BLD-Final | 6/13/2017 | 6/14/2017 | 6/14/2017 | P | PASS |
Jim Storey
|
|
|
Please call for access thanks Phone #: ###-#### Inspection requested via web by Matt Greenman
|
DOC - Permit Finaled | 6/14/2017 | 6/14/2017 | 6/14/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 6/12/2017 | 6/13/2017 | 6/13/2017 | P | CANC |
Jim Storey
|
|
|
Thank You Phone #: ###-#### >> Inspection requested via web by Matt Greenman Inspection cancelled from web by: Matt Greenman
|
BLD-Final | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | CANC |
Jim Storey
|
|
|
Thank you Phone #: ###-#### >> Inspection requested via web by Matt Greenman Inspection cancelled from web by: Matt Greenman
|
BLD-Wall cover | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PASS |
Jim Storey
|
|
|
Garage gyp soffit Phone #: ###-#### Inspection requested via web by Matt Greenman
|
BLD-Wall cover | 3/28/2017 | 3/29/2017 | 3/29/2017 | P | PART |
Dave Hannah
|
|
|
Soffit Gyp Phone #: ###-#### Inspection requested via web by Matt Greenman house soffits ok but still needs to do garages
|
BLD-Wall cover | 2/15/2017 | 2/16/2017 | 2/16/2017 | A | PASS |
Jim Storey
|
|
|
Thanks Phone #: ###-#### Inspection requested via web by Matt Greenman
|
BLD-Framing/Rough-in | 2/14/2017 | 2/15/2017 | 2/15/2017 | A | PASS |
Jim Storey
|
|
|
Please call for access. Thanks Phone #: ###-#### Inspection requested via web by Matt Greenman
|
Plan Modification Accepted | | | 1/27/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/27/2017 | | 1/27/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 1/19/2017 | 1/20/2017 | 1/20/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Matt Greenman
|
BLD-Wall cover | 1/13/2017 | 1/17/2017 | 1/17/2017 | A | NR |
Jim Sly
|
|
|
Thanks Phone #: ###-#### Inspection requested via web by Matt Greenman Talked to Matt. Too many components missing. Contractor to acertain that Bldg. is ready for inspection.
|
BLD-Footing | 12/2/2016 | 12/5/2016 | 12/5/2016 | A | PASS |
Jim Storey
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 11/21/2016 | 11/22/2016 | 11/22/2016 | A | PASS |
Jim Storey
|
|
|
chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/15/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 11/10/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 11/5/2016 | 11/5/2016 | 11/10/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 11/10/2016 | | DONE |
|
|
|
|
Telephone call | | | 11/10/2016 | | DONE |
|
|
|
called Matthew- told him permit is ready and fees due
|
1st review completed | | | 11/10/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 11/10/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/10/2016 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 11/8/2016 | | 11/10/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 10/31/2016 | | 11/8/2016 | | PASS |
Sarah Schafer
|
|
|
|
Routing - MECHANICAL | 11/8/2016 | | 11/8/2016 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 11/7/2016 | | 11/7/2016 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH16-00407
|
Plan assigned to (LEG) Tisha | 10/31/2016 | | 11/5/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - Addressing | 10/31/2016 | | 10/31/2016 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/31/2016 | | 10/31/2016 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/31/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/31/2016 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/31/2016 | | DONE |
|
|
|
|
Application received | | | 10/24/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2016 2:43PM
|