDave Hannah
levels 2-5 - jeff Phone #: ###-####
BLD-Final1/30/20181/31/20181/31/2018PCANC
DetailsDave Hannah
Jeff Phone #: ###-####
FIRE-Final Inspection1/30/20181/31/20181/31/2018PDONE
DetailsJim Page
levels 2-5- later afternoon- Jeff Phone #: ###-####
Print Occupancy Form  1/24/2018 DONE
BLD-Final1/16/20181/17/20181/17/2018ADONE
DetailsDave Hannah
TCO - Robert Phone #: ###-####
BLD-Final1/11/20181/16/20181/17/2018PPART
DetailsDave Hannah
Robert Phone #: ###-####phase 1 ground floor only ok
Temporary Occupancy1/17/20184/17/20181/17/2018 DONE
DetailsChristina Prado
Zoning Approval Temp1/17/20181/17/20181/17/2018 PASS
DetailsSarah Schafer
Ground Floor Temporary only.
FIRE-Final Inspection1/11/20181/16/20181/16/2018APART
DetailsJim Page
Partial final inspection complete for level 1 parking, ry standpipe inspection complete for levels 1, 2 and 3, fire alarm inspection complete for level 1, fire extinguishers are in place for level 1, permit will remain in issued status until completion of project.
BLD-Framing/Rough-in1/5/20181/8/20181/8/2018PPEND
DetailsDave Hannah
Robert Phone #: ###-####
Print Occupancy Form  1/5/2018 DONE
DetailsChristina Prado
BLD-Framing/Rough-in11/29/201711/30/201712/5/2017APASS
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Conference10/26/201710/26/201710/27/2017PDONE
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Other10/16/201710/18/201710/24/2017APART
DetailsDave Hannah
rebar // Robert Phone #: ###-#### ok met with al from mti
CHANGE STATUS TO (ISS)  9/12/2017 DONE
(F) Reprint permit  9/12/2017 DONE
Plan assigned to (CDM)7/31/20177/31/20178/23/2017 PASS
DetailsCarl D Madsen
Routing - Design Review8/20/2017 8/23/2017 PASS
DetailsSarah Schafer
Approved per modification.
Permit Ready to Issue  8/23/2017 DONE
DO NOT REISSUE PLAN MOD
Routing Off Site - STRUCTURAL7/31/2017 8/20/2017 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK7/31/2017 8/20/2017 PASS
DetailsCarl D Madsen
BLD-Foundation8/16/20178/17/20178/18/2017APEND
DetailsDave Hannah
Rebar // Robert Phone #: ###-####
Routing - FIRE7/31/20177/31/20178/7/2017 PASS
DetailsScott Arellano
Attached revised plan review comments to case.
Routing - PLUMBING7/31/2017 8/1/2017 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing - Design Review7/31/2017 8/1/2017 FAIL
DetailsSarah Schafer
Design Review Modification approval needed prior to building permit sign off. Hearing is 8/9/17.
Routing - PLANNING7/31/2017 7/31/2017 PASS
DetailsCody Riddle
Plan Modification Accepted  7/31/2017 DONE
Plan mod work flow started for addition to add a 5th level to a 4-story parking garage that is currently under construction. The building was originally designed to have 2 additional stories, so the original design accommodated for this modification.
