BLD-Final | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tracy Lee
|
BLD-Energy code compliance | 2/28/2017 | 3/3/2017 | 3/3/2017 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tracy Lee
|
BLD-Framing/Rough-in | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Jim Sly
|
|
|
Tracey Phone #: ###-####
|
BLD-Framing/Rough-in | 2/28/2017 | 3/1/2017 | 3/1/2017 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tracy Lee Need pressure test
|
BLD-Wall Bracing | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 1/27/2017 | 1/27/2017 | 1/27/2017 | P | PASS |
Jim Storey
|
|
|
Wall // Dane Phone #: ###-####
|
BLD-Footing | 1/23/2017 | 1/24/2017 | 1/24/2017 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 1/19/2017 | 1/20/2017 | 1/20/2017 | P | NR |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/13/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/13/2017 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 11/5/2016 | 11/5/2016 | 11/14/2016 | | DONE |
David Ferguson
|
|
|
due 11/14
|
1st review completed | | | 11/14/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/14/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - PLAN CHECK | 11/1/2016 | | 11/14/2016 | | PASS |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 11/1/2016 | | 11/5/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 11/1/2016 | | 11/3/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 11/1/2016 | | 11/1/2016 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 11/1/2016 | | 11/1/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 11/1/2016 | | 11/1/2016 | | PASS |
Nicolette Womack
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/1/2016 | | DONE |
|
|
|
|
Intake Approval | | | 11/1/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/1/2016 | | DONE |
|
|
|
|
Application received | | | 10/28/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 28 2016 9:50AM
|