Print Statement | | | 10/20/2017 | | DONE |
|
|
|
|
Second Notice | | 9/29/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
First Notice | | 8/24/2017 | 9/19/2017 | | DONE |
|
|
|
Mailed 9-20-17
|
BLD-Final | 8/11/2017 | 8/14/2017 | 8/14/2017 | A | PASS |
Mike Jordan
|
|
|
Harvey Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 8/14/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/9/2017 | 8/10/2017 | 8/10/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide single action hardware on doors with locks prior to a building inspection.
|
BLD-Final | 8/9/2017 | 8/9/2017 | 8/9/2017 | P | NR |
Mike Jordan
|
|
|
harvey Phone #: ###-#### - call for access code. Needs fire/life/safety fianl first.
|
BLD-Ceiling Grid Inspection | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Mike Jordan
|
|
|
Harvey Phone #: ###-####. Base layer 5/8 type x rock ok on 1hr. roof/ceiling assembly.
|
BLD-Energy code compliance | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | PASS |
Mike Jordan
|
|
|
Insulation // Harvey Phone #: ###-####
|
BLD-Wall cover | 4/14/2017 | 4/17/2017 | 4/17/2017 | P | PASS |
Mike Jordan
|
|
|
Joseph Phone #: ###-####. All issues resolved. ok to insulate.
|
BLD-Conference | 4/13/2017 | 4/14/2017 | 4/14/2017 | A | DONE |
Mike Jordan
|
|
|
Joseph Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | PART |
Mike Jordan
|
|
|
Joseph Phone #: ###-####. firecaulk all penetrations through top plate. Needs to remove foam from can light enclosures and use firecaulk. Will recall when complete and wil meet contractor to go over remainder.
|
BLD-Framing/Rough-in | 2/17/2017 | 2/17/2017 | 2/17/2017 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Have framing and Firestopping issues......but let insulate for now.
|
BLD-Framing/Rough-in | 1/10/2017 | 1/11/2017 | 1/10/2017 | P | NR |
Mike Jordan
|
|
|
Joseph Phone #: ###-####. Needs MEP rough in inspections first.
|
Issue PAID IN FULL permit | | | 10/6/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/6/2016 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/12/2016 | 9/12/2016 | 9/27/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) (Sept 30 - 15 days) Level 3 TI
|
Plan resubmittals received | | | 9/27/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/27/2016 | | 9/27/2016 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/27/2016 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
1st review completed | | | 9/20/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/20/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/12/2016 | | 9/20/2016 | | FAIL |
Carl Westfall
|
|
|
1st IBC review done
|
Routing - MECHANICAL | 9/19/2016 | | 9/19/2016 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 9/12/2016 | | 9/14/2016 | | FAIL |
Troy James
|
|
|
Spoke with mechanical engineer. He will email me and architect revise drawing showing return air path from offices and conference room.
|
Routing - FIRE | 9/12/2016 | 9/12/2016 | 9/12/2016 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Intake Approval | | | 9/12/2016 | | PASS |
David Ferguson
|
|
|
|
Routing - Addressing | 9/12/2016 | | 9/12/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2016 | | 9/12/2016 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 9/9/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 9 2016 12:44PM
|