Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD16-03512
StatusFinaled
Name ESI
Site Address 195 S CAPITOL BLVD
Project NameDistrict Kitchen and Escalator
Customer Number 
ePlanReviewYes
Description
(THE DISTRICT CONVENTION CENTER KITCHEN AND ESCALATORS FOR GBAD – BOISE CENTRE EAST AT CITY CENTER PLAZA – 1ST, 2ND, AND 4TH STORIES) The fire sprinkler system is used for occupancy and to comply with the high-rise requirements of the building code. This work was formerly permitted under BLD15-02494 for the Convention Center kitchen located on the lower 2nd story and the support area located on the 1st story and under BLD14-03207 for the Convention Center escalators.

1st Story Delivery: To construct a 525 square foot delivery area having direct access at grade to the exit passageway located between City Center Plaza and the Grove Hotel/CenturyLink Arena. Deliveries for the convention center will be brought from Capitol Blvd. to the delivery area through the exit passageway. Delivery vehicles are not allowed to be parked within the exit passageway. An interior elevator will connect the delivery area to the commercial kitchen located on the level directly above. Work is to include finishes, a freight elevator, a walk-in cooler, and a walk-in freezer. An 8” deep floor depression will be provided for the cooler and for the freezer to accommodate insulated floors. Condensate will drain to a floor sink.

2nd Story (lower) Kitchen: To construct a 5,745 square foot commercial kitchen on the lower 2nd story to serve the convention center located on the 4th story above. Service elevators connect the kitchen to the convention center. Work is to include interior nonbearing walls, two restrooms accessible to the disabled, two grease hood, walk-in coolers, a walk-in freezer, kitchen equipment, suspended acoustical ceilings, and finishes. An 8” deep floor depression will be provided for the coolers and for the freezers to accommodate insulated floors. Condensate will drain to a floor sink.

Escalator between the 2nd Story (upper) Lobby and the 4th story Lobby: To install an escalator between the 2nd story Convention Center lobby and 4th story Convention Center lobby. Occupants will generally arrive at the 2nd Story (upper) Lobby across a bridge connected to the existing convention center. The escalators and elevators will give access from the upper 2nd story lobby to the convention center lobby located on the 4th story above. The escalator was formerly permitted under BLD14-03207. Refer to the drawings and documents under that permit for additional information about the escalators, including the structural design and details and the plan review comments.

The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 1/15/20172/13/2017 DONE
DetailsChristina Prado
emailed to ESI rep
Print Occupancy Form  2/9/2017 DONE
Second Notice 12/22/20161/10/2017 DONE
Mailed 1-11
First Notice 12/12/201612/12/2016 DONE
Mailed 12-13-16
Permanent Occupancy  12/2/2016 DONE
BLD-Final12/1/201612/1/201612/1/2016PPASS
DetailsDave Hannah
Final inspections done under Bld14-03207, Shell & Core Permit and Bld15-02494 GBAD TI.
FIRE-Final Inspection12/1/201612/1/201612/1/2016PPASS
DetailsJim Page
Final Inspections done under BLD14-03207, Shell and Core Permit, and BLD15-02494.
Conference12/1/201612/1/201612/1/2016 PASS
DetailsAngela Brosious
Plumbing, electrical and mechanical finaled under BLD15-02494.
Conference12/1/201612/1/201612/1/2016 PASS
DetailsAngela Brosious
Escalators passed state certification and inspection by Daryl and Rock. Documentation from State attached.
CDHD Occupancy Approval12/1/201612/1/201612/1/2016 PASS
DetailsAngela Brosious
CDHD sign off by Antonucci on 11/8/16.
Issue & PRINT permit  11/17/2016 DONE
Routing - MECHANICAL11/10/2016 11/16/2016 PASS
DetailsChad Schwendiman
PLANS/APPL TAKEN TO FRONT DESK  11/16/2016 DONE
Permit Ready to Issue  11/16/2016 DONE
Need GC Form and Revised Cert of Value
Plan assigned to (CJW)9/26/2016 11/16/2016 PASS
DetailsCarl Westfall
(1st done) Convention Center East - Kitchen, etc
Plan resubmittals received  11/10/2016 DONE
As built mechanical plans received and uploaded into eplan.
Code Occupancy Approval Temp  11/10/2016 DONE
Ok for TCO; final inspections for electrical, pumbing, mechanical, fire and structural verified.
Plan resubmittals received  11/10/2016 DONE
Routing - PLAN CHECK11/10/2016 11/10/2016 PASS
DetailsCarl Westfall
Routing - MECHANICAL10/25/2016 10/27/2016 FAIL
DetailsTroy James
Still need to have grease duct design to match how it is installed on site.
Plan resubmittals requested  10/27/2016 DONE
Routing - PLAN CHECK10/24/2016 10/25/2016 PASS
DetailsCarl Westfall
Approved before
Plan resubmittals received  10/24/2016 DONE
1st review completed  10/5/2016 DONE
Plan resubmittals requested  10/5/2016 DONE
Routing - PLAN CHECK9/26/2016 10/5/2016 PASS
DetailsCarl Westfall
Routing - PLUMBING9/26/2016 10/5/2016 PASS
DetailsBill VanDegrift
Signed-off for Bill because it is understood that the Plumbing sheets are identical to what was approved under permit BLD15-02494.
Routing - MECHANICAL9/26/2016 9/30/2016 FAIL
DetailsTroy James
Routing - FIRE9/26/20169/26/20169/27/2016 PASS
DetailsKatie Marron
Comments attached to case.
Routing PW Environmental9/26/2016 9/26/2016 PASS
DetailsRick Christenson
Routing - PUBLIC WORKS9/26/2016 9/26/2016 PASS
DetailsRachael Beierle
SEWER CREDITS REMAIN AND UTILIZED FROM BLD15-02494.
Intake Approval  9/26/2016 PASS
DetailsAdele J Schaffeld-Griffin
Routing - Design Review9/26/2016 9/26/2016 PASS
DetailsSarah Schafer
Intake Approval  9/23/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Please upload 304 form.
Please have design professional of record stamp all drawings submitted for review.
Application received  9/22/2016 DONE
Application submitted via PDS Online on Sep 22 2016 2:16PM