BLD-Final | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | CANC |
Mike Jordan
|
|
|
Dick Phone #: ###-####
|
FIRE-Final Inspection | 7/26/2017 | 7/26/2017 | 7/26/2017 | P | CANC |
Troy Cobbley
|
|
|
No life safety sign off required.
Dick Phone #: ###-####
|
Zoning Approval | 7/25/2017 | 7/25/2017 | 7/25/2017 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 3/21/2017 | 3/21/2017 | 3/22/2017 | | PASS |
Mike Jordan
|
|
|
Full permit issued. Wiil final this permit when the Bldg. permit finals.
|
BLD-Foundation | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | PASS |
Mike Jordan
|
|
|
Rebar... As late as possible // Dante Phone #: ###-####. Rebar in slab on grade.
|
BLD-Energy code compliance | 10/25/2016 | 10/25/2016 | 10/25/2016 | P | PASS |
Mike Jordan
|
|
|
Rigid insulation at interior side of stemwall ok.
|
BLD-Energy code compliance | 10/24/2016 | 10/25/2016 | 10/25/2016 | A | NR |
Mike Jordan
|
|
|
Insulation // Dante Phone #: ###-####. Provide additional insulation at footings were they step down. Need 24 inches min.
|
BLD-Foundation | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PART |
Mike Jordan
|
|
|
Dante Phone #: ###-####. perimeter stemwalls, work in progress. Will have special inspection.
|
BLD-Footing | 10/13/2016 | 10/13/2016 | 10/13/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | NR |
Mike Jordan
|
|
|
Dante Phone #: ###-####. No approved plans on site. rescheduled for pm.
|
Issue PAID IN FULL permit | | | 10/11/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/21/2016 | | |
|
|
|
|
OVERRIDE | | | 9/21/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 9/21/2016 | 9/21/2016 | 9/21/2016 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/21/2016 | | 9/21/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/21/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/21/2016 | | DONE |
|
|
|
***all requirments met 10-11-16 /CEV
need GC & Rev Cert of Val & ACHD needs to be paid-permit in drawer
|
Telephone call | | | 9/21/2016 | | DONE |
|
|
|
called Thomas (also talked to Joel) to let know the foundation permit is ready-need GC, rev cert of val & ACHD
|
Intake Approval | | | 9/21/2016 | | |
|
|
|
|
Intake Approval | | | 9/21/2016 | | PASS |
|
|
|
|