Print Statement | | | 12/5/2016 | | DONE |
|
|
|
|
First Notice | 10/18/2016 | 10/18/2016 | 11/15/2016 | | DONE |
Jim Sly
|
|
|
Mailed 11-15-16
|
BLD-Final | 10/17/2016 | 10/18/2016 | 10/18/2016 | A | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
DOC - Permit Finaled | 10/18/2016 | 10/18/2016 | 10/18/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Footing | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Jim Sly
|
|
|
Ben Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/10/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/7/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/7/2016 | | DONE |
|
|
|
need GC form
|
Telephone call | | | 10/7/2016 | | DONE |
|
|
|
called Shadeworks- told Jenna that permit is ready and fees due
|
Plan assigned to (JG) | 10/3/2016 | 10/3/2016 | 10/6/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, patio cover
|
Plan Reviewer's activity | | | 10/6/2016 | | DONE |
Javier Guzman
|
|
|
Jason Blais was Okay to accept on this project the palns as is on 8.5' x 11" sheets
|
Routing - PLAN CHECK | 10/6/2016 | | 10/6/2016 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 10/6/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2016 | | DONE |
|
|
|
|
Routing - Design Review | 10/3/2016 | | 10/6/2016 | | PASS |
Katelyn Menuge
|
|
|
|
1st review completed | | | 10/3/2016 | | FAIL |
Javier Guzman
|
|
|
spoke to adele and the sheets are required to be 18"x24" min. But he stated he spoke to her and they were OK with the sheets being 8.5" x 11" so i took them in since i could nor verify with adele since she was at a meeting
|
Plan Reviewer's activity | | | 10/3/2016 | | DONE |
Javier Guzman
|
|
|
spoke to adele and the sheets are required to be 18"x24" min. But he stated he spoke to her and they were OK with the sheets being 8.5" x 11" so i took them in since i could nor verify with adele since she was at a meeting
|
Routing - PLAN CHECK | | | 10/3/2016 | | FAIL |
Javier Guzman
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/3/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/3/2016 | | DONE |
|
|
|
|
Application received | | 9/29/2016 | | | |
|
|
|
|