BLD-Foundation4/25/20174/26/20175/4/2017APASS
DetailsDave Hannah
Robert Phone #: ###-####
(F) Reprint permit  4/25/2017 DONE
CHANGE STATUS TO (ISS)  4/25/2017 DONE
BLD-Foundation4/17/20174/19/20174/21/2017APEND
DetailsDave Hannah
Robert-rebar Phone #: ###-#### signed off by spec inspection
BLD-Foundation4/3/20174/4/20174/4/2017APASS
DetailsDave Hannah
Rebar // Robert Phone #: ###-####
Plan assigned to (CDM)3/24/20173/24/20174/4/2017 PASS
DetailsCarl D Madsen
routed to Plumbing, Mechanical and Building plan mod accepted in e plan
Routing - PLAN CHECK3/24/2017 4/4/2017 PASS
DetailsCarl D Madsen
Permit Ready to Issue  4/4/2017 DONE
DO NOT RE ISSUE
BLD-Foundation3/28/20173/30/20173/30/2017APEND
DetailsDave Hannah
Robert Phone #: ###-####
BLD-Foundation3/23/20173/29/20173/30/2017APEND
DetailsDave Hannah
Rebar // Robert Phone #: ###-#### ok after spec inspection sign off
Routing - MECHANICAL3/24/2017 3/27/2017 PASS
DetailsTroy James
no review required
Routing - PLUMBING3/24/2017 3/27/2017 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Plan Modification Accepted  3/24/2017 DONE
plan mod accepted in e plan
BLD-Foundation3/16/20173/17/20173/17/2017APASS
DetailsDave Hannah
Rebar // Rob Phone #: ###-####
BLD-Foundation2/16/20172/17/20172/17/2017APART
DetailsJim Storey
Rebar // Robert Phone #: ###-#### placed w/si
Print Occupancy Form  2/15/2017 DONE
CHANGE Issued DATE  2/10/2017 DONE
DetailsRita DeYoung
Issue PAID IN FULL permit  2/10/2017 DONE
Print Occupancy Form  2/10/2017 DONE
CHANGE STATUS TO (RDY)  2/10/2017 DONE
DO NOT REISSUE. Architect said he was with Okland and then when haded the permit asked if he was allowed to sign because he's the architect. He called Okland and they want to sign for permit
Plan assigned to (CDM)1/26/20171/26/20172/8/2017 PASS
DetailsCarl D Madsen
Plan mod per Angie route to Carl M. and Bill V.
Routing - PLAN CHECK1/26/2017 2/8/2017 PASS
DetailsCarl D Madsen
Plan mod per Angie route to Carl M. and Bill V.
Routing PW Sewer Design1/30/2017 2/8/2017 PASS
DetailsKyle S. Rosenmeyer
Permit Ready to Issue  2/8/2017 DONE
DetailsChristina Prado
All met
Routing - PUBLIC WORKS1/27/2017 1/30/2017 PASS
DetailsRachael Beierle
Routing - PLUMBING1/26/2017 1/26/2017 PASS
DetailsBill VanDegrift
Plan mod for change to drains/underground plumbing sheet P2.1
Plan Modification Accepted  1/26/2017 DONE
Plan mod per Angie route to Carl M. and Daryl S.
Meeting  1/5/2017 DONE
cstomer came in and paid fees but we're still waiting for the RP and ACHD so i did not issue permit
OVERRIDE  12/29/2016  
Plan assigned to (CDM)10/27/201610/27/201612/29/2016 PASS
DetailsCarl D Madsen
Parcel B Parking Garage First review completed.
Routing - PLANNING10/27/2016 12/29/2016 PASS
DetailsCarl D Madsen
Routing PW Street Lights12/6/2016 12/29/2016 PASS
DetailsTom Marshall
per E-plan
Routing - Design Review12/29/2016 12/29/2016 PASS
DetailsCarl D Madsen
Routing - PUBLIC WORKS12/29/2016 12/29/2016 PASS
DetailsRachael Beierle
Routing PW Sewer Design12/29/2016 12/29/2016 PASS
DetailsKyle S. Rosenmeyer
Routing - PLAN CHECK12/29/2016 12/29/2016 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  12/29/2016 DONE
Permit Ready to Issue  12/29/2016 DONE
Needs- RP & ACHD Approval
Routing PW Sewer Design12/22/2016 12/27/2016 FAIL
DetailsKyle S. Rosenmeyer
11/7 Comments not addressed.
Routing - PLAN CHECK12/22/2016 12/27/2016 PASS
DetailsCarl D Madsen
Routing PW Street Lights12/22/2016 12/23/2016 PASS
DetailsTom Marshall
Routing - FIRE12/22/201612/22/201612/22/2016 PASS
DetailsScott Arellano
Garage WILL NOT BE sprinklered. Revised report attached to case.
Routing - PUBLIC WORKS12/22/2016 12/22/2016 PASS
DetailsRachael Beierle
Routing - PUBLIC WORKS12/6/2016 12/22/2016 PASS
DetailsRachael Beierle
Routing PW Drainage12/22/2016 12/22/2016 PASS
DetailsBrian Murphy
For parking bld only
Routing PW Drainage10/28/2016 12/20/2016 FAIL
DetailsBrian Murphy
NEED achd ok plus calcs
Routing - PLAN CHECK12/6/2016 12/17/2016 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL12/6/2016 12/17/2016 PASS
DetailsCarl D Madsen
Routing - FIRE12/15/201612/15/201612/15/2016 FAIL
DetailsKatie Marron
Resubmittals indicated garage is not intended to be sprinklered. It is required based on fire area and fire flow available. Email was sent to architect.
