Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD16-03317
StatusFinaled
Name STOCK CONSTRUCTION MANAGEMENT
Site Address 5796 E MILLET DR
Project NameMair Residence
Customer Number 
ePlanReviewYes
Description
WUI Zone A, Class A roof required** Permit for the construction of a new 2966 sq. ft., two story (first story 1786 sq. ft., second story 1180 sq. ft.) single family dwelling with 3 bedrooms, 3.5 bathrooms, approximately 473 sq. ft. of covered patio/porch and a 1885 sq. ft. attached garage per the approved plans, and any notations. R-1C zoning and setbacks per planning. **DAF** This structure is required to be fire sprinlered in accordance with NFPA 13D; per Fire Department conditions (CFH16-00047). A separate fire sprinkler permit will be required. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/30/201712/1/201711/30/2017APASS
DetailsBrandon Shaw
Dining room/patio sliding door and Master bedroom slider, at final, permanent locks (tools required) had been installed.
Rear patio/deck to be permited and installed at a later time
DOC - Permit Finaled11/30/201711/30/201711/30/2017PPASS
DetailsBrandon Shaw
PubWorks Occupancy Approval11/30/201711/30/201711/30/2017 DONE
DetailsJason C. Taylor
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
BLD-Final11/21/201711/21/201711/21/2017PNR
DetailsBrandon Shaw
James Phone #: ###-####
BLD-Energy code compliance7/27/20177/28/20177/28/2017PPASS
DetailsBrandon Shaw
James Phone #: ###-####
BLD-Framing/Rough-in7/25/20177/26/20177/26/2017APART
DetailsBrandon Shaw
See corection notice
Need revised Engineering for missing beams
BLD-Energy code compliance7/25/20177/25/20177/25/2017PNR
DetailsBrandon Shaw
Need framing rough-in prior to energy code.
BLD-Wall Bracing7/24/20177/24/20177/24/2017PPART
DetailsBrandon Shaw
Blocking for garage wall done
Nail header and hold down at North( main entry steps) wall
BLD-Wall Bracing7/21/20177/21/20177/21/2017PFAIL
DetailsBrandon Shaw
See correction notice and red crayon
BLD-Conference1/6/20171/9/20171/9/2017APASS
DetailsPhil Shearer
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Foundation1/9/20171/9/20171/9/2017PPASS
DetailsPhil Shearer
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Foundation12/29/201612/30/201612/30/2016AFAIL
DetailsPhil Shearer
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro. Only 9 degrees no heat.
BLD-Footing12/15/201612/16/201612/16/2016APART
DetailsPhil Shearer
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro.
PubWorks Subgrade Approval12/16/201612/16/201612/16/2016 DONE
DetailsJason C. Taylor
**Perimeter footings only***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
FIRE-Conference11/23/201611/23/201611/23/2016PDONE
DetailsKatie Marron
Discussion with homeowner: revised driveway meets grade requiremet for FD Access per Assistant Fire Marshall. No sprinkleres are required.
Issue PAID IN FULL permit  11/15/2016 DONE
Inspection Record Card- Bld  11/15/2016 DONE
OVERRIDE  11/9/2016  
Plan assigned to (DAF)10/7/201610/7/201611/9/2016 DONE
DetailsDavid Ferguson
due 10/18 - plan review #2 failed - eng. stamp on page A-2
Routing PW Grading-Hillside11/9/2016 11/9/2016 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
PLANS/APPL TAKEN TO FRONT DESK  11/9/2016 DONE
Permit Ready to Issue  11/9/2016 DONE
All requirements met
Routing - PLAN CHECK11/1/2016 11/1/2016 PASS
DetailsDavid Ferguson
Routing PW Grading-Hillside10/24/2016 10/24/2016 FAIL
DetailsJason C. Taylor
See changemark in ePlan. JCT
Routing - MECHANICAL10/18/2016 10/18/2016 PASS
DetailsTroy James
redlined plans
Routing - PLAN CHECK10/18/2016 10/18/2016 FAIL
DetailsDavid Ferguson
Need engineers stamp on page A-2
Routing - PLANNING10/5/2016 10/17/2016 PASS
DetailsSusan Riggs
CFH16-00047
Routing PW Grading-Hillside10/5/2016 10/14/2016 FAIL
DetailsJason C. Taylor
Upload new grading plans.
1st review completed  10/11/2016 FAIL
DetailsDavid Ferguson
Routing - PLAN CHECK10/5/2016 10/11/2016 FAIL
DetailsDavid Ferguson
Plan assigned to (LEG) Tisha10/5/2016 10/7/2016 DEFR
DetailsTisha Gallop
Routing - FIRE10/5/201610/5/201610/5/2016 PASS
DetailsKatie Marron
THIS STRUCTURE IS REQUIRED TO BE FIRE SPRINKLERED IN ACCORDANCE WITH NFPA13D, DUE TO LIMITED FD ACCESS AND DRIVEWAY SLOPE. AS STATED UNDER CFH16-00047). A SEPARATE FIRE PERMIT WILL BE REQUIRED.
Routing - MECHANICAL10/5/2016 10/5/2016 FAIL
DetailsTroy James
Left message with James with stock const.
Routing - Addressing10/5/2016 10/5/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS10/5/2016 10/5/2016 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment10/5/2016 10/5/2016 PASS
DetailsAndy J. Long
ESC plan submitted and approved. Valid RP and PD desingated.
Plans ACCEPTED BY PLAN TECH  10/5/2016 DONE
Intake Approval  10/5/2016 PASS
Recd Pcfee & Taken To Pln CK  10/5/2016 DONE
Intake Approval  9/26/2016 FAIL
DetailsChristina Prado
Must wait until appeal period is up - 9-29-16 at 5PM
Application received  9/8/2016 DONE
Application submitted via PDS Online on Sep 8 2016 4:45PM