Third Notice | | 1/15/2017 | 2/13/2017 | | DONE |
Christina Prado
|
|
|
emailed to ESI rep
|
Print Occupancy Form | | | 2/9/2017 | | DONE |
|
|
|
|
Second Notice | | 12/22/2016 | 1/10/2017 | | DONE |
|
|
|
Mailed 1-11
|
First Notice | | 12/12/2016 | 12/12/2016 | | DONE |
|
|
|
Mailed 12-13-16
|
Permanent Occupancy | | | 12/2/2016 | | DONE |
|
|
|
|
BLD-Final | 12/1/2016 | 12/1/2016 | 12/1/2016 | P | PASS |
Dave Hannah
|
|
|
Final inspections done under Bld14-03207, Shell & Core Permit and Bld15-02494 GBAD TI.
|
FIRE-Final Inspection | 12/1/2016 | 12/1/2016 | 12/1/2016 | P | PASS |
Jim Page
|
|
|
Final Inspections done under BLD14-03207, Shell and Core Permit, and BLD15-02494.
|
Conference | 12/1/2016 | 12/1/2016 | 12/1/2016 | | PASS |
Angela Brosious
|
|
|
Plumbing, electrical and mechanical finaled under BLD15-02494.
|
Conference | 12/1/2016 | 12/1/2016 | 12/1/2016 | | PASS |
Angela Brosious
|
|
|
Escalators passed state certification and inspection by Daryl and Rock. Documentation from State attached.
|
CDHD Occupancy Approval | 12/1/2016 | 12/1/2016 | 12/1/2016 | | PASS |
Angela Brosious
|
|
|
CDHD sign off by Antonucci on 11/8/16.
|
Issue & PRINT permit | | | 11/17/2016 | | DONE |
|
|
|
|
Routing - MECHANICAL | 11/10/2016 | | 11/16/2016 | | PASS |
Chad Schwendiman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/16/2016 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Plan assigned to (CJW) | 9/26/2016 | | 11/16/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) Convention Center East - Kitchen, etc
|
Plan resubmittals received | | | 11/10/2016 | | DONE |
|
|
|
As built mechanical plans received and uploaded into eplan.
|
Code Occupancy Approval Temp | | | 11/10/2016 | | DONE |
|
|
|
Ok for TCO; final inspections for electrical, pumbing, mechanical, fire and structural verified.
|
Plan resubmittals received | | | 11/10/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/10/2016 | | 11/10/2016 | | PASS |
Carl Westfall
|
|
|
|
Routing - MECHANICAL | 10/25/2016 | | 10/27/2016 | | FAIL |
Troy James
|
|
|
Still need to have grease duct design to match how it is installed on site.
|
Plan resubmittals requested | | | 10/27/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/24/2016 | | 10/25/2016 | | PASS |
Carl Westfall
|
|
|
Approved before
|
Plan resubmittals received | | | 10/24/2016 | | DONE |
|
|
|
|
1st review completed | | | 10/5/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/5/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/26/2016 | | 10/5/2016 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLUMBING | 9/26/2016 | | 10/5/2016 | | PASS |
Bill VanDegrift
|
|
|
Signed-off for Bill because it is understood that the Plumbing sheets are identical to what was approved under permit BLD15-02494.
|
Routing - MECHANICAL | 9/26/2016 | | 9/30/2016 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 9/26/2016 | 9/26/2016 | 9/27/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Environmental | 9/26/2016 | | 9/26/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - PUBLIC WORKS | 9/26/2016 | | 9/26/2016 | | PASS |
Rachael Beierle
|
|
|
SEWER CREDITS REMAIN AND UTILIZED FROM BLD15-02494.
|
Intake Approval | | | 9/26/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Design Review | 9/26/2016 | | 9/26/2016 | | PASS |
Sarah Schafer
|
|
|
|
Intake Approval | | | 9/23/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please upload 304 form.
Please have design professional of record stamp all drawings submitted for review.
|
Application received | | | 9/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 22 2016 2:16PM
|