Print Statement | | | 12/5/2016 | | DONE |
|
|
|
|
Telephone call | | | 12/1/2016 | | DONE |
|
|
|
Left a message for Sean to ask him about the values for both building and electrical. BLD given was 1,500 and ELE was 250 but the final value sent in stated BLD is 145,080(?) and ELE is 4,211
|
First Notice | | 11/7/2016 | 11/15/2016 | | DONE |
|
|
|
Mailed 11-16-16
|
Permanent Occupancy | | | 10/28/2016 | | DONE |
|
|
|
|
BLD-Final | 10/26/2016 | 10/27/2016 | 10/27/2016 | P | PASS |
Jim Storey
|
|
|
would like call ahead; Justin Phone #: ###-####
|
FIRE-Final Inspection | 10/26/2016 | 10/27/2016 | 10/27/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags, multiple doors had surface mount slide bolt locks in place, all slide bolt locks were removed at time of inspection, noted that some of the existing exterior doors have round type door hardware, advised point of contact, Justin (phone number ###-####) that round type door hardware may need to be replaced for final building inspection. Final life fire safety inspection passed/complete.
|
Issue PAID IN FULL permit | | | 10/24/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/10/2016 | 10/10/2016 | 10/21/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, Best Drive
|
Routing - PLAN CHECK | 10/19/2016 | | 10/21/2016 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 10/21/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/21/2016 | | DONE |
|
|
|
**MET 10-24-16** Need GC Form and Revised Cert of Value
|
Print Occupancy Form | | | 10/21/2016 | | DONE |
|
|
|
|
Telephone call | | | 10/21/2016 | | DONE |
|
|
|
called Ed to let know permit is ready and that we need the gc and rev cert of val
|
Routing - FIRE | 10/19/2016 | 10/19/2016 | 10/19/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing - FIRE | 10/11/2016 | 10/11/2016 | 10/13/2016 | | FAIL |
Katie Marron
|
|
|
Report attached to plans.
|
1st review completed | | | 10/13/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 10/10/2016 | | 10/10/2016 | | FAIL |
Javier Guzman
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/10/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/10/2016 | | PASS |
Javier Guzman
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/10/2016 | | DONE |
|
|
|
|
Application received | | 10/10/2016 | | | |
|
|
|
|