First Notice | 2/14/2017 | 2/14/2017 | 3/16/2017 | | DONE |
Mike Jordan
|
|
|
This permit finaled on the web by Michele Rodgers
|
BLD-Final | 2/13/2017 | 2/14/2017 | 2/14/2017 | P | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####
|
DOC - Permit Finaled | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 2/13/2017 | 2/13/2017 | 2/13/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Footing | 1/12/2017 | 1/13/2017 | 1/13/2017 | P | PASS |
Mike Jordan
|
|
|
mike Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 1/12/2017 | | DONE |
|
|
|
fees were paid online
|
BLD-Framing/Rough-in | 1/4/2017 | 1/5/2017 | 1/5/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-####. Interior steel stud framed walls and hardlids for new restrooms. Pending elec. mech. and firesprinkler for hardlid.
|
Plan assigned to (JG) | 1/3/2017 | 1/3/2017 | 1/4/2017 | | PASS |
Javier Guzman
|
|
|
Albertson Plan Mod new restrooms
|
Routing - PLAN CHECK | 1/3/2017 | | 1/4/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 1/3/2017 | | 1/4/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/4/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/4/2017 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
Routing - Addressing | 1/3/2017 | | 1/3/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/3/2017 | | 1/3/2017 | | PASS |
Morgan Webb
|
|
|
PLAN MODIFICATIONS. ADDING 2 LAVS AND 2 W/C. WBSD
|
Plan Modification Accepted | | | 1/3/2017 | | DONE |
Christina Prado
|
|
|
Plan mod requested to add additional restrooms to floor plan
|
BLD-Framing/Rough-in | 12/27/2016 | 12/28/2016 | 12/28/2016 | A | NR |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Needs to resolve plumbing issues prior to framing inspections.
|
(F) Reprint permit | | | 12/27/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/27/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/19/2016 | 12/19/2016 | 12/21/2016 | | PASS |
Javier Guzman
|
|
|
Albertsons #154 Plan Mod
|
Routing - Design Review | 12/19/2016 | | 12/21/2016 | | PASS |
Josh Wilson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/21/2016 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD.
|
Routing - PLAN CHECK | 12/19/2016 | | 12/20/2016 | | PASS |
Javier Guzman
|
|
|
|
Plan Modification Accepted | | | 12/19/2016 | | DONE |
Christina Prado
|
|
|
Plan Mod accepted to remove existing canopy on north elevation and add new trellis
|
BLD-Framing/Rough-in | 12/15/2016 | 12/16/2016 | 12/16/2016 | A | PASS |
Mike Jordan
|
|
|
mike Phone #: ###-####. Iterior steel stud framed walls for pharmacy consult and new demissing wall for back of house.
|
BLD-Framing/Rough-in | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Interior steel stud half walls for floral work center ok.
|
Issue PAID IN FULL permit | | | 11/15/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/15/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/14/2016 | | DONE |
|
|
|
***ALL MET*** Need GC Form and Revised Cert of Value
|
Plan assigned to (JG) | 11/3/2016 | 11/3/2016 | 11/12/2016 | | PASS |
Javier Guzman
|
|
|
11/16 L2 Albertsons ePlan
|
Routing - PLAN CHECK | 11/3/2016 | | 11/12/2016 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 11/12/2016 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2016 | | DONE |
|
|
|
|
Routing - PLUMBING | 11/3/2016 | | 11/8/2016 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - FIRE | 11/3/2016 | 11/3/2016 | 11/4/2016 | | PASS |
Katie Marron
|
|
|
Creating two new rooms at pharmacy area and customer service along with other interior modifications. Separate Fire permits WILL BE REQUIRED. No comments attached.
|
Intake Approval | | | 11/3/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 11/3/2016 | | 11/3/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/3/2016 | | 11/3/2016 | | PASS |
Rachael Beierle
|
|
|
Contact West Boise Sewer District for permit.
|
Application received | | | 11/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 1 2016 2:59PM
|