BLD-Final | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | DONE |
Tony Young
|
|
|
Bill Phone #: ###-####
|
DOC - Permit Finaled | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/9/2018 | 5/11/2018 | 5/11/2018 | A | NR |
Tony Young
|
|
|
Bill Phone #: ###-####-please call with an approx meet time
|
BLD-Aging Inspection | 6/1/2017 | 6/1/2017 | 6/5/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 5/31/2017 | 5/31/2017 | 6/5/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 1/13/2017 | 1/17/2017 | 1/17/2017 | A | PASS |
Tony Young
|
|
|
Bill; Phone #: ###-####,, ele sticker on site
|
BLD-Framing/Rough-in | 12/20/2016 | 12/23/2016 | 12/23/2016 | A | PART |
Tony Young
|
|
|
Call half hour before // Bill Phone #: ###-####,, exterior shear ok
|
BLD-Foundation | 12/14/2016 | 12/15/2016 | 12/15/2016 | A | PART |
Tony Young
|
|
|
Bill Phone #: ###-####,, ftgs below slab
|
BLD-Foundation | 12/2/2016 | 12/5/2016 | 12/5/2016 | A | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Tony Young
|
|
|
Bill Phone #: ###-####,, garage addition footings ok
|
PubWorks Subgrade Approval | 12/2/2016 | 12/2/2016 | 12/2/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 11/29/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/22/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 10/14/2016 | 10/14/2016 | 11/22/2016 | | DONE |
Brian McGowan
|
|
|
Faile, need WUI and Engineering
|
Case Summary (BLD) | | | 11/22/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 11/22/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/22/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/22/2016 | | DONE |
|
|
|
All Met
|
Telephone call | | | 11/22/2016 | | DONE |
|
|
|
Spoke with Bill informing him this permit is ready and the fee amount due for issuance
|
Routing - PLAN CHECK | 11/21/2016 | | 11/22/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing PW Grading-Hillside | 11/18/2016 | | 11/21/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Plan resubmittals received | | | 11/18/2016 | | DONE |
|
|
|
received (2) revisions of site plan
|
Routing - PLANNING | 11/18/2016 | | 11/18/2016 | | PASS |
Colleen T Carroll
|
|
|
|
Plan resubmittals received | | | 11/15/2016 | | DONE |
|
|
|
Three copies of sheets 1 floor plan and 2 roof. Taken to Brian Mc
|
Routing - PLAN CHECK | 11/18/2016 | | 11/13/2016 | | FAIL |
Brian McGowan
|
|
|
Need revised Site Plan
|
Plan resubmittals received | | | 11/10/2016 | | DONE |
|
|
|
Two copies of sheets 1, floor plan and 2, roof. taken to Brian Mc
|
Routing - Erosion and Sediment | 10/3/2016 | | 10/18/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Homeowner RP.
|
Routing - PLAN CHECK | 10/14/2016 | | 10/17/2016 | | FAIL |
Brian McGowan
|
|
|
WUI details needed. Foundation plan must be stamped and signed. Wall bracing does not meet requirements.
|
Routing Walk-In (Zoning) | 10/3/2016 | 10/3/2016 | 10/3/2016 | A | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (PW Hillside) | 10/3/2016 | 10/3/2016 | 10/3/2016 | A | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (BLD) | 10/3/2016 | 10/3/2016 | 10/3/2016 | A | FAIL |
Brian McGowan
|
|
|
Foundation needs signed and stamped plan and calculations
|
1st review completed | | | 10/3/2016 | | FAIL |
Brian McGowan
|
|
|
Need WUI Details, foundation must have calculations, foundation plan must be stamped and signed.
|
Application received | | 10/3/2016 | | | |
|
|
|
|