First Notice | | 2/6/2017 | 1/30/2017 | | DONE |
|
|
|
This permit finaled on the web by Jim Calle
|
BLD-Final | 1/27/2017 | 1/27/2017 | 1/27/2017 | P | PASS |
Tony Young
|
|
|
ok for c of o
|
FIRE-Final Inspection | 1/26/2017 | 1/27/2017 | 1/27/2017 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 1/27/2017 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/26/2017 | | DONE |
|
|
|
Spoke with Jim Colley of Amazing Exteriors regarding a barrier placed in the rear warehouse, told him that the barrier needs to be removed or at min a 36” opening at the barrier is required for egress.
|
BLD-Final | 1/24/2017 | 1/25/2017 | 1/25/2017 | A | PART |
Tony Young
|
|
|
After 9 am, please Phone #: ###-#### Inspection requested via web by Jim Calle,, ok after f/l/s passes,, same issues
|
FIRE-Final Inspection | 1/24/2017 | 1/25/2017 | 1/25/2017 | A | FAIL |
Troy Cobbley
|
|
|
Provide address facing the street as discussed, repair the three exit sign/emergency lights as marked on the plans, discuss with plan review the barrier and lack of egress from the east end of the storage ared due to a barrier built that is not shown on the plans.
|
Print Occupancy Form | | | 1/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/6/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/6/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 11/4/2016 | 11/4/2016 | 12/29/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 11/23 L3 Amazing Exteriors E Plan
|
Routing - PLAN CHECK | 12/29/2016 | | 12/29/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/29/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/29/2016 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Routing - PLAN CHECK | 12/8/2016 | | 12/8/2016 | | FAIL |
Javier Guzman
|
|
|
4th submittal corrections not addressed architect refuses to clarify display space or make changes
|
Routing - PLAN CHECK | 12/6/2016 | | 12/6/2016 | | FAIL |
Javier Guzman
|
|
|
3rd submittal corrections not addressed architect refuses to clarify display space or make changes
|
Routing - PLAN CHECK | 12/5/2016 | | 12/5/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 11/4/2016 | | 11/16/2016 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 11/16/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 11/4/2016 | 11/4/2016 | 11/8/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Addressing | 11/4/2016 | | 11/7/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/4/2016 | | 11/4/2016 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 11/4/2016 | | PASS |
Carl D Madsen
|
|
|
|
Application received | | | 11/3/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 3 2016 2:34PM
|