Permanent Occupancy | | | 10/6/2017 | | DONE |
|
|
|
|
BLD-Final | 10/5/2017 | 10/5/2017 | 10/5/2017 | P | PASS |
Jim Storey
|
|
|
Abbey Phone #: ###-####
|
BLD-Final | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | NR |
Jim Storey
|
|
|
Jim Phone #: ###-#### no card and plans on site
|
BLD-Aging Inspection | 4/19/2017 | 4/19/2017 | 4/20/2017 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 4/18/2017 | 4/18/2017 | 4/20/2017 | | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 12/2/2016 | 12/5/2016 | 12/5/2016 | A | PASS |
Jim Page
|
|
|
No fire alarms, no fire sprinklers, fire extinguishers are in common area's with current inspection tags, noted that the door hardware on east door will have to be changed, door hardware is keyed type and will need to be changed to a pass through function (door is the designated exit from space) Final life fire safety inspection passed/complete.
|
Print Occupancy Form | | | 11/15/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/15/2016 | | DONE |
|
|
|
|
Routing PW Sewer Rating | 10/25/2016 | | 10/26/2016 | | PASS |
Rachael Beierle
|
|
|
Janitor's closet converted to a restroom
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/26/2016 | | DONE |
|
|
|
ALL MET ***We still need the ACHD letter and/or fees-all other requirements have been met 11-10-16 CAN***Need GC Form and Revised Cert of Value-business owner came in and was told they need the parcel owner to fill out the GC form and rev cert of val-i asked them to please have the parcel owner verify that he/she is the business name in GIS
|
Plan assigned to (CJW) | 10/3/2016 | | 10/26/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) (Oct 21 - 15 days) dawson taylor
|
Plan resubmittals received | | | 10/25/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/25/2016 | | 10/25/2016 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
1st review completed | | | 10/21/2016 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/21/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/3/2016 | | 10/21/2016 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - PUBLIC WORKS | 10/3/2016 | | 10/4/2016 | | PASS |
Morgan Webb
|
|
|
|
Routing - FIRE | 10/3/2016 | 10/3/2016 | 10/3/2016 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Routing - Addressing | 10/3/2016 | | 10/3/2016 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 10/3/2016 | | PASS |
David Ferguson
|
|
|
|
Intake Approval | | | 9/28/2016 | | FAIL |
David Ferguson
|
|
|
Major TI not a minor due to change of use. Need restroom evaluation and CDHD approval.
|
Application received | | | 9/27/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2016 2:47PM
|