Letter of compliance/Occupancy | | | 11/26/2018 | | DONE |
|
|
|
|
BLD-Final | 4/24/2018 | 4/24/2018 | 4/25/2018 | P | PASS |
Jim Sly
|
|
|
Tim Phone #: ###-####
|
DOC - Permit Finaled | 4/25/2018 | 4/25/2018 | 4/25/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 4/13/2018 | 4/13/2018 | 4/16/2018 | P | NR |
Jim Sly
|
|
|
Tim Sevig Phone #: ###-####
|
BLD-Aging Inspection | 1/26/2018 | 1/26/2018 | 1/30/2018 | | DONE |
Jim Sly
|
|
|
EXP.
|
BLD-Energy code compliance | 9/13/2017 | 9/14/2017 | 9/14/2017 | P | PASS |
Jim Sly
|
|
|
Tim Phone #: ###-####
|
BLD-Framing/Rough-in | 9/6/2017 | 9/7/2017 | 9/7/2017 | P | PASS |
Jim Sly
|
|
|
Tim Phone #: ###-####
|
Telephone call | | | 7/26/2017 | | DONE |
|
|
|
Tony with Blue Repair turned in the 1st manual j's but they need revised manual's so some other company is going to submitt all new maual's. Tisha and I talked and since he's not the GC or HVAC and just did the manual's he does not have to cancel the orig since the revised with replace the old manual j's
|
BLD-Wall Bracing | 5/30/2017 | 5/31/2017 | 5/31/2017 | A | PASS |
Jim Sly
|
|
|
Shear // Tim Phone #: ###-####
|
BLD-Foundation | 11/9/2016 | 11/9/2016 | 11/9/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 11/8/2016 | 11/8/2016 | 11/8/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 11/7/2016 | 11/7/2016 | 11/8/2016 | P | NR |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 10/18/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 10/17/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 9/16/2016 | 9/16/2016 | 10/17/2016 | | DONE |
Brian McGowan
|
|
|
Due 9-26 - Fail - Tall wall, retaining wall and lateral engineering needed. Several misc. items.
|
Inspection Record Card- Bld | | | 10/17/2016 | | DONE |
|
|
|
|
Telephone call | | | 10/17/2016 | | DONE |
|
|
|
Spoke with Tim informing him that this permit is ready and the fee amount due for issuance
|
Routing - PLAN CHECK | 10/17/2016 | | 10/17/2016 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 10/17/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 10/17/2016 | | DONE |
|
|
|
all requirements met
|
Plan resubmittals received | | | 10/5/2016 | | DONE |
|
|
|
received two copies of sheets 3, 4, 5, and 6, structural calcs, and dimensions- put on Brian's desk
|
1st review completed | | | 9/22/2016 | | FAIL |
Brian McGowan
|
|
|
Tall wall, retaining wall and lateral engineering needed. Several misc. items.
|
Routing - PLAN CHECK | 9/15/2016 | | 9/22/2016 | | FAIL |
Brian McGowan
|
|
|
Tall wall, retaining wall and lateral engineering needed. Several misc. items.
|
Plan assigned to (LEG) Tisha | 9/13/2016 | | 9/16/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 9/14/2016 | | 9/15/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/14/2016 | | 9/14/2016 | | PASS |
Leon Letson
|
|
|
Max Driveway width to be 33' measured at 20' from front property line.
|
Routing - Addressing | 9/13/2016 | | 9/14/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 9/14/2016 | | PASS |
|
|
|
owner built ADU prior to SFD. Lived in ADU as primary home. SFD impact fees paid, and ADU owed.
|
Plans ACCEPTED BY PLAN TECH | | | 9/13/2016 | | DONE |
|
|
|
plan review fee was added the wrong way
|
Intake Approval | | | 9/13/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/13/2016 | | DONE |
|
|
|
|
Application received | | 9/12/2016 | | | |
|
|
|
|