Print Statement | | | 12/6/2017 | | DONE |
|
|
|
|
Meeting | | | 12/6/2017 | | DONE |
|
|
|
Original final value had $1,321,000 but that had the gatehouse and that has it's own permit. Took off $400,000
|
First Notice | 10/18/2017 | 10/18/2017 | 11/14/2017 | | DONE |
Dave Hannah
|
|
|
Mailed 11-15-17
|
BLD-Aging Inspection | 10/18/2017 | 10/18/2017 | 10/18/2017 | | DONE |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 10/17/2017 | 10/17/2017 | 10/18/2017 | | DONE |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 10/18/2017 | 10/18/2017 | 10/18/2017 | A | PASS |
Dave Hannah
|
|
|
|
Letter of compliance/Occupancy | | | 6/6/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/2/2017 | 6/5/2017 | 6/5/2017 | A | PASS |
Jim Page
|
|
|
Fire alarm inspection complete for hearing impaired rooms, final life fire safety inspection passed/complete.
|
FIRE-Final Inspection | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | CANC |
Jim Page
|
|
|
Project has rooms that have modifications to the fire alarm system (FIR17-00189, permit is not attached in project related cases), audio visual device modifications need to be tested, inspected and passed before final inspection for life fire safety can be completed. This inspection request is cancelled and will be rescheduled by contractor to coincide with fire alarm final.
|
BLD-Final | 5/9/2017 | 5/9/2017 | 5/9/2017 | P | PASS |
Dave Hannah
|
|
|
Terry Phone #: ###-####-building 8 room 811, 813, bldg 6 room 613, bldg 5 room 513, bldg 10 room 1013, and all of building 7
|
BLD-Final | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PEND |
Dave Hannah
|
|
|
Terry-bldg 8 with the exception of rooms 811 & 813. and also a final on rooms 411 and 413 Phone #: ###-#### ok for temp occ
|
BLD-Framing/Rough-in | 4/25/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Dave Hannah
|
|
|
Rooms 811 and 813 Terry Phone #: ###-####
|
BLD-Final | 4/24/2017 | 4/24/2017 | 4/26/2017 | P | DONE |
Dave Hannah
|
|
|
bldg 14; Gary Phone #: ###-####
|
BLD-Final | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | PART |
Dave Hannah
|
|
|
Building 12 // Terry Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 4/17/2017 | 4/17/2017 | 4/17/2017 | P | PART |
Jim Page
|
|
|
Final life fire safety inspection complete for buildings 7 and 8, all ADA rooms will be inspected at a later date.
|
FIRE-Final Inspection | 4/14/2017 | 4/14/2017 | 4/14/2017 | P | CANC |
Troy Cobbley
|
|
|
bldg 7, 8; Terry Phone #: ###-####
|
BLD-Framing/Rough-in | 4/5/2017 | 4/6/2017 | 4/6/2017 | P | PASS |
Dave Hannah
|
|
|
Terry Phone #: ###-####
|
BLD-Final | 4/5/2017 | 4/6/2017 | 4/6/2017 | P | PASS |
Dave Hannah
|
|
|
Building 11 // Terry Phone #: ###-#### ok to occ bld 11
|
BLD-Final | 3/29/2017 | 3/30/2017 | 4/3/2017 | P | PART |
Dave Hannah
|
|
|
Building 10 // Terry Phone #: ###-#### ok for temp
|
FIRE-Final Inspection | 3/29/2017 | 3/30/2017 | 3/30/2017 | A | PART |
Jim Page
|
|
|
Building 12 and 14, no fire sprinklers, no fire alarm modifications, fire extinguishers are in place with current inspection tags. Final life fire safety for buildings 12 and 14 passed/complete.
|
BLD-Framing/Rough-in | 3/29/2017 | 3/30/2017 | 3/30/2017 | A | PASS |
Dave Hannah
|
|
|
Building 6 and 10 // Terry Phone #: ###-####
|
BLD-Final | 3/24/2017 | 3/27/2017 | 3/27/2017 | A | PART |
Mike Jordan
|
|
|
building 9; Gary Phone #: ###-####. Building 9 ok for temp occ.
