Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD16-04022
StatusFinaled
Name STOR-MOR SYSTEMS
Site Address 614 E CURLING DR
Project NameLee Storage Shed
Customer Number 
ePlanReviewYes
Description
WUI Zone A; To build a 20X20 storage shed, with concrete retaining wall foundation per approved plans and engineering. Separate erosion permit is required.//leg *** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/13/20174/13/20174/13/2017PPASS
DetailsTony Young
Preston Phone #: ###-####
DOC - Permit Finaled4/13/20174/13/20174/13/2017PPASS
DetailsTony Young
BLD-Framing/Rough-in4/13/20174/13/20174/13/2017PPASS
DetailsTony Young
Preston Phone #: ###-####
BLD-Wall Bracing4/11/20174/11/20174/11/2017PPASS
DetailsTony Young
Preston Phone #: ###-####
BLD-Framing/Rough-in4/11/20174/11/20174/11/2017PPART
DetailsTony Young
Preston Phone #: ###-####,, soffit for WUI okay,, frame ok so far
BLD-Footing3/30/20173/31/20173/31/2017APASS
DetailsTony Young
Preston Phone #: ###-####
BLD-Footing3/30/20173/30/20173/30/2017PNR
DetailsTony Young
Preston Phone #: ###-####
BLD-Footing3/29/20173/30/20173/30/2017ANR
DetailsTony Young
Preston Phone #: ###-####
Routing PW Grading-Hillside3/30/2017 3/30/2017 PASS
DetailsJim Wyllie
Received letter fro geotechnical engineer approving footing subgrade. Okay to schedule a footing inspection.

Jim Wyllie / ###-####
BLD-Footing3/29/20173/29/20173/29/2017PNR
DetailsTony Young
Preston Phone #: ###-####
BLD-Footing3/28/20173/29/20173/29/2017ANR
DetailsTony Young
Preston Phone #: ###-####,, late am,, needs hillside soils approval,, should be ready this pm
BLD-Footing3/27/20173/28/20173/28/2017PNR
DetailsTony Young
Preston Phone #: ###-####
BLD-Footing3/24/20173/27/20173/27/2017PCANC
DetailsTony Young
Preston Phone #: ###-####
Issue PAID IN FULL permit  12/19/2016 DONE
OVERRIDE  12/13/2016  
Plan assigned to (LEG) Tisha11/7/2016 12/13/2016 DONE
DetailsTisha Gallop
1st review 11/14; planning (setback), hillside(cat II), plan check(eng. found details and tie in to existing wall)
Routing - PLAN CHECK12/13/2016 12/13/2016 PASS
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  12/13/2016 DONE
n/a energy, yes esc
Permit Ready to Issue  12/13/2016 DONE
need RP
Plan resubmittals received  12/12/2016 DONE
Plan resubmittals received  12/12/2016 DONE
Routing PW Grading-Hillside12/3/2016 12/7/2016 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Routing - PLANNING12/3/2016 12/6/2016 PASS
DetailsNicolette Womack
Plan resubmittals received  12/3/2016  
Routing - PLAN CHECK12/3/2016 12/3/2016 FAIL
DetailsTisha Gallop
still need eng. found details
Routing - PLAN CHECK11/7/2016 11/14/2016 FAIL
DetailsTisha Gallop
Routing PW Grading-Hillside11/7/2016 11/14/2016 FAIL
DetailsJason C. Taylor
per eplan, need cat II hillside approval
1st review completed  11/14/2016 FAIL
pending approval by planning, PW hillside, plan check
Routing - PLANNING11/7/2016 11/8/2016 FAIL
DetailsNicolette Womack
Must comply with setbacks on plat.
Routing - Erosion and Sediment11/7/2016 11/8/2016 PASS
DetailsAndy J. Long
ESC plan submitted and approved.
Plans ACCEPTED BY PLAN TECH  11/7/2016 DONE
Intake Approval  11/7/2016 PASS
Recd Pcfee & Taken To Pln CK  11/7/2016 DONE
Application received  11/2/2016 DONE
Application submitted via PDS Online on Nov 2 2016 10:16AM