Third Notice | | 4/16/2017 | 5/10/2017 | | DONE |
|
|
|
Mailed 5-11
|
Second Notice | | 3/3/2017 | 4/11/2017 | | DONE |
|
|
|
Mailed 4-12-17
|
First Notice | | 1/14/2017 | 2/21/2017 | | DONE |
|
|
|
Mailed 2-22-17
|
Print Occupancy Form | | | 1/4/2017 | | DONE |
|
|
|
|
Telephone call | | | 1/4/2017 | | DONE |
|
|
|
aws per Jim Page ok to change partial to pass since this permit is for the office only-a seperate permit will be needed for the warehouse. Talked to John to let him know I can't get the C of O ready because there is no mechanical permit for the mechanical partion-left message on his phone
|
Permanent Occupancy | | | 1/4/2017 | | DONE |
|
|
|
|
BLD-Final | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PASS |
Dave Hannah
|
|
|
call ahead for access; john Phone #: ###-####-1-7-14 as per Dave Hannah no mechanical permit needed CAN
|
FIRE-Final Inspection | 12/6/2016 | 12/6/2016 | 12/6/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher is in place with a current inspection tag, previously noted items have been repaired. Final life fire safety inspection for phase one passed/complete (Office area only, phase 2 is warehouse which was not inspected today)
|
BLD-Final | 12/2/2016 | 12/6/2016 | 12/6/2016 | P | CANC |
Dave Hannah
|
|
|
Please call ahead for access - John Phone #: ###-####
|
FIRE-Final Inspection | 12/2/2016 | 12/5/2016 | 12/5/2016 | P | FAIL |
Jim Page
|
|
|
Emergency egress discharge landing lighting is not installed, exterior light needs to be installed per approved plans and connected to emergency power source. Fire extinguisher needs a current inspection tag, inspection tag on fire extinguisher expired in 2011.
|
Issue PAID IN FULL permit | | | 10/27/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/27/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/18/2016 | 10/18/2016 | 10/26/2016 | | PASS |
Javier Guzman
|
|
|
10/31 L2 LONECONE.com T.I. Phase-I
|
Routing - PLAN CHECK | 10/18/2016 | | 10/26/2016 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 10/26/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/26/2016 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Routing - FIRE | 10/18/2016 | 10/18/2016 | 10/18/2016 | | PASS |
Katie Marron
|
|
|
Basic Life Safety requirements. No comments attached.
|
Intake Approval | | | 10/18/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 10/18/2016 | | 10/18/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2016 | | 10/18/2016 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 10/17/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2016 9:24AM
|