BLD-Final | 4/14/2017 | 4/14/2017 | 4/14/2017 | P | PASS |
Brandon Shaw
|
|
|
Jason Phone #: ###-####
|
BLD-Energy code compliance | 1/20/2017 | 1/20/2017 | 1/20/2017 | P | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####
|
BLD-Framing/Rough-in | 1/18/2017 | 1/18/2017 | 1/18/2017 | P | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####,, add sill bolt in garage, ok to insulate
|
BLD-Wall Bracing | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PASS |
Tony Young
|
|
|
Jason Phone #: ###-####
|
BLD-Footing | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/10/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/8/2016 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/8/2016 | | DONE |
|
|
|
|
Telephone call | | | 11/8/2016 | | DONE |
|
|
|
called Jason- left message that permit is ready and fees due
|
Routing - Addressing | 11/7/2016 | | 11/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Case Summary (BLD) | | | 11/8/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/8/2016 | | DONE |
|
|
|
All Met
|
Plan assigned to (LEG) Tisha | 9/9/2016 | | 11/8/2016 | | DONE |
Tisha Gallop
|
|
|
**pending ROS completion (reroute to PW for new address and parcel)
|
Routing - PLAN CHECK | 9/15/2016 | | 9/16/2016 | | PASS |
Tisha Gallop
|
|
|
redlined beams per telephone conversation with applicant
|
Telephone call | | | 9/16/2016 | | DONE |
|
|
|
spoke to applicant about patio beams failed in StruCalc and planning approval issue pending about recorded parcels for original lots of record.
|
1st review completed | | | 9/16/2016 | | FAIL |
|
|
|
pending planning issue about recorded parcels numbers
|
Routing - MECHANICAL | 9/12/2016 | | 9/15/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/12/2016 | | 9/12/2016 | | PASS |
Josh Wilson
|
|
|
Ok w/ redline to construct 5 foot sidewalk along 34th Street per DRH16-00283/283.
|
Routing - Addressing | 9/12/2016 | | 9/12/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 9/12/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/9/2016 | | DONE |
|
|
|
|
Intake Approval | | | 9/9/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/9/2016 | | DONE |
|
|
|
|
Application received | | 9/9/2016 | | | |
|
|
|
|