Second Notice | | 2/23/2017 | 3/9/2017 | | DONE |
|
|
|
put in mail 3-10-17
|
First Notice | | 1/22/2017 | 2/13/2017 | | DONE |
|
|
|
Mailed 2/14/17
|
Print Occupancy Form | | | 1/12/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/12/2017 | | DONE |
|
|
|
|
BLD-Final | 1/4/2017 | 1/5/2017 | 1/5/2017 | P | PASS |
Mike Jordan
|
|
|
Zack Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 1/4/2017 | 1/5/2017 | 1/5/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Ceiling Grid Inspection | 12/12/2016 | 12/12/2016 | 12/12/2016 | P | PASS |
Mike Jordan
|
|
|
Zack Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 | P | NR |
Mike Jordan
|
|
|
Zack Phone #: ###-####. Needs fire sprinkler rough in inspection first.
|
BLD-Framing/Rough-in | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Mike Jordan
|
|
|
Zack Phone #: ###-####. Interior steel stud framed walls for conferance room ok. no grid.
|
Issue PAID IN FULL permit | | | 11/18/2016 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/26/2016 | | 11/4/2016 | | PASS |
Carl Westfall
|
|
|
(Nov 2 - 7 days) paper plan
|
Routing - PLAN CHECK | 10/26/2016 | | 11/4/2016 | | PASS |
Carl Westfall
|
|
|
Review completed. Drawings approved.
|
1st review completed | | | 11/4/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/4/2016 | | DONE |
|
|
|
***MET 11-18-16 CAN***please see Candy has the form but is waiting for Nasser to contact her with info about the names on the form-NEED GC
|
Print Occupancy Form | | | 11/4/2016 | | DONE |
|
|
|
|
Telephone call | | | 11/4/2016 | | |
|
|
|
called Stanley- told him permit is ready and that we need GC form and certificate of value
|
Plans ACCEPTED BY PLAN TECH | | | 10/26/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/26/2016 | | PASS |
|
|
|
Carl Westfall approved the intake 10/25/2016 (see checklist) customer paid plan review fee on 10/26/2016
|
Recd Pcfee & Taken To Pln CK | | | 10/26/2016 | | DONE |
|
|
|
Carl Westfall approved the intake 10/25/2016 (see checklist) customer paid plan review fee on 10/26/2016
|
Application received | | 10/25/2016 | | | |
|
|
|
|