BLD-Final | 5/16/2017 | 5/16/2017 | 5/16/2017 | A | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PASS |
Jim Sly
|
|
|
Jason Phone #: ###-####
|
DOC - Permit Finaled | 5/16/2017 | 5/16/2017 | 5/16/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Footing | 3/20/2017 | 3/23/2017 | 3/23/2017 | P | PASS |
Jim Sly
|
|
|
Steve Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/17/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/16/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 11/16/2016 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 10/3/2016 | 10/3/2016 | 11/8/2016 | | DONE |
David Ferguson
|
|
|
due 10/14 - failed plan review - need #310 form statement of special inspection - plan review passed, still failed by planning 10/31/16
|
Routing - PLANNING | 10/3/2016 | | 11/8/2016 | | PASS |
Brent Moore
|
|
|
|
Routing - PLAN CHECK | 11/8/2016 | | 11/8/2016 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/31/2016 | | 10/31/2016 | | FAIL |
David Ferguson
|
|
|
|
1st review completed | | | 10/10/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 10/3/2016 | | 10/10/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - Erosion and Sediment | 10/3/2016 | | 10/4/2016 | | PASS |
Andy J. Long
|
|
|
General ESC permit issued.
|
Intake Approval | | | 10/3/2016 | | FAIL |
Christina Prado
|
|
|
Need engineering
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/3/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/3/2016 | | DONE |
|
|
|
|
Application received | | | 9/28/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 28 2016 10:49AM
|
First Notice | 5/16/2017 | 5/16/2017 | | | |
Jim Sly
|
|
|
|
First Notice | 5/16/2017 | 5/16/2017 | | | |
Jim Sly
|
|
|
|