|
FIRE-Final Inspection | 3/23/2017 | 3/24/2017 | 3/24/2017 | A | PART |
Jim Page
|
|
|
Life fire safety inspection complete for buildings 9, 10 and 11 with exception to room 1013 (mentioned room is an ADA room, modifications to the fire alarm system are not complete, after inspection for fire alarms is complete, building 10 will be complete)
|
BLD-Framing/Rough-in | 3/16/2017 | 3/17/2017 | 3/17/2017 | A | PASS |
Dave Hannah
|
|
|
Building 4 // Terry Phone #: ###-####
|
BLD-Framing/Rough-in | 3/15/2017 | 3/16/2017 | 3/16/2017 | P | FAIL |
Dave Hannah
|
|
|
Buildings 4, 5 and 6 /// Terry Phone #: ###-#### fire blocking
|
BLD-Final | 3/16/2017 | 3/16/2017 | 3/16/2017 | P | PART |
Dave Hannah
|
|
|
Bldg 6- Gary Phone #: ###-#### ok to occ all but 613
|
BLD-Final | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PART |
Dave Hannah
|
|
|
Building 5 // Terry Phone #: ###-#### ok for tco needs to finish rm 513
|
BLD-Framing/Rough-in | 3/3/2017 | 3/3/2017 | 3/3/2017 | P | PASS |
Dave Hannah
|
|
|
building 6; Kerry Phone #: ###-####
|
BLD-Final | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | PART |
Dave Hannah
|
|
|
Terry-bldg 4 Phone #: ###-#### ok to occ allbut for 411 and 413
|
FIRE-Final Inspection | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | PART |
Jim Page
|
|
|
Life fire safety inspection complete for buildings 4, 5 and 6 with exception to rooms 411, 413, 513 and 613 (mentioned rooms are ADA rooms, modifications to the fire alarm system are not complete, after inspection for fire alarms is complete building 4,5 and 6 will be complete)
|
BLD-Framing/Rough-in | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | PASS |
Dave Hannah
|
|
|
bld5 // Terry Phone #: ###-####
|
BLD-Framing/Rough-in | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | NH |
Jim Sly
|
|
|
Bruce Phone #: ###-####
|
BLD-Final | 2/17/2017 | 2/17/2017 | 2/17/2017 | P | PASS |
Jim Storey
|
|
|
Terry-building 3 for temp c of o Phone #: ###-####
|
BLD-Framing/Rough-in | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | PASS |
Jim Storey
|
|
|
Gary Phone #: ###-#### pending ada rms
|
BLD-Final | 2/15/2017 | 2/15/2017 | 2/15/2017 | P | PART |
Dave Hannah
|
|
|
Terry-bldg 2 only Phone #: ###-#### ok to occ bld 2
|
BLD-Final | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | CANC |
Dave Hannah
|
|
|
bldg 1 ONLY Phone #: ###-####
|
BLD-Final | 2/3/2017 | 2/6/2017 | 2/6/2017 | P | PASS |
Jim Storey
|
|
|
Terry-final on building 1 for temp c of o Phone #: ###-####
|
BLD-Framing/Rough-in | 2/3/2017 | 2/3/2017 | 2/3/2017 | P | PART |
Jim Sly
|
|
|
Terry Phone #: ###-#### Bldgs 2 and 3.....OK
|
FIRE-Final Inspection | 1/31/2017 | 2/1/2017 | 2/1/2017 | A | PART |
Jim Page
|
|
|
No fire sprinklers, no fire alarm modifications, fire extinguishers are in place with current inspection tags, life fire safety inspection is complete for buildings 1,2 and 3. Emergency lighting will need to be serviced on some of the exit discharge landings, will verify egress lighting service at a later inspection. Permit will remain in issued status until all buildings have been inspected and passed.
|
BLD-Conference | 1/26/2017 | 1/27/2017 | 1/27/2017 | A | DONE |
Jim Storey
|
|
|
Call Chad Schwendiman at ###-#### to meet on site to go over bath exhausts to see if fire rated bath exhausts will be required.
|
Inspection Record Card- Bld | | | 1/9/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/9/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 12/1/2016 | 12/1/2016 | 12/23/2016 | | PASS |
Carl Westfall
|
|
|
(Dec 21 - 15 days) (23 sheets) Residence Inn by Marriott
|
Routing - PLAN CHECK | 12/1/2016 | | 12/23/2016 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 12/23/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/23/2016 | | DONE |
|
|
|
NEED GC form and certificate of value
|
Routing - FIRE | 12/1/2016 | 12/1/2016 | 12/5/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PLUMBING | 12/1/2016 | | 12/5/2016 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - PUBLIC WORKS | 12/1/2016 | | 12/2/2016 | | PASS |
Rachael Beierle
|
|
|
REMODEL ONLY. NO ADDITIONAL CONSUMPTION
|
Intake Approval | | | 12/1/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 12/1/2016 | | 12/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 10/5/2016 | | FAIL |
Javier Guzman
|
|
|
Because this project does not fall under a minor T.I. please upload and provide the following, Incomplete submittals will not be accepted:
1. Please provide a completed 520 Major T.I. Checklist, checklist must be completed by the project’s Idaho-licensed design professional of record
2. The checklist is not complete unless all information is filled out, all appropriate boxes are checked and all plan page numbers are listed.
3. Please provide any additional documents or plans requested from the checklist
4. At a glance I saw structural plan sheets uploaded but did not view or notice engineering documents, please provide structural calculations stamped and signed by an Idaho licensed engineer will be required
|
Application received | | | 9/12/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 12 2016 6:42PM
|