Permit Information
Permit NumberBLD16-03998
StatusFinaled
Name FOOTHILL CONSTRUCTION
Site Address 1015 E SHAW MOUNTAIN RD
Project NameKelly Hall Duplex
Customer NumberCAA16-00172
ePlanReviewYes
Description
*ESC issue to be resolved prior to final* (1015 E. Shaw Mountain Rd/1012 E. Logan St.) Permit for the construction of a new three story 3,555 sq. ft. duplex. The front unit is approximately 2,187 sq. ft. with 3 bedrooms, 3 bathrooms, and a 729 sq. ft. garage. The rear unit is approximately 1,437 sq. ft. with 2 bedrooms, and 1.5 bathrooms. All work per the approved plans, and any notations. R-1C zoning and setbacks per planning. **DAF**

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/25/20194/25/20194/25/2019PPASS
DetailsDave Hannah
David Phone #: ###-####
DOC - Permit Finaled4/25/20194/25/20194/25/2019PPASS
DetailsDave Hannah
PubWorks Occupancy Approval4/22/20194/22/20194/22/2019 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Final4/3/20194/4/20194/4/2019ANR
DetailsDave Hannah
Dave Phone #: ###-####
BLD-Aging Inspection4/3/20194/3/20194/4/2019 PEND
DetailsDave Hannah
BLD-Aging Inspection4/4/20194/4/20194/4/2019 PEND
DetailsDave Hannah
OVERRIDE  2/14/2019  
OVERRIDE  2/14/2019  
Permit Ready to Issue  2/14/2019 DONE
plan mod approval
Inspection Record Card- Bld  2/14/2019 DONE
CHANGE STATUS TO (ISS)  2/14/2019 DONE
Plan assigned to (CDM)2/4/20192/4/20192/12/2019 PASS
DetailsCarl D Madsen
Plan assigned to (CDM)2/5/2019 2/12/2019 PASS
DetailsCarl D Madsen
Routing - PLANNING2/5/2019 2/12/2019 PASS
DetailsSusan Riggs
Retaining walls may not exced 3-feet within the front yard setback or vision triangle.
Routing - Erosion and Sediment2/5/2019 2/11/2019 PASS
DetailsAndy J. Long
No changes to ESC plans. Site permitted and inspected regularly.
Routing - PLAN CHECK2/5/2019 2/9/2019 PASS
DetailsCarl D Madsen
Routing PW Grading-Hillside2/5/2019 2/7/2019 PASS
DetailsMelissa Jannusch
Approved plan mod for driveway.A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Melissa Jannusch at ###-####
Plan Modification Accepted  2/4/2019 DONE
change location of retaining wall/grading and drainage. Change driveway.
BLD-Foundation11/20/201811/20/201811/20/2018PPASS
DetailsDave Hannah
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Footing11/14/201811/15/201811/15/2018APASS
DetailsDave Hannah
Call prior to going Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
PubWorks Subgrade Approval11/13/201811/13/201811/13/2018 DONE
DetailsMelissa Jannusch
RETAINING WALL.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

OVERRIDE  11/8/2018  
Reopen Permit (ISS)  11/8/2018 DONE
Permit Ready to Issue  11/8/2018 DONE
Plan assigned to (CDM)8/28/20188/28/201811/5/2018 PASS
DetailsCarl D Madsen
Plan Mod- Duplex
Routing PW Grading-Hillside11/5/2018 11/5/2018 PASS
DetailsMelissa Jannusch
PLAN MOD FOR CHANGING RETAINING WALL FROM ROCK TO CONCRETE APPROVED. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.



All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call ###-#### for an inspection.

