BLD-Final | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####
|
DOC - Permit Finaled | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 6/20/2017 | 6/20/2017 | 6/20/2017 | P | PART |
Tony Young
|
|
|
Ron Phone #: ###-####8,, need cont handrail,, fire caulking
|
Zoning Approval | 6/20/2017 | 6/20/2017 | 6/20/2017 | | PASS |
Sarah Schafer
|
|
|
|
PubWorks Occupancy Approval | 6/19/2017 | 6/19/2017 | 6/19/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
CHANGE STATUS TO (ISS) | | | 4/27/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/27/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 4/12/2017 | | |
|
|
|
|
Plan assigned to (AJS) | 4/12/2017 | 4/12/2017 | 4/12/2017 | | DEFR |
Tisha Gallop
|
|
|
|
Plan assigned to (LEG) Tisha | 4/12/2017 | | 4/12/2017 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 4/12/2017 | | 4/12/2017 | | PASS |
Tisha Gallop
|
|
|
1-hr fee for building review plan mod
|
Case Summary (BLD) | | | 4/12/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/12/2017 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
Inspection Record Card- Bld | | | 4/12/2017 | | DONE |
|
|
|
|
Telephone call | | | 4/12/2017 | | DONE |
|
|
|
Sent a message to Ron (phone number doesn't work ###-####) informing him that his plan mods are ready and the fee amounts due for issunace
|
Inspection Record Card- Bld | | | 4/12/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/12/2017 | | DONE |
|
|
|
Two copies of sheets S2.1 and A3.1. Taken to Tisha per Tisha
|
BLD-Energy code compliance | 2/27/2017 | 2/28/2017 | 2/28/2017 | A | PASS |
Dave Hannah
|
|
|
Ron Phone #: ###-####
|
BLD-Framing/Rough-in | 2/21/2017 | 2/22/2017 | 2/22/2017 | A | PART |
Tony Young
|
|
|
Ron-party wall Phone #: ###-####,, c/n posted,, ok to insulate,, need fireplaces
|
BLD-Framing/Rough-in | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PART |
Tony Young
|
|
|
Ron-party wall Phone #: ###-####,, party wall framing ok to cover between floors,, ok to insulate ,, need f/place permit and inspection..
|
BLD-Conference | 2/7/2017 | 2/9/2017 | 2/9/2017 | A | PEND |
Tony Young
|
|
|
Ron Phone #: ###-####,, pending design for seperation
|
BLD-Framing/Rough-in | 2/6/2017 | 2/7/2017 | 2/7/2017 | P | NR |
Tony Young
|
|
|
Ron Phone #: ###-####,, no plans,, conf walk through only,, firewall issue also
|
BLD-Framing/Rough-in | 1/12/2017 | 1/12/2017 | 1/12/2017 | P | NR |
Tony Young
|
|
|
james Phone #: ###-####,, frame ?s
|
BLD-Other | 1/3/2017 | 1/3/2017 | 1/3/2017 | P | PART |
Jim Storey
|
|
|
Aaron-party wall Phone #: ###-#### screws in gyp ok 2nd floor assembled on ground.
