BLD-Final | 4/28/2017 | 5/1/2017 | 5/1/2017 | A | PASS |
Jim Storey
|
|
|
Chris Phone #: ###-####
|
DOC - Permit Finaled | 5/1/2017 | 5/1/2017 | 5/1/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 2/21/2017 | 2/22/2017 | 2/22/2017 | A | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Conference | 2/21/2017 | 2/21/2017 | 2/21/2017 | P | DEFR |
Tony Young
|
|
|
Chris Phone #: ###-####, out of time,, called and told them they could start sheet rocking ceiling
|
BLD-Framing/Rough-in | 2/15/2017 | 2/16/2017 | 2/16/2017 | A | PASS |
Jim Storey
|
|
|
After 8:30, please - Chris Phone #: ###-####
|
Routing - MECHANICAL | 12/16/2016 | | 12/16/2016 | | PASS |
Chad Schwendiman
|
|
|
|
BLD-Framing/Rough-in | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PART |
Jim Storey
|
|
|
Chris Phone #: ###-#### need trades
|
BLD-Wall Bracing | 11/21/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Jim Storey
|
|
|
Travis Phone #: ###-####
|
BLD-Footing | 10/26/2016 | 10/27/2016 | 10/27/2016 | A | PASS |
Jim Storey
|
|
|
Phillip Phone #: ###-####
|
OVERRIDE | | | 10/18/2016 | | |
|
|
|
|
Routing Walk-In (Zoning) | 10/18/2016 | 10/18/2016 | 10/18/2016 | A | PASS |
Josh Wilson
|
|
|
OK per DRH16-00458
|
Routing Walk-In (BLD) | 10/18/2016 | 10/18/2016 | 10/18/2016 | A | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 10/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 10/18/2016 | | 10/18/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 10/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 10/18/2016 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 10/18/2016 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 10/17/2016 | 10/17/2016 | 10/17/2016 | P | FAIL |
Josh Wilson
|
|
|
Requires design review approval.
|
Application received | | 10/17/2016 | | | |
|
|
|
|