Letter of compliance/Occupancy | | | 4/30/2018 | | DONE |
|
|
|
|
BLD-Final | 11/8/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Tony Young
|
|
|
Homeowners are currently living in the residence so please call me for a time we can meet at the property. Thanks Bryan ###-#### Phone #: ###-#### Inspection requested via web by Bryan Mogel
|
DOC - Permit Finaled | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Tony Young
|
|
|
c of o issued
|
PubWorks Occupancy Approval | 10/27/2017 | 10/27/2017 | 10/27/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Other | 9/1/2017 | 9/5/2017 | 9/7/2017 | A | PASS |
Dave Hannah
|
|
|
Brian-sheet rock in soffits Phone #: ###-####
|
BLD-Energy code compliance | 8/10/2017 | 8/11/2017 | 8/11/2017 | A | PASS |
Tony Young
|
|
|
Please call Brent with Marv''s at ###-#### with any questions on Insulation. Thanks Phone #: ###-#### Inspection requested via web by Bryan Mogel
|
BLD-Framing/Rough-in | 8/8/2017 | 8/8/2017 | 8/9/2017 | P | PART |
Tony Young
|
|
|
Please call James at 208.899.0640 when headed to the project so he can meet you there. Thanks Phone #: ###-#### Inspection requested via web by Bryan Mogel
|
BLD-Framing/Rough-in | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PART |
Tony Young
|
|
|
Please call James at 208.899.0640 when headed to the project so he can meet you there. Thanks Phone #: ###-#### Inspection requested via web by Bryan Mogel,, need point loads, straps, fire blocking, interior shear,, verify tempered glass at final,, ok to insulate
|
BLD-Wall Bracing | 7/5/2017 | 7/6/2017 | 7/6/2017 | P | PASS |
Jim Storey
|
|
|
Plans are located in black tube in the garage. Looking for shear and bracing inspection. thanks Phone #: ###-#### Inspection requested via web by Bryan Mogel walls ok/ pool ok pending ele
|
Routing PW Grading-Hillside | 6/28/2017 | | 6/28/2017 | | PASS |
Jason C. Taylor
|
|
|
Approved re-submittals for grading plans with addition of pool. JCT
|
Plan resubmittals received | | | 6/28/2017 | | DONE |
|
|
|
three copies of revised grading plan which includes pool on plan
|
Telephone call | | | 6/28/2017 | | DONE |
|
|
|
called Bryan Mogel and told him revised grading plan approved by Jason Taylor, needs to come pick up copy of approved plan to put with site set. One copy put with records set. No fee due
|
BLD-Foundation | 5/3/2017 | 5/4/2017 | 5/4/2017 | A | PART |
Tony Young
|
|
|
Jack Phone #: ###-####,, work in progress
|
BLD-Foundation | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PART |
Tony Young
|
|
|
Jack Phone #: ###-####,, work in progress
|
BLD-Foundation | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | PART |
Tony Young
|
|
|
Jack Phone #: ###-####... work in progress.. ok
|
BLD-Foundation | 4/14/2017 | 4/17/2017 | 4/17/2017 | A | PART |
Brandon Shaw
|
|
|
Jack Phone #: ###-#### Ok to pour thru south retaining wall. Call for inspection on addition to toe in south retaining
|
BLD-Foundation | 4/13/2017 | 4/14/2017 | 4/14/2017 | P | NR |
Tony Young
|
|
|
Jack Phone #: ###-####,, too much rain
|
BLD-Foundation | 3/13/2017 | 3/14/2017 | 3/14/2017 | P | PART |
Dave Hannah
|
|
|
Jack Phone #: ###-#### north retainning wall ok to place concrete
|
BLD-Footing | 2/24/2017 | 2/27/2017 | 2/27/2017 | A | PEND |
Mike Jordan
|
|
|
Jack Phone #: ###-####. Needs soils report. Footings inspected by #415.
|
BLD-Footing | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | PEND |
Tony Young
|
|
|
Jack Phone #: ###-####
|
BLD-Footing | 2/22/2017 | 2/23/2017 | 2/23/2017 | P | PEND |
Tony Young
|
|
|
Jack Phone #: ###-####,, needs soils approval 1st
|
BLD-Footing | 2/22/2017 | 2/22/2017 | 2/22/2017 | P | PEND |
Tony Young
|
|
|
Jack Phone #: ###-####
|
BLD-Footing | 2/21/2017 | 2/22/2017 | 2/22/2017 | A | PEND |
Tony Young
|
|
|
Jack Phone #: ###-####,, need soils report,, received letter from engineer for ok as built on rebar and forms
|
BLD-Foundation | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | NR |
Tony Young
|
|
|
Jack Phone #: ###-####,, needs hillside soils report 1st
|
CHANGE STATUS TO (ISS) | | | 2/17/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/7/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 12/6/2016 | | |
|
|
|
|
Telephone call | | | 12/6/2016 | | DONE |
|
|
|
called Bryan to let know permit is ready and how much is owed-left message on his phone
|
Plan assigned to (LEG) Tisha | 11/16/2016 | | 12/6/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 11/29; L2 hillside; plancheck & fire
|
Routing - PLAN CHECK | 11/30/2016 | | 12/6/2016 | | PASS |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 12/6/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/6/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/5/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/5/2016 | | |
|
|
|
|
Routing - FIRE | 11/29/2016 | 11/29/2016 | 11/30/2016 | | PASS |
Katie Marron
|
|
|
revised report attached to plans.
|
Plan resubmittals received | | | 11/30/2016 | | DONE |
|
|
|
received resubmittals required for review
|
Routing - PLAN CHECK | 11/22/2016 | | 11/29/2016 | | FAIL |
Tisha Gallop
|
|
|
e-mailed comments to applicant
|
Plan resubmittals received | | | 11/28/2016 | | DONE |
|
|
|
Two copies of sheets L1.00, L1.01, L1.02 and L1.03. Taken to Tisha
|
Routing - MECHANICAL | 11/23/2016 | | 11/23/2016 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - FIRE | 11/23/2016 | | 11/23/2016 | | FAIL |
Katie Marron
|
|
|
Report sent to applicant and attached to case.
|
Routing PW Grading-Hillside | 11/17/2016 | | 11/22/2016 | | PASS |
Jason C. Taylor
|
|
|
Final Inspection will be needed on this project. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Plan resubmittals received | | | 11/17/2016 | | DONE |
|
|
|
received two copies of sheets M1.0, M2.0, and M3.0- gave to Tisha
|
Routing - PLANNING | 11/16/2016 | | 11/17/2016 | | PASS |
Jeff Lowe
|
|
|
|
Application received | | 10/11/2016 | 10/11/2016 | | DONE |
Rita DeYoung
|
|
|
|
Routing Walk-In (Zoning) | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | FAIL |
Jeff Lowe
|
|
|
applicant should combine parcels to satisfy WUI, retaining walls crossing property lines, and rear yard setbacks.
|
1st review completed | | | 10/11/2016 | | FAIL |
|
|
|
failed planning, no contact with building dept
|