BLD-Final | 4/14/2017 | 4/14/2017 | 4/14/2017 | P | DONE |
Tony Young
|
|
|
Phone #: ###-####
|
DOC - Permit Finaled | 4/14/2017 | 4/14/2017 | 4/14/2017 | P | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | CANC |
Dave Hannah
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
BLD-Final | 4/11/2017 | 4/11/2017 | 4/11/2017 | P | CANC |
Dave Hannah
|
|
|
John Phone #: ###-####
|
Zoning Approval | 4/10/2017 | 4/10/2017 | 4/10/2017 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Final | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | NR |
Dave Hannah
|
|
|
Ed Phone #: ###-#### needs zoning final first
|
BLD-Energy code compliance | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PASS |
Tony Young
|
|
|
John Phone #: ###-####,, house ok
|
BLD-Framing/Rough-in | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Tony Young
|
|
|
John Phone #: ###-####,, house ok
|
CHANGE STATUS TO (ISS) | | | 1/17/2017 | | DONE |
|
|
|
Case summary was pulled and put permit back in REV status
|
BLD-Framing/Rough-in | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PART |
Tony Young
|
|
|
Phone #: ###-####,, house addition frame inspection,, ok to insulate
|
BLD-Foundation | 12/5/2016 | 12/6/2016 | 12/6/2016 | A | PASS |
Dave Hannah
|
|
|
Greg Phone #: ###-#### garage ok
|
BLD-Footing | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PASS |
Tony Young
|
|
|
John Phone #: ###-####,, garage ftg ok
|
BLD-Foundation | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PART |
Jim Sly
|
|
|
Avarro Phone #: ###-#### Basement walls......OK.
|
BLD-Foundation | 11/8/2016 | 11/9/2016 | 11/9/2016 | P | PASS |
Mike Jordan
|
|
|
Avarro Phone #: ###-####-pour time 1:00. Footing for basement wall.
|
OVERRIDE | | | 9/20/2016 | | |
|
|
|
|
Routing Walk-In (BLD) | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 9/20/2016 | 9/20/2016 | 9/20/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 9/20/2016 | | 9/20/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 9/20/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 9/20/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/20/2016 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 9/20/2016 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | PASS |
Josh Wilson
|
|
|
Ok per DRH16-00314.
|
Routing Walk-In (BLD) | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | FAIL |
David Ferguson
|
|
|
Need wall bracing plan, portal frame detail, rebar schedule for new basement walls.
|
1st review completed | | | 9/8/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 9/8/2016 | | 9/8/2016 | | FAIL |
David Ferguson
|
|
|
|
Application received | | 9/8/2016 | | | |
|
|
|
|