Routing PW Sewer Design12/6/2016 12/15/2016 FAIL
DetailsKyle S. Rosenmeyer
No comments appear to be addressed.
Routing PW Solid Waste12/6/2016 12/12/2016 PASS
DetailsEvan Carpenter
Solid waste is OK as planned.
Route to Impact Fee Review11/26/201611/29/201611/29/2016 PASS
DetailsCindy M. Gould
1st review completed  11/26/2016 FAIL
Plan review attached
Routing Off Site - STRUCTURAL10/27/2016 11/26/2016 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK10/27/2016 11/26/2016 FAIL
DetailsCarl D Madsen
Routing PW Environmental10/28/2016 11/10/2016 PASS
DetailsRick Christenson
Routing PW Street Lights10/28/2016 11/9/2016 FAIL
DetailsTom Marshall
See comments in eplan
Routing - Design Review10/27/2016 11/9/2016 PASS
DetailsJosh Wilson
Routing PW Sewer Design10/28/2016 11/7/2016 FAIL
DetailsKyle S. Rosenmeyer
Label existing manhole connection in Myrtle St. SSMH 68A1. Core drill SSMH 68A1 and provide Kor-N-Seal boot to create water tight connection. Rechannel manhole to provide smooth flow line. Label both in/out inverts on sewer manhole and indicate grade adjustment of lid (if applicable). Label new SSMH "SSMH 71A3". Also label the upstream/north manhole (71A2) and the downstream/south manhole (71A1). New manhole must have pre-cast base. CCTV up and downstream line segments upon completion and provide video records to Boise Public Works. GENERAL: Label all manhole angles and manhole inverts. Contact Boise Public Works 48 hours prior to construction to obtain tap permits and schedule inspection.
Routing - FIRE10/27/201610/27/201611/3/2016 PASS
DetailsKatie Marron
Revised plan received before initial review complete. Revised report attached to case
Routing - PLUMBING10/27/2016 11/1/2016 PASS
DetailsBill VanDegrift
SOI-1 shall be vented seperately from any othe vent piping.
Per plan and ISPC.
Routing - PLANNING Land Div10/27/2016 10/31/2016 PASS
DetailsTodd Tucker
Routing - MECHANICAL10/27/2016 10/31/2016 PASS
DetailsTroy James
Routing PW Solid Waste10/28/2016 10/31/2016 FAIL
DetailsEvan Carpenter
There needs to be 12’ of clearance between the gate posts on the solid waste enclosure to ensure that the dumpster can be serviced properly.

Additionally, you must have a way to service the solid waste needs of the parking garage separate from the other phases of the project. As currently planned, the parking garage has no way for solid waste to be removed once it is constructed.
Routing PW Geothermal10/28/2016 10/28/2016 CANC
DetailsJon R. Gunnerson
No review needed
Routing - Addressing10/27/2016 10/28/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS10/27/2016 10/28/2016 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment10/27/2016 10/28/2016 PASS
DetailsAndy J. Long
ESC16-01354 previously issued for Pioneer Crossing project. ESC plan reviewed with GRD16-00078. No new/duplicate ESC permit required.
Intake Approval  10/27/2016 PASS
Intake Approval  10/26/2016 FAIL
Second pre-screen 10/26/16 Carl Madsen
Please provide or correct the following items.
1. Verification of legal lot and parcel completed and signed by the planning land division.
2. Form 310 Special inspection start-up form signed and stamped by the engineer of record.
3. Erosion and sediment control narrative.
4. Remove the not for construction stamps from all plan sheets. It appears that this stamp is confined to the civil sheets
5. Specification manual that is reference on the plans and the checklist.
6. Electrical sheets and related lighting compliance forms.
Intake Approval  9/27/2016 FAIL
Plan resubmittals requested  9/23/2016 DONE
Requested a intake checklist from Angie on 9/23/16. She asked that we not fail the pre-screen for a few days. CDM
Application received  9/7/2016 DONE
Application submitted via PDS Online on Sep 7 2016 1:21PM