Routing - PLAN CHECK9/11/2018 10/5/2018 PASS
DetailsCarl D Madsen
Routing PW Grading-Hillside10/2/2018 10/2/2018 FAIL
DetailsMelissa Jannusch
see changemark in ePlan
Plan Modification Accepted  8/28/2018 DONE
crawl space: completeing plumbing
BLD-Other8/13/20188/14/20188/14/2018APASS
DetailsDave Hannah
fire sheetrock // Dave Phone #: ###-####
BLD-Energy code compliance8/6/20188/6/20188/6/2018PPASS
DetailsDave Hannah
Dave Phone #: ###-####
BLD-Framing/Rough-in7/25/20187/25/20187/26/2018PPASS
DetailsDave Hannah
Dave Phone #: ###-####
BLD-Framing/Rough-in7/20/20187/23/20187/23/2018APART
DetailsDave Hannah
David Phone #: ###-#### draft stop party and furred out walls drill hold downs ok to spray foam
Routing - MECHANICAL6/20/2018 6/20/2018 PASS
DetailsTroy James
Plan Modification Accepted  6/19/2018 DONE
new manual j report
Routing - MECHANICAL6/19/2018 6/19/2018 FAIL
DetailsTroy James
resubmitted manual j report
BLD-Wall Bracing5/22/20185/23/20185/23/2018APART
DetailsDave Hannah
Dave Phone #: ###-#### ok to cover third floor ext wall missing some fl/fl strapes and hold downs ok to set windows
BLD-Conference4/2/20184/3/20184/3/2018ADONE
DetailsDave Hannah
Dave-framing consult Phone #: ###-####
BLD-Foundation12/15/201712/15/201712/15/2017APASS
DetailsDave Hannah
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Footing11/20/201711/21/201711/21/2017APASS
DetailsDave Hannah
Early as possible - Wes Phone #: ###-####
PubWorks Subgrade Approval11/20/201711/20/201711/20/2017 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor 208 ###-####.
BLD-Footing11/15/201711/15/201711/16/2017PCANC
DetailsDave Hannah
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
Issue PAID IN FULL permit  8/30/2017 DONE
Inspection Record Card- Bld  8/30/2017 DONE
OVERRIDE  8/29/2017  
Plan assigned to (CDM)8/22/20178/22/20178/29/2017 PASS
DetailsCarl D Madsen
The plans have been approved with the conditions that the proposed retaining wall is not permitted to be constructed under this permit. It has been red lined from the approved plans. A certificate of occupancy will not be granted if any unapproved retaining walls/structures are constructed without the required permits.
Plan assigned to (CDM)6/2/20176/2/20178/29/2017 PASS
DetailsCarl D Madsen
2nd done Duplex
Routing - PUBLIC WORKS7/8/2017 8/29/2017 PASS
DetailsRachael Beierle
PLANS/APPL TAKEN TO FRONT DESK  8/29/2017 DONE
Permit Ready to Issue  8/29/2017 DONE
DetailsChristina Prado
All requirements met
Routing - PLAN CHECK8/26/2017 8/26/2017 PASS
DetailsCarl D Madsen
Routing PW Grading-Hillside8/22/2017 8/22/2017 PASS
DetailsMelissa Jannusch
The plans have been approved with the conditions that the proposed retaining wall is not permitted to be constructed under this permit. It has been red lined from the approved plans. A certificate of occupancy will not be granted if any unapproved retaining walls/structures are constructed without the required permits.

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

Routing - PLAN CHECK8/3/2017 8/12/2017 FAIL
DetailsCarl D Madsen
Failed pending hillside
Plan assigned to (DAF)11/22/201611/22/20168/8/2017 DEFR
DetailsDavid Ferguson
(1st done) due 12/09 - plan review failed - need details for fire rated walls - also failed fire and hillside.
Routing PW Grading-Hillside8/1/2017 8/1/2017 FAIL
DetailsJason C. Taylor
See changemarks from November JCT
Routing PW Grading-Hillside7/19/2017 7/19/2017 FAIL
DetailsJason C. Taylor
see changemarks from November. JCT
Routing - PLAN CHECK7/8/2017 7/8/2017 FAIL
DetailsCarl D Madsen
Failed pending public works
Routing - PLAN CHECK6/7/2017 6/7/2017 FAIL
DetailsCarl D Madsen
Routing PW Grading-Hillside6/2/2017 6/6/2017 FAIL
DetailsJason C. Taylor
See changemarks in ePlan. JCT ###-####
Routing - FIRE6/2/20176/2/20176/5/2017 PASS
DetailsKatie Marron
SFD to be fully fire sprinklered. A Fire Sprinkler Permit will be required.
Routing - MECHANICAL6/2/2017 6/5/2017 PASS
DetailsTroy James
Routing - PLAN CHECK6/2/2017 6/4/2017 FAIL
DetailsCarl D Madsen
Extend Review Timeline  5/10/2017 DONE
1st Approved 180 day extension per Adele
1st review completed  12/16/2016 FAIL
DetailsDavid Ferguson
Routing - PLAN CHECK11/22/2016 12/16/2016 FAIL
DetailsDavid Ferguson
Routing - PLANNING11/22/2016 12/2/2016 PASS
DetailsSusan Riggs
Routing - Addressing11/22/2016 11/28/2016 PASS
DetailsLaura Hunter
Added 1015 E Shaw Mountain Rd address for duplex
Routing PW Grading-Hillside11/22/2016 11/28/2016 FAIL
DetailsJason C. Taylor
See changemarks and notations in ePlan. JCT
Routing - MECHANICAL11/22/2016 11/23/2016 FAIL
DetailsTroy James
Emailed corrections to Greenworks LLC
Routing - FIRE11/22/201611/22/201611/22/2016 FAIL
DetailsKatie Marron
Report attached to case and emailed to applicant.
Routing - PUBLIC WORKS11/22/2016 11/22/2016 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment11/22/2016 11/22/2016 PASS
DetailsAndy J. Long
ESC plan approved. Valid PD and RP designated. BMP installation and site preparation inspection required prior to construction, call ###-#### or ###-####
Plans ACCEPTED BY PLAN TECH  11/22/2016 DONE
Intake Approval  11/22/2016 PASS
Recd Pcfee & Taken To Pln CK  11/22/2016 DONE
Plan assigned to (LEG) Tisha11/22/2016 11/22/2016 DEFR
DetailsTisha Gallop
Application received  10/31/2016 DONE
Application submitted via PDS Online on Oct 31 2016 4:01PM
Routing - PUBLIC WORKS7/20/2017    
DetailsRachael Beierle