|
BLD-Framing/Rough-in | 12/27/2016 | 12/27/2016 | 12/28/2016 | P | PART |
Jim Sly
|
|
|
Aaron Phone #: ###-#### 5/8 rock...next to property line at 1hr wall....OK
|
BLD-Framing/Rough-in | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PART |
Dave Hannah
|
|
|
Paul Phone #: ###-#### second half first floor fire wall ok to stand
|
BLD-Framing/Rough-in | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | PART |
Tony Young
|
|
|
Erin Phone #: ###-####,, 1st level party wall (pl) nailing,,, ok to stand,, firewall and drywall shear 1st level ok
|
BLD-Foundation | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | PASS |
Tony Young
|
|
|
Randy Phone #: ###-####,, ok now
|
PubWorks Subgrade Approval | 11/29/2016 | 11/29/2016 | 11/29/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 11/28/2016 | 11/28/2016 | 11/28/2016 | P | PEND |
Tony Young
|
|
|
Randy Phone #: ###-####,, need soils approval 1st
|
BLD-Footing | 11/23/2016 | 11/23/2016 | 11/23/2016 | P | PASS |
Phil Shearer
|
|
|
Randy Phone #: ###-####
|
OVERRIDE | | | 11/10/2016 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/10/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 11/10/2016 | | 11/10/2016 | | PASS |
Josh Wilson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 11/10/2016 | | DONE |
|
|
|
|
Telephone call | | | 11/10/2016 | | DONE |
|
|
|
called Ron to let know permits are ready-left message on his phone
|
Permit Ready to Issue | | | 11/10/2016 | | DONE |
|
|
|
|
Place hold on job | 11/2/2016 | | 11/10/2016 | | DONE |
Brittany Hill
|
|
|
DO NOT ISSUE WITHOUT BLD16-03502
|
Routing PW Grading-Hillside | 11/7/2016 | | 11/9/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Plan resubmittals received | | | 11/7/2016 | | DONE |
|
|
|
Three copies of sheets C1.0, C3.0, C3.1 and ESC3.2. Taken to Tisha.
|
CHANGE STATUS TO (REV) | | | 11/4/2016 | | DONE |
|
|
|
change out of RDY staus see Jim Wylie.
|
OVERRIDE | | | 11/2/2016 | | |
|
|
|
|
Case Summary (BLD) | | | 11/2/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/2/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/2/2016 | | DONE |
|
|
|
ALL MET
|
Routing - PLAN CHECK | 10/18/2016 | | 11/2/2016 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2016 | | DONE |
|
|
|
final value added for difference between flatland and hillside living square footage
|
Plan assigned to (LEG) Tisha | 9/23/2016 | | 11/2/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 10/8; L2 townhouse; hillside & plan check
|
Plan resubmittals received | | | 10/27/2016 | | DONE |
|
|
|
Received two copies of plan sheets A1.1, A1.2, A2, A3.1, A3.2, S2.2, S3.1, S3.2, S4; inserted into plans by LEG
|
Routing PW Grading-Hillside | 10/18/2016 | | 10/19/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 10/18/2016 | | 10/18/2016 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 10/4/2016 | | 10/8/2016 | | FAIL |
Tisha Gallop
|
|
|
e-mailed applicant comments
|
1st review completed | | | 10/8/2016 | | FAIL |
|
|
|
PW hillside & plan check
|
Plan resubmittals received | | | 10/4/2016 | | DONE |
|
|
|
Received three full sets of grading and erosion & sediment control sheets, plans taken to LEG for review
|
Routing - FIRE | 10/3/2016 | | 10/4/2016 | | PASS |
Scott Arellano
|
|
|
This project has been evaluated for compliant Fire Department vehicle access, water supply, and applicable provisions of BMC 7-01-69 for defensible space. Final approval will be subject to satisfactory field inspection by Boise Fire Department.
|
Routing - Erosion and Sediment | 9/30/2016 | | 9/30/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan submitted and approved. Valid RP and PD designated.
|
Routing - MECHANICAL | 9/29/2016 | | 9/30/2016 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 9/28/2016 | | 9/29/2016 | | PASS |
Josh Wilson
|
|
|
DRH14-00164
|
Routing - PUBLIC WORKS | 9/27/2016 | | 9/28/2016 | | FAIL |
Morgan Webb
|
|
|
failed hillside
|
Routing - PLANNING | | | 9/28/2016 | | PASS |
Leon Letson
|
|
|
|
Routing PW Grading-Hillside | 9/26/2016 | | 9/27/2016 | | FAIL |
Jason C. Taylor
|
|
|
Subdivision not approved for construction. will need revised geotech and grading plan prior to approval. JCT See email dated 9/27/2016
|
Routing PW Sewer Rating | 9/26/2016 | | 9/26/2016 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 9/23/2016 | | 9/26/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/23/2016 | | DONE |
|
|
|
|
Intake Approval | | | 9/23/2016 | | PASS |
Carlos Velazquez
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/23/2016 | | DONE |
|
|
|
|
Application received | | 9/22/2016 | | | |
|
|
|
|