Second Notice | | 4/21/2017 | 4/17/2017 | | DONE |
|
|
|
This permit finaled on the web by Mike McHargue
|
First Notice | | 4/10/2017 | 4/11/2017 | | DONE |
|
|
|
sent in mail 4-12-17
|
Permanent Occupancy | | | 3/31/2017 | | DONE |
|
|
|
|
BLD-Final | 1/23/2017 | 1/23/2017 | 1/23/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue. Ok for perm occ.
|
FIRE-Final Inspection | 1/18/2017 | 1/18/2017 | 1/18/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 1/4/2017 | 1/5/2017 | 1/5/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Ceiling Grid Inspection | 1/4/2017 | 1/4/2017 | 1/4/2017 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue
|
BLD-Framing/Rough-in | 11/17/2016 | 11/18/2016 | 11/18/2016 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 11/17/2016 | 11/18/2016 | 11/18/2016 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McHargue
|
BLD-Framing/Rough-in | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | FAIL |
Mike Jordan
|
|
|
Interior TI Framing Phone #: ###-#### Inspection requested via web by Mike McHargue. Firblock fur downs at ADA drinking fountain. Needs ti fireblock area at electrical conduits. Foam around conduits going through mezz. floor. OK to insulate. Correction notice posted.
|
Issue PAID IN FULL permit | | | 10/14/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/14/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 10/13/2016 | | |
|
|
|
|
Plan assigned to (JG) | 9/29/2016 | 9/29/2016 | 10/13/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 10/12 L2 208 Real Estate ePlan
|
Routing - PLAN CHECK | 10/13/2016 | | 10/13/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2016 | | DONE |
|
|
|
NEED RP, GC & rev cert of val
|
Routing - Design Review | 10/10/2016 | | 10/12/2016 | | PASS |
Josh Wilson
|
|
|
|
1st review completed | | | 10/12/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 9/29/2016 | | 10/11/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 9/29/2016 | | 10/6/2016 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - MECHANICAL | 9/29/2016 | | 9/30/2016 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - FIRE | 9/29/2016 | 9/29/2016 | 9/29/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Intake Approval | | | 9/29/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen approved by Carl W
|
Routing - Addressing | 9/29/2016 | | 9/29/2016 | | PASS |
Laura Hunter
|
|
|
Suite 120
|
Routing - PUBLIC WORKS | 9/29/2016 | | 9/29/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 9/29/2016 | | 9/29/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Valid RP designated.
|
Plan Reviewer's activity | | | 9/28/2016 | | PASS |
|
|
|
Plan intake approved
|
Intake Approval | | | 9/27/2016 | | FAIL |
|
|
|
(9-27-16) Please see the circled items in the plan intake checklist and resolve each item as noted.
|
Intake Approval | | | 9/27/2016 | | FAIL |
|
|
|
(9-27-16) Please see the circled items in the plan intake checklist and resolve each item as noted. (2nd review for the day)
|
Application received | | | 9/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 22 2016 2:57PM
|