BLD-Final | 2/6/2017 | 2/7/2017 | 2/9/2017 | P | PASS |
Jim Sly
|
|
|
Please call prior to inspection for access. Note: Boise City had changed this residence''s address during construction. The Correct Final address is: 2782 N. Linda Vista Phone #: ###-#### Inspection requested via web by Chris Laraway NEW ADDRESS>>2782 N. LINDA VISTA PL.
|
BLD-Wall cover | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Laraway Energy code OK.
|
BLD-Framing/Rough-in | 12/7/2016 | 12/8/2016 | 12/8/2016 | A | PASS |
Jim Sly
|
|
|
Jim. House around the corner is also framed ; rough-in approved on plumbing ; Mechanical. Electricians have drilled it for rough-in, but have not finished pulling wire for inspection. I mention if, it would save you time to walk it at the same time. FYI, I will still request thru PDS after electrical is approved. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
Routing - Addressing | 11/22/2016 | | 11/22/2016 | | PASS |
Laura Hunter
|
|
|
changed address to 2782 N Linda Vista Ln due to postition of house
|
BLD-Wall Bracing | 11/18/2016 | 11/21/2016 | 11/21/2016 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Footing | 10/21/2016 | 10/24/2016 | 10/25/2016 | P | PASS |
Jim Sly
|
|
|
Berny-would like as early as possible Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/18/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 10/10/2016 | | |
|
|
|
|
Routing - PLANNING | 10/8/2016 | | 10/10/2016 | | PASS |
Nicolette Womack
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/10/2016 | | DONE |
|
|
|
all requirements met
|
Plan assigned to (LEG) Tisha | 9/29/2016 | | 10/10/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 10/7; planning eave setback (arch. stamp plans)
|
Plan resubmittals received | | | 10/8/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/8/2016 | | 10/8/2016 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 9/29/2016 | | 10/7/2016 | | FAIL |
Tisha Gallop
|
|
|
per planning requirement (architectural stamped drawings)
|
1st review completed | | | 10/7/2016 | | FAIL |
|
|
|
planning & building
|
Routing - MECHANICAL | 9/29/2016 | | 10/3/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/29/2016 | | 9/29/2016 | | PASS |
Nicolette Womack
|
|
|
Eaves cannot encroach more than 2' into setbacks. Spoke over phone, adjustments will be made.
|
Routing - Addressing | 9/29/2016 | | 9/29/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 9/29/2016 | | 9/29/2016 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/29/2016 | | DONE |
|
|
|
|
Intake Approval | | | 9/29/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/29/2016 | | DONE |
|
|
|
|
Application received | | | 9/23/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 23 2016 2:55PM
|