BLD-Final | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PASS |
Jim Storey
|
|
|
Garage code 1905 Phone #: ###-#### Inspection requested via web by bryan murdoch
|
DOC - Permit Finaled | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 12/26/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Jim Storey
|
|
|
Thanks Phone #: ###-#### Inspection requested via web by bryan murdoch
|
BLD-Framing/Rough-in | 12/22/2016 | 12/22/2016 | 12/22/2016 | P | PASS |
Jim Sly
|
|
|
Merry Christmas Phone #: ###-#### Inspection requested via web by bryan murdoch
|
Plan Modification Accepted | | | 12/20/2016 | | DONE |
|
|
|
Revised acca report
|
Routing - MECHANICAL | 12/20/2016 | | 12/20/2016 | | PASS |
Chad Schwendiman
|
|
|
Revised acca report
|
BLD-Wall Bracing | 12/14/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Jim Storey
|
|
|
Thanks Phone #: ###-#### Inspection requested via web by bryan murdoch
|
BLD-Foundation | 11/8/2016 | 11/9/2016 | 11/9/2016 | A | PASS |
Jim Storey
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 11/3/2016 | 11/7/2016 | 11/7/2016 | A | PASS |
Jim Storey
|
|
|
Eric ###-#### Phone #: ###-#### Inspection requested via web by bryan murdoch
|
OVERRIDE | | | 11/3/2016 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/3/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/3/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/3/2016 | | 11/3/2016 | | PASS |
Tisha Gallop
|
|
|
spoke to Josh Wilson/Design review regarding shortened eave lenght and eliminated one window on side of building. No modification to DR requried.
|
Inspection Record Card- Bld | | | 11/3/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/3/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/3/2016 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 10/19/2016 | | 11/3/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 11/1; plan check (eaves and wall bracing)
|
Plan resubmittals received | | | 11/2/2016 | | DONE |
|
|
|
resubmittals received 2 sets of sheets A-102 & A-103-took to Tisha
|
Routing - PLAN CHECK | 10/21/2016 | | 11/1/2016 | | FAIL |
Tisha Gallop
|
|
|
|
1st review completed | | | 11/1/2016 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 10/20/2016 | | 10/21/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/20/2016 | | 10/20/2016 | | PASS |
Andrea Tuning
|
|
|
DRH16-00374
|
Routing - PUBLIC WORKS | | | 10/20/2016 | | PASS |
|
|
|
|
Routing - Addressing | 10/19/2016 | | 10/19/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/19/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/19/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/19/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/18/2016 | | FAIL |
|
|
|
needs framing plan on one of the sets
|
Application received | | 10/18/2016 | | | |
|
|
|
|