Permit NumberBLD16-03302
StatusExpired
Name DALE BINNING
Site Address 8200 S EISENMAN RD
Project NameTrinity Trailers - #3
Customer NumberBLD16-01532 AND 03301
ePlanReviewNo
Description
**see attached ACHD***(TRINITY TRAILERS - Detached accessory Membrane Structures) Permit to construct three membrane structures on an existing lot. Each structure is approximatly 2,520 square feet creating a combined square feet of 7,560. Note: these structures were permitted without a permit and are now going through the process to permit these as new structures. **TLW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan assigned to (AJS)8/24/20168/24/20166/21/2019 DONE
DetailsAdele J Schaffeld-Griffin
Trinity Trailers 1st review completed by Tim
See BLD16-01532
Permit EXPIRED  6/21/2019 DONE
DetailsAdele J Schaffeld-Griffin
Membrane for structure has been removed, structure still stands. Permit application expired per city ordinance. Will need to submit new permit and pay fees to move forward.
BLD-Conference6/12/20187/12/20187/11/2018APEND
DetailsBob Archibald
Membrane status? No change in status. No new permit applications received.
BLD-Conference6/11/20186/11/20186/11/2018APEND
DetailsBob Archibald
The membranes have been removed from the three structures. I spoke with the manager and architect yesterday and they plan on deciding a course of action to make the structures legal by engineering frames and getting an approved membrane or replacing entire assemblies with an approved product. They requested a time of 30 days to submit there proposal. Chris @ ###-####.
BLD-Conference6/7/20186/7/20186/7/2018ADONE
DetailsBob Archibald
Conference with Architect and site manager. Membrane removal has been authorized and is currently being removed from frames.
BLD-Conference6/6/20186/6/20186/6/2018PDONE
DetailsBob Archibald
Conference with site managers, structures posted and CN issued for failure to comply with previous Notice and Orders
Extend Review Timeline  6/5/2017 DONE
1st approved extension per Adele. See documents
Recd Pcfee & Taken To Pln CK  9/8/2016 DONE
See BLD16-01532
Plan assigned to (TLW)5/13/2016 8/24/2016 DEFR
DetailsTim L. Woodard
1st review completed.
See BLD16-01532
Route to Impact Fee Review8/10/20168/13/20168/11/2016 PASS
DetailsCindy M. Gould
See BLD16-01532
1st review completed  5/19/2016 FAIL
DetailsTim L. Woodard
See BLD16-01532
Routing - FIRE5/18/2016 5/19/2016 FAIL
DetailsScott Arellano
Emailed comments to applicant and posted comments to case.
See BLD16-01532
Routing - PLAN CHECK5/17/2016 5/18/2016 FAIL
DetailsTim L. Woodard
See BLD16-01532
Routing - Design Review5/16/2016 5/17/2016 PASS
DetailsJosh Wilson
Routing PW Drainage5/16/2016 5/16/2016 FAIL
DetailsRachael Beierle
SEE BRIAN MURPHY FOR DETAILS. See BLD16-01532
Routing PW Sewer Rating5/16/2016 5/16/2016 PASS
DetailsRachael Beierle
See BLD16-01532
Routing - PUBLIC WORKS5/16/2016 5/16/2016 FAIL
DetailsRachael Beierle
see Brian Murphy for failed drainage. See BLD16-01532
Routing - Addressing5/13/2016 5/13/2016 PASS
DetailsLaura Hunter
Pending Assignment by TLW5/4/2016 5/13/2016 DONE
DetailsTim L. Woodard
See BLD16-01532
Routing Off Site - STRUCTURAL5/4/2016 5/13/2016 FAIL
DetailsTim L. Woodard
Emailed letter to owner and applicant. TLW
See BLD16-01532
Plans ACCEPTED BY PLAN TECH  5/4/2016 DONE
See BLD16-01532
Intake Approval  5/4/2016 PASS
DetailsCarlos Velazquez
Per Javier See BLD16-01532
Application received 5/3/2016   
See BLD16-01532
Routing - PLAN CHECK5/19/2016    
See BLD16-01532