Permit Information
Permit NumberBLD16-03518
StatusFinaled
Name TRILOGY DEVELOPMENT INC
Site Address 9840 W OVERLAND RD Unit: 120
Project Name208 Real Estate - Suite #120
Customer Number 
ePlanReviewYes
Description
**(208 REAL ESTATE – SUITE #120)** (Note: Do not final until BLD15-01393 is finaled) Permit is to build out a first time a 3,455 sq. ft. business tenant space. Core and shell built under BLD15-01393. Approval is contingent on adhering to the approved plans and attached documents. Work to include: construction of interior non-bearing walls to create (7) offices, an entry/reception area, a conference room, a break/kitchen area, (2) accessible restroom, a showcase room, (2) open office areas, a small closet and a janitor’s closet, new exterior stairs, (2) new exterior doors, millwork, accessible drinking fountain, suspended acoustic ceiling, select gypsum ceiling, new light fixtures, electrical work, plumbing work, mechanical work and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. This building is not fire sprinklered. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 4/21/20174/17/2017 DONE
This permit finaled on the web by Mike McHargue
First Notice 4/10/20174/11/2017 DONE
sent in mail 4-12-17
Permanent Occupancy  3/31/2017 DONE
BLD-Final1/23/20171/23/20171/23/2017PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Mike McHargue. Ok for perm occ.
FIRE-Final Inspection1/18/20171/18/20171/18/2017PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Ceiling Grid Inspection1/4/20171/5/20171/5/2017APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Ceiling Grid Inspection1/4/20171/4/20171/4/2017PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue
BLD-Framing/Rough-in11/17/201611/18/201611/18/2016APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Energy code compliance11/17/201611/18/201611/18/2016APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Framing/Rough-in11/16/201611/16/201611/16/2016PFAIL
DetailsMike Jordan
Interior TI Framing Phone #: ###-#### Inspection requested via web by Mike McHargue. Firblock fur downs at ADA drinking fountain. Needs ti fireblock area at electrical conduits. Foam around conduits going through mezz. floor. OK to insulate. Correction notice posted.
Issue PAID IN FULL permit  10/14/2016 DONE
Print Occupancy Form  10/14/2016 DONE
OVERRIDE  10/13/2016  
Plan assigned to (JG)9/29/20169/29/201610/13/2016 PASS
DetailsJavier Guzman
1st review completed, 10/12 L2 208 Real Estate ePlan
Routing - PLAN CHECK10/13/2016 10/13/2016 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  10/13/2016 DONE
Permit Ready to Issue  10/13/2016 DONE
NEED RP, GC & rev cert of val
Routing - Design Review10/10/2016 10/12/2016 PASS
DetailsJosh Wilson
1st review completed  10/12/2016 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK9/29/2016 10/11/2016 FAIL
DetailsJavier Guzman
Routing - PLUMBING9/29/2016 10/6/2016 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing - MECHANICAL9/29/2016 9/30/2016 PASS
DetailsChad Schwendiman
Routing - FIRE9/29/20169/29/20169/29/2016 PASS
DetailsKatie Marron
Comments attached to case.
Intake Approval  9/29/2016 PASS
DetailsAdele J Schaffeld-Griffin
pre screen approved by Carl W
Routing - Addressing9/29/2016 9/29/2016 PASS
DetailsLaura Hunter
Suite 120
Routing - PUBLIC WORKS9/29/2016 9/29/2016 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment9/29/2016 9/29/2016 PASS
DetailsAndy J. Long
ESC plan waiver approved. Valid RP designated.
Plan Reviewer's activity  9/28/2016 PASS
Plan intake approved
Intake Approval  9/27/2016 FAIL
(9-27-16) Please see the circled items in the plan intake checklist and resolve each item as noted.
Intake Approval  9/27/2016 FAIL
(9-27-16) Please see the circled items in the plan intake checklist and resolve each item as noted. (2nd review for the day)
Application received  9/22/2016 DONE
Application submitted via PDS Online on Sep 22 2016 2:57PM