BLD-Final | 7/31/2017 | 7/31/2017 | 8/4/2017 | P | PEND |
Dave Hannah
|
|
|
ok after ti finals
|
BLD-Wall cover | 3/2/2017 | 3/3/2017 | 3/3/2017 | A | PASS |
Dave Hannah
|
|
|
This is to cover some of the walls and hard lid, phase 1 cover. Please call with an approximate meet time so I can be sure and be there. Thanks Dave. Phone #: ###-#### Inspection requested via web by Tim Bergey
|
FIRE-Conference | 2/14/2017 | 2/15/2017 | 2/15/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete
|
Plan assigned to (AJS) | 12/13/2016 | 12/13/2016 | 1/3/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
White Dog Brewing
|
Routing PW Environmental | 12/13/2016 | | 1/3/2017 | | PASS |
Rick Christenson
|
|
|
On-site inspection to review future Pretreatment needs.
|
1st review completed | | | 1/3/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/3/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/3/2017 | | DONE |
|
|
|
**MET** Needs; GC Form & Revised Cert of Value
|
Issue PAID IN FULL permit | | | 1/3/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/3/2017 | | DONE |
|
|
|
|
Routing PW Sewer Rating | 12/13/2016 | | 12/30/2016 | | PASS |
Beverly Mountain
|
|
|
signed off in e plan
|
Routing - PLAN CHECK | 12/13/2016 | | 12/30/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 12/13/2016 | 12/13/2016 | 12/15/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Addressing | 12/13/2016 | | 12/13/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/13/2016 | | 12/13/2016 | | PASS |
Morgan Webb
|
|
|
ROUTED ONLY
|
Routing - Design Review | 12/13/2016 | | 12/13/2016 | | PASS |
Katelyn Menuge
|
|
|
CZC16-00290
|
Intake Approval | | | 12/13/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 11/21/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
11-21-16 Please see check list for missing information needed for submittal.
|
Intake Approval | | | 10/18/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
This project is a Major TI. Please complete the Major TI check list, form 520. We need all of the documents required by this check list.
All drawings need to be stamped by a licensed architect.
|
Application received | | | 10/17/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2016 8:36AM
|